8/17/26 - Ryan Ran the meeting, couldnt get the agenda up, lol, asked peyton to go over clashes, peyton said he wasn't ready, then Ryan did a round table, no body had anything to
8/24/26 - Didn't really go over anything, Ryan Warner, we ended early. Ryan Warner started a new meeting at 712am, he was late
Peyton showing MES MP Pipeing into duct and framing, mic didn't work so I couldn’t talk to verify MES Elevations
8/3/2026 - Abe said UCO3 UG Signoff is pushed to next week
Peyton going over clashes
#816 shows vesda FP content going through our bypass at hac, adam modeled the vesda
MH Duct at EMT1 was low, scott said he will take a look
8/10/2026 - Melanie says she will look at MES Alignment, I said on Saturday mes was mis-aligned again
Adam said he will fix Vesda Clash with HAC EOL Bypass
I said the MES Loop/ Flush Loop piping needs to be reconfigured, its clashing with TWMU Skid, the tee will get rolled to vertical and cantilever pipe supports will be brought in
8/31/26 - Abe says we need to have clashes cleared by sept 28th
sign off should be around that time
Tom was asking about workflow for clashes, reports. ALex Hubbard eluded to it saying it was more verbal, no reports
EMT1 is showing clash with UG FW Handle into wall and hitting TWMU Skid piping support, Also showing duplicates, worksets need turned off, EMT1 has misaligned piping
6/1/2026 - Noel Nunez says Alehandro Chew will be safety manager
Michael said he sent TXE3 embeds along with PDF dimension in mid April
Says we havent been funded for Region 2, he is sending out embeds as needed
Michael asked what the question was about RO and TW, I said it was going over how to connect to the RO skid, from DCW and to TW MES
Michael asked if MES Loops were completed, adam said yes, he created new BOMs
Michael said his goal is to get everything ordered
Doesn’t think TXE3 has been poured, think they are behind schedule
Michale Paul said they thought the walls weren't going to be in until they could do anchor
They said that was what was agreed to
6/8/2026 - Michael said they had a PM Coins Mandatory meeting and couldn't host the meeting
6/15/2026 - Chris Moss came on board from TSMC, Pipe fitter, GF
Jose Alejandro Chew, new Safety Manager for TXE
6/22/2026 - Shop drawings (Engineer Drawings) looking at submittal on Frid, 6/26
6/29/2026 - Keylan Cancelled
7/6/2026 - Carson will scan on Thursday
7/13/2026 - Scans on TXE10 complete, should have done this week, EOW
Jacob will be pulling field measurements of FW Stub ups
Adam will overlay scans to see how they match up with our Stub Ups
SOK will be starting next week, 27th will have more setup covered
7/16/2026 - Zach wants scanning sent back out, scan off control points, need to get CPs from Greg, put in model, talk to carson to see what they need from us
Control points were requested on 6/12 meeting with Greg H, it was stated they would be sent to Michal and James Homrighausen
I also asked for control points from Luke Justice on 5/21, he said he would get with Greg H.
They made it out like it was detailing fault they scanned without using control points
Paul asked how soon I can get the points into model, I said immediately, but Im not sure scanning needs anything from us, they may input control points into the rcap software maually but we will have it the model if they need it
7/27/2026 - Scanning this week
FTI Will be doing Trimble next week
8/3/2026 - Adam brought up new pipe supportts that were sent to Tom due to more access to mes loop valves
Adam asked about tapped caps for mes connections, michael said it was a miss on them so they will cover it
Trimble is shooting wall points tomorrow and Wednesday
8/10/2026 - Asked about txe2, keylan said they have bottom plate down, trimble is showing walls off
Asked about info for points from trimble, is this for field use only, are they showing HP where walls are off
Keylan says they are using the info to show HP were walls are off, TXE1 had walls off, HP is still working on solutions
I asked for TXE2 Cerris bypass schedule so we can get scanning out
He said he would get me that info
Need to ask about Access panels, whos providing?
Need to ask about info for HP saying they are having issues with control point discrepancies
FTI says Jennifer is gong to get involved and veriy, Meta says they will send their own Surveyors out to verify, this was last I heard
I will put together an email of who said what in which meeting and send to keylan to start a chain
Keylan said he will double shcek with paul and nate
Paul says he hasn't heard anything about control points, alec says HP is suggesting we move our anchors
8/17/2026 - Cancelled
8/24/26 - Jacob went through agenda. Boots on the ground "soon", they had exterior and interior walls up on TXE2, how do we not have boots on the ground now?
Nate is supposed to be trimbling the rest of TXE1, I didn't know TXE1 was even poured and ready
Keylan said he has to verify Control points. They were going to take it off agenda. I told them the medallions werent identified or center punched, Keylan told jacob he needs to get with Alec, I suggested filling out an issue on FTI site abou this, keylan agreed
7/27/2026 - Missed, went to Cameron Shop to meet Mid Atlantic Crew
8/17/2026 - Went over UG and sign off dates. EMT1 Sign off on hold due to CDD1 change, looking to still start coordinating knowing they will need to incorporate the changes after the fact
8/24/2026 - Going over drone shots, showing UG progress
8/31/26 - DPR Hosted continuation of the weekly HRV Mechanical Component call, for the discussion of project document contorl, high priorty issues/ Coordination topics, and quality items for MEP, FP, BMS Control scope.
Ashley shows a line item for FW supports at SOG, said she would rather handle that on a smaller group
9/7/26 - Labor Day
ARUP has not included the Access panels in the latest IFC set. Isabella informed Ashley that we have submitted them, we havent submitted dcb90 yet. We will bring up clash with cable tray in Wednesday detailing meeting
Isabella brought up flushing power requirements to make sure DPR was aware of skid locations and power requirements, seeing if DPR needed a side call, she asked if Isabella can forward information, it was said to tag anthony, curtis and ben for temp power
Doowoo with MCdean said he will forward chain to anthony and curtis
Ashley continued the FW UG Support discussion with CWC, ARUP, MCDean, DPR
Ashley would like to have follow up meeting with Arup and CWC having information about the thrust/movement at bypass.
Ashley said they will design slab to not allow movement in the stubups so MCDean and Southland do not have to redesign piping, pads will take care of growth and thrust. 9x9x3 piller with possible fittings that attach to pipe and transfer forces back to slab
Neema also brought up thrust from MES side, peter said they will be minimal
Tom brought up the bypass actually needing support, they asked if we have submittals on our veritical supports since we are drilling into concrete.
CWC is putting together information on supports at penetrations.
Neema with ARUP says they havent evaluated the displacements or forces at bypass and stubups so Peter ran designs to look at them. Neema talked about flexible connections. Peter says vertical pipe will have 6" exp at bypass, if restrained it will be 30k lbs
TOm chirdon chimed in talking about our anchors, Tom was asking who is resposible for the thrust coming from bypass.
Melanie Working through EMT Models, links needed repathed
Go Through EMT1 and EMT2 and make sure MES, TW and MP content are good
IF good, push to Revizto
Also check MSA/FSHAC Piping
EMT Does have IFC's for Base Build, Scott showed them yesteday, I coulda swore we didn't have any sheets, prob thinking of HRV
7/16/2026 - Melanie says our MP model doesn’t line up with Eng Model, we are using Lightning Shared Coordinates, Eng is using ETM100
Download arch model, link our models in and see who lines up
She says archs did change the g datum model a while back, she had to repath it and that’s when things stopped lining up correctly
Abe - Attached Sign off schedule to summary email, have content populated and coordinated ahead of signoff dates highlighted in RED, these dates line up with Mortenson
I told her our content, mes content lines up in revizto, if you change anything, it will no longer line up
7/17/2026 - Cancelled
7/20/2026 - Cancelled
7/22/2026 - Ryan says Mortenson is on the verge of issue stop work order with Meta due to electrical incompetetance
7/23/2026 - Cancelled
7/30/2026 - Cancelled
8/6/2026 - Adam said he will cover EMT, I will do the LEB Meeting
8/13/2026 - Cancelled
8/18/2026 - Missed, at EL PASO FOK/SOK
8/24/2026 - Went over WPI and hac frames, new DCIS about SKU Numbering, Updating the model to make sure its accurate.
9/1/26 - I told Abe I am aligning and cleaning up EMT1, will tell Nicole about a workset thats turned on showing duplicate bypasses.
9/1/26 - Arthur brought up flipping the leg on the MSA 180deg to clear the clash with the MES Anchor, we wouldn't have to move anything!
Use the MDI model for FSHAC steel, the ENG model is for design and doesn't show steel
Need to go through the excel report from Darren to clear and check clashes
Darren will clear the FCU clashes since they will only be 1/8" and get cleared
Isabella did find out cable trays will be installed before flush fill according to schedule, april of next year, just before our day 0, MCDean Darren said he will get with them also to make sure they dont impede in drive aisle
Adam brought up the Bypass clash with FCU and cable and having to rotate valves, Darren said if they are there for next clash report, he will flag them
9/8/26 - isabella brought up DPR saying they would take a look at the access panel clash with cable tray last week. Will bring it up in tomorrows meeting
isabella aslo brough up the sign off for FW UG locations, Darren agreed, Ben was planing on meeting with JEDUnn for a sign off process. She will bring it up tomorrow also
Darren asked about elevations of TW in fshac and supports not at proper height with clamp. Adam said take a look at dcb90, it looks better, it looks like the 2 buildings have different elevations. Darren said Jasmine will be looking into it
Darren said rotating the legs around has cleared a lot of clashes
Scott brought up zero coordination between lightning scope duct connecting to base build scope.
9/8/26 - This meeting is getting moved to Friday by TIA, still waiting on new invite
Tia/ Tom
Follow up on HAC Panel clashes with Patrick Brinnehal
Meeting to go over stratus and models with all PMs, Adam, Scott, Supers sometime next week, look at schedules
Chris Chase is the PM of EMT
5/26/2026 - Check if Adam got the 4" Welded Bypass to Shop, from 5/5/25 email in Inbox "Im shooting to have the LTG build out scope package done by end of week (For Review only not for construction). "
Need meeting to discuss, txe10 anchor clashing with interior of walls, adam sent info out about conflicting models, but as of today, there is still clashes
RFI says they are changing wall to Gypsm board and expanding toward corridor 2.5"
Verify what spools have been put on stratus for TIA/TOM Lightning huddle
6/2/2026 - We did get 2 more sites in Ohio
Adam said he will give link to CIAs, TXE3-12 and LEB3-12 not ready
Adam had meeting with HRV, told them to start using our coordination models for coordination
Quick hello, this is who we are meeting
with MC Dean
Mealnie says they will be updating projects to new architect model
SI will be integrator
Heath introduced Peyton Steveons as VDC supervisor
Starting with HRV
Type F - 4 buildings
Type G - 2 buildings
Melanie introduced Vasi, VDC specialist helping out ron and melanie
Tia went over deliverable schedules
She setup a break out meeting
Per site, per building
Adam said they are moving the walls away from anchors so we are clear
only 2 walls changed from IMP, 2 others are still IMP
Michael said Greg told him they are putting walls up next week
Adam said we are 1/2" clear from plate, it will be a field issue installing the plate
Michael said he will talk to paul, he doesn't know what to do, he will call greg
Told Tia I sent snip of Dog Leg Metraflex in chat, didn’t get any smiles
Let her know we have LEB complete, TXE10,1,2 is complete
6/9/2026 - Adam said they are going to move the MSA, HAC spools to the Lighting Program, for one source
Melanie and Keylan said it can be done
6/30/2026 - FTI wants scanners badged
Toms Eng review comments will be looking at doing updates next week
Michael said they have drug test this week, orientation on Monday
HRV Embed Dims, ryan says he has, I have Angle working on them now, wtf?!!!
PIQ, melanie is setting up, I asked her to keep an eye out for the BIM ex plan and contact list
TXE1 special Support approved
H Support hanger, supposed to get stamped this week
HRV supposed to get linked in models setup so we can coordinate ug
Need to verify LEB and TXE CIA points
SS Headers are in fab per EAN
John Rhee asked about Waldinger misaligned, we are now good, sending email showing HDR is off
7/7/2026 - Cancelled
7/14/2026 - Melanie is going through EMT with cupertino to verify alignment
Isabella asked about clashing HRV, Peyton will be running coordination model for HRV as well as EMT
HRV Embed sheets need to be sent to Basebuild, adam mentioned
Still waiting on word a
7/27/2026 - Adam said Zach gave him the low down on the CIA, it is not a contractual document, it was sebastian telling faith to do it
8/4/2026
8/11/2026 - Michael says all walls are off, asked me and adam to comment, I said get us the points, we can drop them in model, create a document to be used to create an issue and escalate it
HRV, MCD Dean working through hac and pipe clash
I brought up the control point issue at TXE
Metas involved with their surveyors according to Louis Saldana, FTI was supposed to verify with Jennifer
John Rhee says they will need to bring up the bypass support in their next meeting when Tia relayed toms concerened about it
LEB only wants 2 14" skids, need to update maps and bom
John verified there were 11 8" and 6" skids on the BOM package for LEB
He dropped Trimble information into chat
8/25/26 - I updated the Support on Basebuild bypass, said I emailed Trevor at Cerris, no responde
If tom wants more info, we may need to issue an RFI
9/1/26 - Michael was there. I gave a break down of what hensel phelps said in last meeting. They will adjust existing walls for anchors, adjust existing layout for anchors, create cut outs and leave outs for drilling and installing bolts
Michael said they have anchors being sent to site on 9/9 and will start drilling and installing
I gave a break down of the HRV HDPE stub ups, thickening of the slab and anchoring of the UG FW Stubups to compensate for the 6" expansion/ 30k Thrust issues from the HDPE, could affect all jobs
Adam brought up the note from TOm C about Diana re calcing the embeds and causing a change in layout
Phil said he will get with Diana, Michael at TXE said they are installing building 8 right now and looking at installing epoxy anchors in a few weeks.
Neema says stub ups need to be slurried, underground pipes need to be verified for undergound thrust and that passive soil will be sufficient
Above ground thrust will be satisfied by slurry and surrounding footers
Gave thrust block info
Carl and Seth are present from CWC
MC Dean Bridged files
Danton Wein with MC Dean
MDI has steel and skids, fabrication
ENG has electrical equipment
They both have all links turned on, these need turned off
mcd plan for trench moving, not relating to Southland
Southland
MP Model connections to FW UG Stub ups
Need CWC Bypass, will they be included in the CWC Model we already have or in a separate above ground model?
Ben verified the models are good
Ben then went to stub ups and neema took the convo to RFI something, I said we were going to take a first pass at matching CWC Stub ups
Neema was talking about some kind of trnech shit moving that didn’t apply
7/15/2026 - Adam CWC said no update on the bypass for CWC
7/22/2026 - Talked FWM and MCUP issues mainly
Eli from Colonial was present
Neema says they need to move FW Stup ups away from footer about 5"
This means CW Will need to move their stub ups to get out of way of footers
I mentioned they need to hit the critical North south dimension of 6'-1 5/8" to match the mes skid line, but we can match whatever movement they do east and west
Ben and Neema both pointed out CWC can rotate bypass valve to the front, one of the bypasses was already rotated this direction, CWC started to fight back a little bit
Danton affirmed that the 2 MDC ENG and MCD MDI Models are the current models for the FSHAC
Storefont issues
7/29/2026 - Ben gave dimesnions of shift in DCB2, around 4" toward wall, and will rotate valve
Ben said they are doing things in the field to make sure they hit the 6' - 1 5/8"
Once the shift is completed in DCB2, Ben will ping us
8/12/2026 - Architect asked about information for the Access panel layout, Ben let them know they have been distributed and they were on the email chain
Ben talked about scanning, I brought up us aligning to 3d scan after bypass installed and 3d scans complete
Isabella brought up Wall and anchor proximity, I told them what happened on another site, walls were put up, making it impossible to install anchors
Walls were floating all over the place and not accurate
Need to make sure the small distance between embed and wall is achieved
I told ben we were reconfiguring supports at MES loops so all the clashes with Valve handles will go away
I told team I had DCB90 aligned and published
8/19/2026 - Cancelled
8/26/26 - Cancelled
9/2/26 - Need to switch middle Supports to Cantilever
- Need to look at relocating Exp Tanks to clear fork lift and robotic paths
- Brought up the access panel clash with Cable tray at NWS CD, ben said they will look into it, do possible leave out if need be
- Ben asked about who is receiving embed deliveries, we are still in design stage for nws. Will southland have a representative? Isabella says dpr or concrete should receieve since they are installing. Ben asked for points to assist in install, adam said absolutely
- Isabella asked for verification of date of pour so we can make sure we get them delivered on time, she asked jackson for delivery date to make sure they aren't triple handling, he verified they will be receiving, SI needs to make sure they get packing slips
- Jackson verified february is looking like a good time line for embed delivery
9/8/26 - Get the MES verified, make sure its current, export it
Colonial web/ southland POC sign off procedure should be agreed on at the end of this week - ben will distribute at end of this week
Cantilever supports will not impact CWC stub up locations - Isabella explained this
Need to verify the 2'-8" space between TMU Skid and Bypass Valves is adequate and code compliant
No clearance dimension found in IMC, UMC, ASME B31.9 or ASHRAE, only adequate clearance for safe operation and maintanance.
No update from Adam Truslow from comfort systems usa for the supports of the bypasses
Look at adjusting the Expansion tank location to get out of the fork lift path
Scott asked where they were as far as signing off OH at Loop area for his duct connection to loop area base build, ben said they havent signed off yet and still dialing in sign off date. Concentrating more on corridor
ben asked if Dean or SI has a fork left path they can drop in for clearances, Darren Ballestros asked patrick if he can contact danton and get a model put together for this
Isabella says no changes so far with embed layout for anchors
Isabella brough up the cable tray and access panel location, she asked about dcb100 whats the solution, dcb90 is good, she says the layout sheets will live on DPR forma, once we are finalized they will be submitted.
Isabella says she will submit to DPR, ben showed an integrator submittal folder she can place them in
Access Panel for DCB90 still need to be provided to ARUP so they can capture them in the architectural IFC drawings, isabella brought it up, Ben said he will check it out
LEB10 FLEX HOSE on 8" Flush skid hitting column, need to clear clashes
talked about email I sent about a list of which models to use for which trades as far as Walls, Wall Panels, Electrical, Arch, Structural etc
Kyle said he was still working on that
John Cowhey is asking about Lugs on the MES
I will chase this down, find who responded Johns email and start there
Robert Cheek responded on Monday saying he would get the answer same day, still waiting
I told Jay we are currently working through shop drawings and spools, while we are doing those we are paying attention to clashes and working through the clashes
I Brought up the FW underground being off and that we will be scanning and verifying CIA POC's, Should be doing this within a week
LUKE SAID HE WILL DISCUSS IN HIS MEETING WITH MORTENSON
JAY ADDED THIS AS AN ACTION ITEM
EMMA SENT EMAIL REQUESTING CLARIFICATION, TRISTEN WAS CONFUSED
5/27/2026 - I BROUGHT UP LEB1 COORDINATING WITH CRIDER NO MODEL, USING HDR FOR UNDERGROUND COORDINATION
JAY BROUGHT UP TXE10 ANCHOR CLASH WITH WALL, ADAM SENT EMAIL ASKING ABOUT IT, SOMEONE SAID THEY WERE CHANGING WALL IN A EMAIL RESPONSE, ADAM REQUESTED MEETING, NO ONE RESPONDED
JAY ADDED THIS AS AN ACTION ITEM
6/3/2026 - New LEB Mech and Plumbing meeting on Wed, John and Reece involved, going over FW stub up locations and F/F water gallery connections
Informed John of Convos with Greg to coordinate wall install with coring of anchor plate holes
Told Jay/John, Lance Holmes is coordinating with other trades on fix for LEB UG FW stubups not hitting POC points or dimensions
6/10/2026 - Verify Span models work on LEB10, 1, 2
6/17/2026 - Checked LEB1, Span_SS model is still only showing Labeled grids, no steel in revit linked model, 2models, same dates, different version, latest verison wont load, gives error
Bring up Walbringer as new MP contractor on LEB6, sent email out with dimension sheets for someone to get them the information
Coordination Sign off
Jay gave links to Turner and HP sign off locations
Clash Review
Jay said he will go through and filter out white noise, setup a meeting to over others. I told him whenever he wants and I will be there
Friday 6/19/22 9am
6/24/2026 - Check with Adam if he verified the lastest info from Crider lining up ug, LEB10
Check LEB1 model HDR Underground lining up with Model, We are lined up with HELM Bypass on LEB10
Luke will get with LEB and Turner for Verifying CIA Points
Louis will get with TXE and HP for Verifying CIA points
LEB6 - MP Model misalignment, I checked the Turner NWD, they are using a FTI Container that may have a misaligned MP NWC
I Put together and new NWD with current NWCs Available and everything lined up correctly
LEB, DCW Drops, Get with John to find out which way they want to go, then follow up with HDR and Helm and Waldinger
I sent John Rhee an email requesting update
7/1/2026 - Jay brought up LEB6 issue I emailed, I told them HDR still needs to update their pipe stup ups, they fixed the grid though
I brought up CIA from other GCs since they were talking about FTI Scanning HP elements, if HP didn't provide documented points what is FTI going to shoot?
Justin said yeah, it is a meta requirement but meta hasn’t really lined out what exactly is required
I told them FTI did such a great job on the document and spearheading it, I was wondering if the other GCs also maintained this document since we are connecting to systems from other trades
Jay follow up with Kyle on HP for going through HP clashing directly, can we access them, create issues, clear?
7/8/2026 - Brought up LEB10 turner models, stay with NWC, even though they have
Advised that I have moved our DCW POCs to match HELM and HDR
Advised of TXE10 Scanning schedule starting tomorrow
Waiting on Patrick B for response on HAC FCU orientation
7/15/2026 - Told Jay, I havent verified Turners FTI Container files are updated this week
TXE Told Jay, Adam noticed the Fan Coils may need rotated 180 degrees, sent email, waiting on Patrick B to look at it
Verify Bypass submittals to FTI for John Cowhey
Check LEB6 FTI Container updated
7/22/2026 - Patrick sent out email saying txe10 FCUs have been reorientated based on Adams email, he will be going to other buildings
John is still waiting for Submittal for EOL HAC Bypass, he is talking to Jacob onsite, need submittal approved and start releasing fab on those
Underground conduit was missed for TWMU Skids, they need to be run overhead, it’s a substantial amount of conduit
Sent John, Justin, Jay the Control Point Map
Told Jay I would do a fly through on Leb10, LEB2 and LEB6 checking for FTI Container alignment
Do we need to do an official submittal for the Dimensions for UG Stub ups and Bypass elevations?
Start using ACC Issues module for tthings like LEB10 Crider stub ups being off
7/29/2026 - John says, he still hasn’t received the Bypass Submittal
I told Jay I would send LEB Control point email from Richard Lopez
I said I would get with Jacob and Keylan to make sure he gets it
I gave low down of what we are scanning, including CP's, what happened with CSV from Kyle
I asked if FTI was doing Trimble next week, john said yes and they will check certain things
I explained how the columns were off, I thought HP should be verifying columns and grid lines, walls may be off
8/5/2026 - They need stub up information for Conduit for the TWMU skid
Alex Harpel says the control points may be off at TXE10, Jennifer will be going through and verifying points
I told Jay, Region 1 alignment looked good, Region 2 I will check at end of week
check leb6 slab elevations different
8/12/2026 - Jay said cerris will be adjusting model based off scans
I made comment in Blue Beam Session for Exp joint hitting MES anchors
Alec said Jennifer says she is ok with Control points at TXE, HP will remove extra brass medallions, once the buidling is turned over, she wwill verify again
I told Jay I will request building control points from Mortenson, Richard Lopez
Get jacob or check status of submittal on HAC Bypass EOL submittals, are they approved?
Verify if Cerris updated TXE10 to match scans
Meta is using XYZ to verify control points, Alec Harpel Verified this
John Cowhey asked if we can put some info together based off Nathan (SI) Trimble information regarding wall and anchor clashes
NO PM/ FIELD TEAM
8/19/26 - Missed, at El Paso FOK/SOK
8/26/26 - Jay is showing a note about EOL Hac Bypass, the last Note shows submittal about Pipe Grade
Need to bring up Bypass Handoff, final scan time, time to create spool, fabricate, deliver and install before Takt schedule, Is Cerris going to verify they are leaving the bypass at HENSEL PHELP scanned asbuilt dimension and do a sign off/ hand off
John asked for an email summarizing this
Jay has entry for TXE10 Anchor (HAC) Bolt coordination, meaning the MES EOL Anchor, John says its being field coordinated
Alec Harpel, asked about JE Dunn asking for Imbed Anchor info for all regions, saying they were pouring concrete, etc
NO FIELD TEAM OR PM TEAM PRESENT
I told jay I looked at LEB6 and alignment looks good, I also republished and exported all new NWC's so everything should be current
Get Luke Jost information from Garrett about the FWM model and sheets and making sure they are updated. Garretts email yesterday said the model was current, they still need to update sheets. He needs all the info for a call later with HDR
TXE CLASH between interior HAC bypass valve handles clashing with FCU frame
John Cowhey brought up floor elevations and having to shim equipment which would through off spools, need to keep randoms in mind
9/2/26 - Jay brought up no progress on in building control points at LEB
- Also brought up setting skids high, shimming up to those points if need be
- I brought up the TXE10/ TXE2 summary of the adjust existing walls, adjust existing layout and the cutouts and leave outs to make sure they were line itemed on the agenda, Jay already had them from the email I sent with the asbuilts
9/9/26 - HP BZI has sent an email request to Alex Herpel requesting leave out/ cut out dims for anchor access. Alec
- Check updated layout for embed sent to JEDUNN from Adam, per John Cowhey. Yes, Adam sent updated sheet for TXE3-12, R3, had to scoot the anchor to be centered on pier, any existing anchors that are set 3-7? are what they are.
- Alex Herpel is working SI Engineering to get stub up POC pin pointed, Region 1 is what is, should affect future regions to make sure conduit doesnt get missed
- Jay said he would setup a meeting with Cerris/ HP to verify pour back/ ensuring bypass will meet HP's Dimensioned document POCs or if we need to rescan before finalizing spools
First of a series of daily check in calls between Mcdean, Tate and Southland to make sure we get steel updates from Tate and clash detection
Matt Mcconnell is the PM from Tate
Should see new update tomorrow morning
Guin Yaprak verified this is the case, 10-11am tomorrow
HRV FOK will be in the NWS
MSA will be included
This will be a recurring meeting everyday
8/3/2026 - Isabella told darren about Seths response to my request for consistent elevations, which was no, she said this is unacceptable. Darren said they went to Meta about this whole situation
I informed Darren the current model they were viewing was outdated, the current model from last week shows updated alignment
Isabella said she doesn't understand why Meta got involved, that was unecessary
8/10/2026 - Tom hammered down on Coordination for HAC and clashing, sign off dates
Tom says we need to align
Isabella said we need work together to get this setup
Danton didn't have anything, he is doing MOFE coordination
8/12/26 - Arthur stated the MES will not be moving, the MSA Frame will be adjusted to clear the clash between msa hac and mes anchor
Arthur asked Doowoo to assist in getting Darren participation and SJS participation
Ryan asked what kind of end was on the 8" flush skid, Arthur reminded it was hitting a timber column. I said it was a grooved end, we will get it through, even if we have to use a come a long, lol
He asked about the 8" TW Flex skid squeezing through column and mes, clashing, I let him know that was a temporary flush skid with flex pipe, we will get It through
Isabella stated that peyton will be putting together all information, and run through a list of clashing
Peyton showed the SI Duct clash with SI Mech pipe
Ryan got pissed that Darren wasn't available, saying this is such a broken proecess, arthur says hes out of his depth, Darren is double booked, Ryan said he needs to be there
Clash is showing flush access panels hitting bus duct on outside of wall
Isabella says since MCDean contracted with SJS to do clash and coordinating, they need to be present and hosting these meetings
8/14/26 - Cancelled
8/17/26 - They did a clash flythrough
Showed 6" FW Skid connector fittings hitting Steel frame, need to either turn MES Fiiting out, to face SKID or offset around Steel post
Also showed clashes with strut and supports, strut clamps need to be aligned to supports
Clash with pipe and steel frame, Tom asked why this clash is here but not in EMT and not the programmatic MES/HAC Steel
MCDean says they updated the steel based on CDD(?) before it is finalized, cart before the horse, they are going to do updates for tomorrow meeting
8/18/2026 - Missed, at El Paso for FOK/SOK
8/19/2026 - Missed, at El Paso FOK/ SOK
8/26/26 - This meeting was moved to Tues and Thur, HRV MECH MODEL COORDINATION REVIEW
Scott did his whole sign off and deliverable schedule rant
We are going to base our Coordination dates form DPRs precon schedule and sign off so that we are signed off with MCDean before DPRs dates
We are supposed to have approved submittals for anchors on 8/21
Document control, Isabella is the point of contact,
Scott explained , need one point of access for Sheets, we are still digging around looking for latest greatest
I obligated to once a week going through clashes, using HRV Forma
Isabella will submitt her stainless steel dog leg expansion for Tom to approve
Isabella will get with Tommy to Verify how many 14" skids they want
Scott asked for a full coordination schedule with dates to hit
Isabella sighed
Isabella said no, we don't have actual dates
Ryan said maybe we should be pulling back required dates from fabrication need by dates
7/29/2026
Explained the moving of embed to get out of wall, will move all embed together but will cause actual anchor to shift on the embed placement
Isabella Vesce Rivera
MSA to HAC needs some couplings removed
Depending on if Ryan can put the couplings on GMP Field because Fab is hard bid
Adam will remove from on site scope, per Ryan
Adam Dial in how we want to name NWS MSA for spool sheets
Adam wants to name them so they are more in line with the stratus packing naming
Deliverables -
Sign off and install schedule
Bridged files from Colonial
Isabella will bring up we need bridged file
I requested to sit on base build coordination meetings with DPR/ Colonial
Adam wants form to access DPR, he will give it to all
Tomas maxell and chirdon talking to structural engineer about eliminating the middle anchor on DCB100
Adam added couplings to MSA that will allevaite having to add welds for field install
Packages were created in stratus, should be able to get dates by EOW
8/5/2026
Adam had to push publish, I lost stratus addin, cant find download, gave up
I updated HRV DCB100 and replaced 07 couplings with 107v
Gave isabella the work flow for Layout sheets for hot items, Sign off, Eng Review, Shop Drawings, Spools
7/15/2026
Adam is supposed to put couplings in MSA to stop field weld
Need this update in stratus per Ean
All packages are created in Stratus with Dates
Get with stone and scott about getting FCU in the HAC for HRV
Southland will be running our own Clash Coordination
MC Dean provides a NWC, but we are choosing to use DPRs NWD in our own Model Coordination due to being more current and includes more trades
Keith, Melanie and Peyton will be putting this together
Melanie says not to clash with their NWD, not good
Either we will use DPR Forma Model coordination, if not available, we will ask if we can bridge their models directly to our forma to run our own Model Coordination and clashes
DCB100 NWS1/4 signoff 9/22
DCB100 NWS2/3 signoff 9/29
Waiting on Corbon to yay or nay the middle small anchor
MC Dean is still making adj to hac steel, they did state it shouldn't affect any of our content, ian is supposed to be complete on 9/24
7/22/2026
Gave run down to Thomas and Ryan of Colonial Stub ups
Trhomas says there will be a middle anchor
Peyton will be leading the Coordnation Model and space, will be issueing clashes
Will be running clashes today
Ryan did sent out an email to DPR and colonial web regarding the UG FW CWC Dim sheet showing critical dimensions
8/26/26 - Brought up the issue thats happened witht the bypasses, cerris moving the bypasses after the scans, waiting to see if cerris plans on verifying the final locations match HP's, or if we will need to do a rescan
waiting to hear from engineering as far as if the MES is moving, MC Dean is saying it will be moving, our Engineering has to ok, get submittals, move concrete pillars
Ryan asked Tom Maxwell to get impacts put together for the moving MES, Tom sent an impact out already along with mine
Scott is saying the DEAN MSA HAC was originally designed off a homemade MES from them, not ours, thats why the MSA HAC was 2" off along with the PSK Room being 4" different
Still waitng for approval on 2" expansion dog leg
Need to send Isabella email of Toms impact and mine from moving MES
9/2/26 - Need access to MCDean Coordinated model in order to clear clashes, submit issues, adam shared Files - Build
- Told Isabella DC90 access panels are good, no more changes
- Isabella confirmed EOL bypasses will not be installed at Fab Shop, still seeing if we can install at MC Dean site before delivered to site
- Told Isabella and Ean we need 8 weeks before day zero to finalize MES and Flush loop spools. Ean will be doing these, Vegas is doing skids
- Ian said he will need BOM info for the 2-1/2" SS since they dont have ss rollers
9/9/26 - Tom sent out email showing markups for anchors/ embeds. Curtis was to reach out from DPR, saying they will need in february. Vendors said they would need docs/calcs by beginning of nov if they are to deliver them in january
We sent the cantilever approval back for another approval. due to the new plate size, we had to increase bottom foot and offset it and now need to get re-approved, adam is hoping to get it back faster. He asked maxwell to get with chirdon and see
Isabella sent out Access Panel for DCB90 today to DPR, no permission on DPR to drop it in forma, I recommended using transmittal
- I told her access panels are good
- Scott brough up HRV using Sq120 but emt is Sq100, hes asking for verification, 120 = 16in sq, 100 = 14" sq
- Expansion leg carbon steel vs stianless steel, tom RR'd it.
- DPR Looking at verifying sign off process by end of week per Ben in previous meeting
- Still looking at install HAC EOLs, MMC (Dean) will ship to Brandywine, Brandywine will ship back to MMC, LEB FTI said they had issues with transmitting with EOL Bypass
- Adam said he will get new report for EOL Byass inside fcu that added 45's, 90's, nipples
- Adam brought up stianless header interference hitting support when we change to stainless headers in leiu of copper headers. MCDEAN is having issues with their steel between DCB90 and DCB100, hoping they will adjust to compensate for SS Headers
- See if we can scoot expansion tank in a little bit to avoid fork lift path
- waiting on cable tray clash with access panel on DCB100 information from DPR
- Need to go through Darrens report before Friday to clear any straggler clashes that may exist
- Isabella asked about lessons learned at sok, curtis gave verbal changes for 3/4" valve on RO cart, I also mentioned the vertical leg on the weld hose support. We agreed we need a formal Lesson learned issued from Paul and Michael
- I asked Maxwell for a formal 2-1/2" ball valve add to the non TWMU Skid side of mes and removing cap/reducer on Skid side of Mes
5/14/26 - - Joe Brought up the access panels for Flush system, asked about rating, I would have to check submittals to verify. Me and Lance holmes informed joe the flush systems are temporary, once done, they get removed and the access panel stay
Anna said they were aware, but not the finalized locations, now they will be going through Valley for engineering, excel engineering to make sure everything is accounted for, engineered
Talked to Stefan, we are not providing the Access Panel, its GC2 wall, they are providing it
I need to check on RO system, ACCess panel and it looks like location may be borked
Scott asked about sign offs for lighting scope to base build duct connections, Joe said they havent covered it, sign off is around end of June. They will be circling back to loop area not that they have certain paperwork available
Joe said any issue can be brought up at anytime
5/21/265 - No John Rhee, Brent, Thomas Holler, NO PM TEAM
They went over stud wall model, Lance asking about raceways for security and bus ducts
5/28/2026 - They went over electrical stuff, skid placement, wall leave outs
Turner wants a meeting with Helm and Southland to go over Wall penetrations
Joe D discussed Span model naming, keeping them the same and consistant.
Will need to relink LEB Span models since they have new models with Nucor suffix
6/4/2026 - Eduardo Ibanez brought up Status of Facility Water Stubups asking if Verification of Stubups with Mortenson needed. Had Crider submitted? Lance was saying Ryan would have this info and asking if Ryan was in meeting
NO PM Team present
I sent PM Team a summary email
I explained, Ryan used HDR model for coordination, I worked with HDR to get everything line up, we provided dimensions, everyone agreed to them, now stub ups are off, Lance Resposnded to John Rhees email asking what is being done
I said we need to start having meeting to go over this issue since its so critical
Luke Jost told eduardo to add an action item for this and lance said he will head this off
6/11/2026 - I brought up the FW UG being off again, told the group Ben Kozel with crider said they were backfilling in layers and trying to get the stub ups on the POC/CIA points
Joe Brought up IMP walls changing to Framed walls, Anna? Said it was still being worked on
Verify LEB10 POC For DCW
Verify DCW POCs line up with CIA
Lance said they are also providing a hose connection for discharge, I stated they are using the FLOOR Drains in center of gallery for discharge, Adam corrected me saying John has requested different discharge points. Wouldn've been nice to know.
Someone asked about the Flex piping from the 8" skid hitting the column, I told them it was flex pipe and temporary, that it will bend around the column
Vent in 6-19x6-D, adam told them to put in between MES Skid
Waldinger is doing the bypass on LEB6
Building 6 MES loops are showing misalignment with Waldinger Bypass
NO PM Team present
I said I would like it added to this meetings notes, Joe Dorinsville basically shut it down, saying it was a field issue
I said it was our issue also since we are constantly being asked to do overlays, which were happy to help any way we can, but this was more of a helm situation since they are the responsible party to connect to the UG and provide us with accurate points of contact according to the CIA
Joe reiterated it was a field issue
Overhead Signoff is schedule for 6/30
Scott asked if it was entire building for NWB, Joe says yes
6/18/2026 - Edwin Perez is showing Verification on stub ups w mortneson needed. Pending Submittal. Eng. Drawings to be submitted - Crider and Crider. He said this is still on going
Edwins model view still shows MP Shifted to plan right, access panels were to the right of the wall they are supposed to be in
LEB6 Arch Coordination model is showing everyhting off, MES Skid not lining up, mp is to the right, access panels are to the right of the walls they are supposed to be in.
LEB10, checked with Joe D, things line up there.
6/25/2026 - Joe, Greg, Luke Long, Greg went over Electrical coordination
I sent email to PM Team, no one was present
Eduardo Ibanez brought up Status of Facility Water Stubups asking if Verification of Stubups with Mortenson needed. Had Crider submitted? He brought this up again. I explained again that we provided dimensions for LEB10 and LEB1 to Mortensen, Crider and HDR, they all agreed
I told group that I also emailed these dimensions to Waldinger for Region 2, but havent received any comments or response from anyone.
Scott asked about tracking for signoff on 6/30, eduardo said yes
Luke Jost asked about LEB10 Embeds to make sure they are getting tracked by turner
Edwin Perez asked about Waldinger Bypass and alignment to SI MES Loop Connection
I told Edwin Perez I provided poc dimensions and elevations, but havent received any response
Edwin said he will bring up in next BIM meeting
7/2/2026 - Get with john as far as who is providing what cam lock adapt for fip drops
Lance Holman also provided additional dishcharges (Drains) for Flush/ fill per john
They showed model, HDR DWC Drops are on face of column, I told group IFC shows they are on Web side, HDR Model doesn’t match HDR IFCs
John Rhee is communicating changes from model to FTI, Turner that they are not telling us, Discharge drains, DCW changes
John fucking totally ignored our information and didn't relay any information
I missed the HDR IFCs showing the drops on the plan south side of corridor
The only reason I found out was because of the meeting flythrough, our pocs were on other side of corridor
I explained LEB6 model misalignment was fixed, publishing issue, I will double check mondays model after the Saturday auto publish
I told group about the FW UG Dimension sheet that has been distributed multiple times and it details where the FW UG stubs are supposed to be ever since LEB1
I will double check LEB2 misalignment
They showed LEB6 and the 8" skids were into the columns again
I explained the deep dive I did last week, it shows everything aligned. There are issues with the FTI Container model that Turner is using for coordination
7/9/2026 - Setup LEB2 SI MP View off turner LEB2 Overall Building NWD, Crider is still off at Grid 2-50/ 2-D
Eduardo Ibanez hosted
LEB10
All Content on slab will be created in a file, progress is ongoing. Jay Asked what does this entail? Above Slab content?
LEB6
SI Duct and Waldinger do not align
Justin verified that Turner is using NWC files NOT the revit
Our MP is still out of alignment in Turner LEB6 Overall Building.nwd, but Joe pulled in a recent nwd and it showed the FTI Container inside the Overall nwd is off
With joes pulled in NWD that shows us and waldinger aligned, Crider was still off around 8-10"
Southland MP looks good
Southland MP model is still a little older, but non-critical
7/16/2026 - Joe D brought up some issue about control joints at LEB10, luke jost and jay kaiser will update as necessary
7/22/2026 - Joe D brought up control joint proximity to MP anchors, they scooted 1 at grid 29ish, no TW Skid.
Checking Coord Space at LEB I see Stratus models getting exported again on 7/17, that was last Friday
The only MP model available is from april, what the fuck is going on with this fucking shit
The LBE10 Publish settings were set to stratus, talked to heath, he showed adam was the last one to do it. Adam said he didn’t know had to change settings back
Lance suggested a meeting with FTI and Southland to get power to TW Skids, Lance Long said they have a meeting setup with FTI Tomorrow, looking at junction box on the wall
Jay K at FTI created an issue with Crider Facility Water Alignment and was trying to add crider watchers, he can only add FTI watchers.
Joe D told him to use Triston with Helm, Mitch with Waldinger
Mitch with Waldinger said it looks like its going to work out with aligning their Bypasses with Southland MP
Jay K brought up container models having outdated southland models
Joe D says its tough to say when the FTI container was reloaded. The last update they show was july 13th, 10 days ago
I rbought up the TW Skids on each end of the building also to check, they have anchors also
I stated I found a recommendaiton of 3" distance between an anchor and a sawcut or concrete joint
7/30/2026 - Jay brought up getting control points from Turner
Jay brought up missing MES/ TW skids from LEB1, LEB2 FTI Container, the MP content was aligned
8/6/2026 - I affirmed with Jay, I have not seen any blue beam sessions
I verified LEB 6 in Navis, using the View I created with all trades
James (Turner) is setting up meeting next week to go over CIA points with FTI and Baker
Jay asked about established control points, joe said bring it up in the session
8/13/2026 - Helm modeled their bypasses to the current asbuilt points received Last Friday, This Monday
I told Joe we would wait for the actual asbuilt 3d scans before we do any further model aligning. It’s a waste of time right now, to turn around and have to do it again after scans are received.
8/20/2026 - I told them again we will be able to squeeze the 8" Flex skid around the column, its a flex pipe and not an issue
8/27/26 - Had to leave to go to EMT meeting due to current emt issues
9/3/26 - Eduardo Ibanez hosted
I told lance and Diogo that the Embed Layout shop drawings have been submitted a while ago, Luke Jost verified they have been submitted. They need to use that information for their anchor information
They couldn't see the MES Anchors, they were yellow, me and jay told them to zoom in and they were there.
issue 4250 Duct at leb 6 not aligning to Waldinger duct, sent chat to Stone, talked to him later, the LEB6 FTI Container.nwd is outdated, showing old duct work according to Stone
issue 4236, Joe was asking about our DCW on a column hitting a camera, but ours are just placeholders. The screen shot they showed had the DCW from Helm/ Waldinger on the other column so it was moved.
9/10/26 - Eduardo Ibanez,
Jay K brought up access panels missing from IMP Elevation drawings from last week, Eduardo asked SP to get with SPO for update, I verified this was the last I heard also
Edward Hammer? Brought up access panels for LEB1, they dont have info, I mentioned it was submittal #5 with FTI, I looked at Turner Submittals, they dont show anything. I emailed Jay, Justin, Luke and John
Melanie Working through EMT Models, links needed repathed
Go Through EMT1 and EMT2 and make sure MES, TW and MP content are good
IF good, push to Revizto
Also check MSA/FSHAC Piping
EMT Does have IFC's for Base Build, Scott showed them yesteday, I coulda swore we didn't have any sheets, prob thinking of HRV
7/16/2026 - Melanie says our MP model doesn’t line up with Eng Model, we are using Lightning Shared Coordinates, Eng is using ETM100
Abe - Attached Sign off schedule to summary email, have content populated and coordinated ahead of signoff dates highlighted in RED, these dates line up with Mortenson
I told her our content, mes content lines up in revizto, if you change anything, it will no longer line up
Download arch model, link our models in and see who lines up
She says archs did change the g datum model a while back, she had to repath it and that’s when things stopped lining up correctly
7/17/2026 - Cancelled
7/20/2026 - Cancelled
7/22/2026 - Ryan says Mortenson is on the verge of issue stop work order with Meta due to electrical incompetetance
7/23/2026 - Cancelled
7/30/2026 - Cancelled
8/6/2026 - Adam said he will cover EMT, I will do the LEB Meeting
8/13/2026 - Cancelled
8/20/2026 - Missed, went to FTI LEB Meeting
8/27/26 - Abe says Mortensen said they will go through and remove duplicate content
Brought up clashes issued to me were showing no clashes when I zoomed into them
also showed the Flush piping and access panels hitting cable tray
9/3/26 - Adam attended, I couldn't since I did the LEB Meeting at 630am
First of a series of daily check in calls between Mcdean, Tate and Southland to make sure we get steel updates from Tate and clash detection
Matt Mcconnell is the PM from Tate
Guin Yaprak verified this is the case, 10-11am tomorrow
Should see new update tomorrow morning
HRV FOK will be in the NWS
MSA will be included
This will be a recurring meeting everyday
8/17/2026 - They did a clash flythrough
Showed 6" FW Skid connector fittings hitting Steel frame, need to either turn MES Fiiting out, to face SKID or offset around Steel post
Also showed clashes with strut and supports, strut clamps need to be aligned to supports
Clash with pipe and steel frame, Tom asked why this clash is here but not in EMT and not the programmatic MES/HAC Steel
MCDean says they updated the steel based on CDD(?) before it is finalized, cart before the horse, they are going to do updates for tomorrow meeting
8/14/2026 - Cancelled
8/3/2026 - Isabella told darren about Seths response to my request for consistent elevations, which was no, she said this is unacceptable. Darren said they went to Meta about this whole situation
I informed Darren the current model they were viewing was outdated, the current model from last week shows updated alignment
Isabella said she doesn't understand why Meta got involved, that was unecessary
8/10/2026 - Tom hammered down on Coordination for HAC and clashing, sign off dates
Danton didn't have anything, he is doing MOFE coordination
Tom says we need to align
Isabella said we need work together to get this setup
8/12/2026 - Arthur stated the MES will not be moving, the MSA Frame will be adjusted to clear the clash between msa hac and mes anchor
Ryan asked what kind of end was on the 8" flush skid, Arthur reminded it was hitting a timber column. I said it was a grooved end, we will get it through, even if we have to use a come a long, lol
He asked about the 8" TW Flex skid squeezing through column and mes, clashing, I let him know that was a temporary flush skid with flex pipe, we will get It through
Isabella stated that peyton will be putting together all information, and run through a list of clashing
Peyton showed the SI Duct clash with SI Mech pipe
Ryan got pissed that Darren wasn't available, saying this is such a broken proecess, arthur says hes out of his depth, Darren is double booked, Ryan said he needs to be there
Clash is showing flush access panels hitting bus duct on outside of wall
Isabella says since MCDean contracted with SJS to do clash and coordinating, they need to be present and hosting these meetings
Arthur asked Doowoo to assist in getting Darren participation and SJS participation
8/17/2026 - No notes, cancelled?
8/18/2026 - Missed, at El Paso for FOK/SOK
8/19/2026 - Missed, at El Paso for FOK/ SOK
8/24/26 - MSA Support foot clash with MES 4.04 is in NWS and the MES 4.03 in the datahalls, datahall clash is smaller
MCDEAN is saying we will have to move the MES into the corridor
Tom and adam explained Anchor shifting 1.5" will cause new submittals, new spooling and parts for MES EOL loops and possibly redesign of the flush skids
MCdean, Danton and Arthur said the msa is 1" wider, they submitted to Meta, scott says the msa is 13'-2" and the other are 13'-0", thats 2"
Tom brough up shifting the MSA supports next to MES toward the FSHAC to clear the clash, MCDean was iffy about whether they looked at that
8/27/26 - TW at MES EOL is clashing with hac frame
Darren said they need to remove the MTR Frame, its still there
Need to check TW at MSA Supports dont line up, steel is missing support
Check Flushing misc piping and parts at NWS clashing on MES and HAC
I brought up the flush piping /access panel clash with cable tray which will be covered in the DPR coordination meeting that isnt happening right now
Darren said those cable trays should be getting installed after flush/ fill due to interfering with moving flush skids, he measured cable tray, it was 10-11 feet AFF
9/3/26 - Darren went through a few clashes, a lot of MSA legs still need rotated, most of those clashes will be cleard. Including a msa leg hitting anchor
Will need to look at rotating a few couplings to clear other clashes
Showed lifting lugs getting removed to clear clash with flush fittings
Some of the TW Header clamps were inside pipe and the pipe was hitting supports. MCDean said they did set hacs at about 1/2" high to compensate for concreate hi-low, they will shim
9/10/26 - Arthur brought up pipe clashing with support, he said their sister site is identical but no clash. Adam says due to changing to stainless the od pipe is bigger by .5", so 1/4" on each side. Arthur said they are using copper on sister site.
He said darren was out til tuesday, but they should still be able to update an NWD and clash report tomorrow. He said they should have legs rotated, new msa steel in place tomorrow
900amClifton Strength 1 on 1 with Wlad C
Jeff L (SI)
9/10/26 - Talked about work, movies, video games, work tools, naviate and Si Tools.
Kaushal Bagdekar with Turner ran the meeting, saying who to contact for what, I asked if he could send an email with that info
They went over underground clashes
5/28/2026 - Tristen with helm verified he is using LEB1 dimensions for LEB 2 elevations and locaitons for FW
6/11/2026 - No PM Team
Went Over UG issues, concrete pads
6/18/2026 - Kaushal Bagdekar
Did a flythrough for LEB2 going over exterior sectionalizers
LEB-2_SPAN_SS.rvt, verifying during meeting that the model is good, Checked LEB2 SPAN_SS model, couldn’t load content, says cant link in NuCOR
NO Interior Walls and framing, Valley, Diogo or Ruth said they will get with valley
No Interior Meta Wall Panels
6/25/2026 - NO PM TEAM
They went over UG issues for LEB2
7/2/2026 - LEB2, Showed model where Helm, SI and Crider not aligned, #2070
LEB2 Building Overall actually has Crider model, showing misaligned
Grid 1-50, 1-D is the only spot where Crider is off looking at Turners LEB2_Building_Overall model only
Everything else is aligned, MP, Duct, Steel, Walls, no issues
Sent email showing misaligned concrete and crider stub ups at 2-50
LEB-SI-MP-LEB2-R25 model lined up identical to LEB2-Building-Overall
Didn't see new DCW POC valves, did I update LEB2
Did see FLUSH VENTS AND DRAINS, VENT ON 2-50 IS OFF
7/9/2026 - Sent Email to Joe, Jay, Edwin, Eduardo and Joe forwarded to Kaushal
Kaushal asked about flush skids in front of door ways, need to send them a time frame for flushing before equipment gets removed
Concrete elevations different at Gird 2-29 and 2-32
Crider stub ups off at 2-50/2-D
Added to chat
7/16/2026 - Sent email to Triston with Jay and Kaushal cc'd about Helm bypass flanges not aligning to SI MP Flanges throughout building
LEB2 looked like it aligned good
7/22/2026 - No southland issues covered
7/30/2026 - Just went over non-southland issues
I dropped for LEB Mortenson meeting at 1000am
8/13/2026 - NO PM/ FIELD TEAM
Ouch, Kaushal called out Triston for not being in the meeting 3 weeks now
Had Kaushal remove the waiting on southland to add content we are waiting for, under MP Pipe - Triston, he labeled it closed
Dropped out at 10am for Mcdean Hac Meeting
8/20/2026 - They went over support pads in yards and clashes on exterior., I dropped for 10am LEB Mortenson meeting
8/27/26 - Just went over all other trades and issues, Triston said no issues from Helm, dropped early for LEB BIM Coordination Meeting with Richard lopez
9/10/26 - This meeting must have moved. Not showing in the calendar anymore for Thursday at 930am
8/20/26 - Asked Richard Lopez if anyone is using shared building Control Points, him and nick both deferred to turner. I said I am used to a site wide control point map that is shared with all trades. I understand this is a bit of unique job with 3 GCs though
Richard corrected his statement and said turner actually did have a meeting last week with him and Nick, he wasn't sure if it was a recurring meeting but would look at getting information dispersed.
Ryan Zoldan - Richard Lopez
John Rhee nor Brent were in this meeting
LEB 6 due finalized next week
I requested a schedule from Ryan, he has the sign off, region schedule, I brought up a pull plan, be he says that will be through Turner
Mortensen is the Base build GC, why aren't they leading a pull plan schedule
6/4/2026 - I brought up the LEB10 FW UG Stub ups totally missing the Dims, Ben Kozel was there and he stated they are bringing them back in to dimensions by backfilling a little and moving them, backfilling and moving them
He acknowledge that lance did contact him
6/11/2026 - Ben Kozel, said there were no issues that need to be talked about.
Richard lopez asked around the room for any issues regarding LEB10 or any others
NO PM Team
6/18/2026 - Richard Lopez Hosted, just asked for any issues with LEB10,1,2,3 Underground issues
Rantwiler asked when IWM for TXE10 was going to be signed off, Ethan says he will talke to kyle since they are not really split out
6/25/2026 - Going over LEB7,8
Ryan brought up LEB6, HDR model is not lining up with the Dimensions provided by SI
Ryan henderson said he will follow up
Ryan said we have all agreed to follow these dimesions, I added that I have distrubuted that dimesion sheet ot Waldinger and explained everything, but havent received a response yet
Ryan brought up LEB6, HDR model is not lining up and my email I sent out
I updated, still waiting for HDR to align the stubups
Ryan said Crider is using civil 3d, but we can work it out to actually use their model for coordination and linking in so I don't have to use HDR
7/9/2026 - No issues to cover, they went over UG clashing for elect, sanitary
7/23/2026 - Richard asked Triston about any alingment issues, he was good
Ben said LEB6 stil had some very minor HDR alignment issues to on udergoung
7/30/2026 - Bend said LEB6 looked good
I said we republished LEB6, there was some extra content we had to remove
8/6/2026 - I brought up the LEB10 FW UG Stub ups totally missing the Dims, Matt Schaff said they are doing repairs this week and lookingat getting into within an inch
I mentioned, for helms benefit of using Eccentric reducers on bypass in order to rotate the stubup to align with MES better
I also mentioned after slab is poured, bypasses installed, we look at doing 3d scans
8/27/26 - No issues were brought up. I was going to bring up control points, but Im done. Ive asked, sent out emails no one has responded except jay kaiser
9/10/26 - Went over clashes and any issue through LEB10 , 1-12, no one brought up anything
TXE1 looks good for the loop area sign off next week
Same with TXE2
6/4/2026 - Own B ran the meeting going over TXE1 and 2
6/11/2026 - Owen B, says TXE10 Loop for sign off
TXE2 Core scheduled for next week
TXE10 AB Datahall and Loop are signed off
TXE3 Alan lopez is running region 2 for signe off
TXE2 Loop and AB South sign off
issue 2602 - Cerris Vent in corner is clashing with Technical water, Rantwiler is saying they don’t have our model, I told them our model has been there for 6 months, the fact that HP is viewing it, means the model is available. If it’s a bridging issue we will help Cerris work it out
Trevor said he will get with rantwiler and get the model bridged, they will offset that vent around our TW Piping
They made comments about the TW skid being so close to the FW valves. Its been this way for over 6 months. Trevor also stated the vent will need an accessible cleanout
6/25/2026 - They just went over IWM and specific Electrical clashes
7/9/2026 - TXE 2 all docs are out, all sign offs are out
TXE1, 2 sign offs left
DHCD 2 weeks from now
7/22/2026 - No Issues
8/20/2026 - They didn't cover anything relevant to us.
8/27/26 - Cancelled
9/3/26 - Cancelled
9/10/26 - Will be doing a new meeting every other week from here on out according to Owen
Follow up on HAC Panel clashes with Patrick Brinnehal
Meeting to go over stratus and models with all PMs, Adam, Scott, Supers sometime next week, look at schedules
Chris Chase is the PM of EMT
9/8/26 - This meeting is getting moved to Friday by TIA, still waiting on new invite
5/26/2026 - Check if Adam got the 4" Welded Bypass to Shop, from 5/5/25 email in Inbox "Im shooting to have the LTG build out scope package done by end of week (For Review only not for construction). "
Verify what spools have been put on stratus for TIA/TOM Lightning huddle
Need meeting to discuss, txe10 anchor clashing with interior of walls, adam sent info out about conflicting models, but as of today, there is still clashes
RFI says they are changing wall to Gypsm board and expanding toward corridor 2.5"
6/2/2026 - We did get 2 more sites in Ohio
Mealnie says they will be updating projects to new architect model
SI will be integrator
Heath introduced Peyton Steveons as VDC supervisor
Starting with HRV
Type F - 4 buildings
Type G - 2 buildings
Melanie introduced Vasi, VDC specialist helping out ron and melanie
Tia went over deliverable schedules
She setup a break out meeting
Per site, per building
Adam said they are moving the walls away from anchors so we are clear
only 2 walls changed from IMP, 2 others are still IMP
Michael said Greg told him they are putting walls up next week
Adam said we are 1/2" clear from plate, it will be a field issue installing the plate
Michael said he will talk to paul, he doesn't know what to do, he will call greg
Told Tia I sent snip of Dog Leg Metraflex in chat, didn’t get any smiles
Let her know we have LEB complete, TXE10,1,2 is complete
Adam said he will give link to CIAs, TXE3-12 and LEB3-12 not ready
Adam had meeting with HRV, told them to start using our coordination models for coordination
with MC Dean
Quick hello, this is who we are meeting
6/9/2026 - Adam said they are going to move the MSA, HAC spools to the Lighting Program, for one source
Melanie and Keylan said it can be done
6/30/2026 - FTI wants scanners badged
TXE1 special Support approved
H Support hanger, supposed to get stamped this week
HRV supposed to get linked in models setup so we can coordinate ug
Need to verify LEB and TXE CIA points
SS Headers are in fab per EAN
John Rhee asked about Waldinger misaligned, we are now good, sending email showing HDR is off
Toms Eng review comments will be looking at doing updates next week
Michael said they have drug test this week, orientation on Monday
HRV Embed Dims, ryan says he has, I have Angle working on them now, wtf?!!!
PIQ, melanie is setting up, I asked her to keep an eye out for the BIM ex plan and contact list
7/7/2026 - Cancelled
7/14/2026 - Melanie is going through EMT with cupertino to verify alignment
Isabella asked about clashing HRV, Peyton will be running coordination model for HRV as well as EMT
HRV Embed sheets need to be sent to Basebuild, adam mentioned
Still waiting on word a
7/27/2026 - Adam said Zach gave him the low down on the CIA, it is not a contractual document, it was sebastian telling faith to do it
8/4/2026
8/11/2026 - Michael says all walls are off, asked me and adam to comment, I said get us the points, we can drop them in model, create a document to be used to create an issue and escalate it
HRV, MCD Dean working through hac and pipe clash
I brought up the control point issue at TXE
Metas involved with their surveyors according to Louis Saldana, FTI was supposed to verify with Jennifer
John Rhee says they will need to bring up the bypass support in their next meeting when Tia relayed toms concerened about it
LEB only wants 2 14" skids, need to update maps and bom
John verified there were 11 8" and 6" skids on the BOM package for LEB
He dropped Trimble information into chat
8/25/26 - I updated the Support on Basebuild bypass, said I emailed Trevor at Cerris, no responde
If tom wants more info, we may need to issue an RFI
9/1/26 - Michael was there. I gave a break down of what hensel phelps said in last meeting. They will adjust existing walls for anchors, adjust existing layout for anchors, create cut outs and leave outs for drilling and installing bolts
Michael said they have anchors being sent to site on 9/9 and will start drilling and installing
I gave a break down of the HRV HDPE stub ups, thickening of the slab and anchoring of the UG FW Stubups to compensate for the 6" expansion/ 30k Thrust issues from the HDPE, could affect all jobs
Adam brought up the note from TOm C about Diana re calcing the embeds and causing a change in layout
Phil said he will get with Diana, Michael at TXE said they are installing building 8 right now and looking at installing epoxy anchors in a few weeks.
9/8/26 - Tia Moved Meeting to Friday at 6am
9/11/26 - Diana has issues with TXE Region 1 epoxy anchors, bolt pattern is changing. Michael wants to drill concrete next week, adam said wait til anchor bolts are finalized from Diana. TOm and Diane have meeting this morning to discuss
Tom says TXE10 is the most problematic due to low PSI concrete, its under 5000 lbs
TOm said we need to hold off HRV anchors also, He needs finalization from Diana.
Michael said continue the training from hilti scheduled for next week.
Michael asked about spools. I explained the same thing I emailed them about Cerris bypass not being on point after they put those extra bypasses on. Ryan chimed in and said scan it and keep track as a billable. Nate is scheduled to trimble on 24th
Keylan brought up no CSVs based on new Control POint PDF, I said the PDF is the actual contractual document, Tom was upset that HP wont give CSV, its up to us to either manually create CSV or use AI for help, Adam said we will take care of it
EMT/HRV Anchors waiting on DIana to confirm
Tom is sending email to Project teams about securing ug stub up bypass, they will expand 6", if they secure pipe it will transfer 30k thrust to slab which will introduce supports around bypass conflicting with our supports
DCIS 4636 FInal Handover from WhiteSpace, does this include anything regarding the Underground Bypass from Base Build, since we are looking at a conflict with Cerris on POCs, we and HP scanned, we aligned, they moved, we need to scan again
Verify 107V and 07 Couplings on Pup pieces, region 1
Adam said we are still working through comments, still waiting on cantilever approval.
LEB10,1,2 will be good to push out to submit to tom
Need to update regions to datahall A,B,C,D
Day zero is 2/25/27
Need spools before 1/5/27, Adam said we wiill shoot for 6-8 weeks before then to allow for review, updates, etc
8/28/26 - Cancelled
Scott says EORs get officially submitted to Tom, he approves, they get submitted to FTI. Not sure if EORs get submitted to Meta or not as part of record drawings
Scott says by Friday the 14th they will publish to stratus
Embed Layout Drawings
We gave drawings, we will have
Crider and Mortenson will provide scans once they are finished, so that helm can update their bypass.
Flush Skid BOM, Curtis used TXE Counts and ordered the material
Hose Carts are still being finalized
Get Reece copies of TXE Flush skid BOM information
Hose Carts will be finalized once FOK and SOK are done
No pour until november
Schedule model? Can we incorporate this?
LEB10 UG Stubup status
Crider, Mike Schaff said they were doing repairs this week
Make sure LEB PM Team knows we need to scan after slab, after bypasses installed, then we align, update spools
8/14/2026 - Cancelled
8/21/2026 - Bring up mentioning Control Points in Meeting yesterday with Richard Lopez (Mortneson), says they dont have any Interior building control points, get with Turner, then said they had a meeting last week with turner, he will check if its recurring
Talked about the 30 email chains from Lance, Jake Wright, Casey, Triston and Ben. The lastest is from Helm asking if their points are good.
Talk to triston about their flush fill, are they using the existing bypass or adding a temp one?
9/4/26 - Adam resubmitting 18" Foot on Cantilever since approved 16" is hitting wall
Adam is asking tom to put small feet on anchors to be welded onto embeds, havent heard anything back from Tom
Need to bring up Control Points - Last I heard from Richard Lopez, he said they had previous meetings between Mortenson and Turner, he was going to check if it was recurring and get us invited. He said they DO NOT have any shared interior building CP's
I relayed this info to Jay Kaiser and Justin Jenkins at FTI, haven't heard anything back
Look up Helms last email on the FW UG Stub ups
November is pour date for LEB10
Reece said he will get with HELM on if they are using Temp Bypass for their flush and fill
Reece said he will coordinate with Richard Lopez, Lance Holman, Jay K, Justin J on control points and getting shared points establishes and shared
Stainless headers will be used in LEB2 from Reece, the stainless headers are bigger, clash with supports, FTI will need to adjust supports for Stainless headers. Reece will get with Keylan at TXE10
Jake brought up the added ports, I explained the email and the status, need all PMs to agree on adding over 500 ball valves per project
8/17/26 - Ryan Ran the meeting, couldnt get the agenda up, lol, asked peyton to go over clashes, peyton said he wasn't ready, then Ryan did a round table, no body had anything to
8/24/26 - Didn't really go over anything, Ryan Warner, we ended early. Ryan Warner started a new meeting at 712am, he was late
Peyton showing MES MP Pipeing into duct and framing, mic didn't work so I couldn’t talk to verify MES Elevations
8/3/2026 - Abe said UCO3 UG Signoff is pushed to next week
Peyton going over clashes
#816 shows vesda FP content going through our bypass at hac, adam modeled the vesda
MH Duct at EMT1 was low, scott said he will take a look
8/10/2026 - Melanie says she will look at MES Alignment, I said on Saturday mes was mis-aligned again
Adam said he will fix Vesda Clash with HAC EOL Bypass
I said the MES Loop/ Flush Loop piping needs to be reconfigured, its clashing with TWMU Skid, the tee will get rolled to vertical and cantilever pipe supports will be brought in
8/31/26 - Abe says we need to have clashes cleared by sept 28th
sign off should be around that time
Tom was asking about workflow for clashes, reports. ALex Hubbard eluded to it saying it was more verbal, no reports
EMT1 is showing clash with UG FW Handle into wall and hitting TWMU Skid piping support, Also showing duplicates, worksets need turned off, EMT1 has misaligned piping
6/1/2026 - Noel Nunez says Alehandro Chew will be safety manager
Michale Paul said they thought the walls weren't going to be in until they could do anchor
They said that was what was agreed to
Michael said he sent TXE3 embeds along with PDF dimension in mid April
Doesn’t think TXE3 has been poured, think they are behind schedule
Says we havent been funded for Region 2, he is sending out embeds as needed
Michael asked what the question was about RO and TW, I said it was going over how to connect to the RO skid, from DCW and to TW MES
Michael asked if MES Loops were completed, adam said yes, he created new BOMs
Michael said his goal is to get everything ordered
6/8/2026 - Michael said they had a PM Coins Mandatory meeting and couldn't host the meeting
6/15/2026 - Chris Moss came on board from TSMC, Pipe fitter, GF
Jose Alejandro Chew, new Safety Manager for TXE
6/22/2026 - Shop drawings (Engineer Drawings) looking at submittal on Frid, 6/26
6/29/2026 - Keylan Cancelled
7/6/2026 - Carson will scan on Thursday
7/13/2026 - Scans on TXE10 complete, should have done this week, EOW
Jacob will be pulling field measurements of FW Stub ups
Adam will overlay scans to see how they match up with our Stub Ups
SOK will be starting next week, 27th will have more setup covered
7/16/2026 - Zach wants scanning sent back out, scan off control points, need to get CPs from Greg, put in model, talk to carson to see what they need from us
Control points were requested on 6/12 meeting with Greg H, it was stated they would be sent to Michal and James Homrighausen
I also asked for control points from Luke Justice on 5/21, he said he would get with Greg H.
They made it out like it was detailing fault they scanned without using control points
Paul asked how soon I can get the points into model, I said immediately, but Im not sure scanning needs anything from us, they may input control points into the rcap software maually but we will have it the model if they need it
7/27/2026 - Scanning this week
FTI Will be doing Trimble next week
8/3/2026 - Adam brought up new pipe supportts that were sent to Tom due to more access to mes loop valves
Adam asked about tapped caps for mes connections, michael said it was a miss on them so they will cover it
Trimble is shooting wall points tomorrow and Wednesday
8/10/2026 - Asked about txe2, keylan said they have bottom plate down, trimble is showing walls off
Asked about info for points from trimble, is this for field use only, are they showing HP where walls are off
Keylan says they are using the info to show HP were walls are off, TXE1 had walls off, HP is still working on solutions
I asked for TXE2 Cerris bypass schedule so we can get scanning out
He said he would get me that info
Need to ask about Access panels, whos providing?
Need to ask about info for HP saying they are having issues with control point discrepancies
I will put together an email of who said what in which meeting and send to keylan to start a chain
Keylan said he will double shcek with paul and nate
Paul says he hasn't heard anything about control points, alec says HP is suggesting we move our anchors
FTI says Jennifer is gong to get involved and veriy, Meta says they will send their own Surveyors out to verify, this was last I heard
8/17/2026 - Cancelled
8/24/26 - Jacob went through agenda. Boots on the ground "soon", they had exterior and interior walls up on TXE2, how do we not have boots on the ground now?
Nate is supposed to be trimbling the rest of TXE1, I didn't know TXE1 was even poured and ready
Keylan said he has to verify Control points. They were going to take it off agenda. I told them the medallions werent identified or center punched, Keylan told jacob he needs to get with Alec, I suggested filling out an issue on FTI site abou this, keylan agreed
7/27/2026 - Missed, went to Cameron Shop to meet Mid Atlantic Crew
8/17/2026 - Went over UG and sign off dates. EMT1 Sign off on hold due to CDD1 change, looking to still start coordinating knowing they will need to incorporate the changes after the fact
8/24/2026 - Going over drone shots, showing UG progress
8/31/26 - DPR Hosted continuation of the weekly HRV Mechanical Component call, for the discussion of project document contorl, high priorty issues/ Coordination topics, and quality items for MEP, FP, BMS Control scope.
Ashley shows a line item for FW supports at SOG, said she would rather handle that on a smaller group
ARUP has not included the Access panels in the latest IFC set. Isabella informed Ashley that we have submitted them, we havent submitted dcb90 yet. We will bring up clash with cable tray in Wednesday detailing meeting
Isabella brought up flushing power requirements to make sure DPR was aware of skid locations and power requirements, seeing if DPR needed a side call, she asked if Isabella can forward information, it was said to tag anthony, curtis and ben for temp power
Doowoo with MCdean said he will forward chain to anthony and curtis
Ashley continued the FW UG Support discussion with CWC, ARUP, MCDean, DPR
CWC is putting together information on supports at penetrations.
Neema with ARUP says they havent evaluated the displacements or forces at bypass and stubups so Peter ran designs to look at them. Neema talked about flexible connections. Peter says vertical pipe will have 6" exp at bypass, if restrained it will be 30k lbs
TOm chirdon chimed in talking about our anchors, Tom was asking who is resposible for the thrust coming from bypass.
Ashley would like to have follow up meeting with Arup and CWC having information about the thrust/movement at bypass.
Ashley said they will design slab to not allow movement in the stubups so MCDean and Southland do not have to redesign piping, pads will take care of growth and thrust. 9x9x3 piller with possible fittings that attach to pipe and transfer forces back to slab
Neema also brought up thrust from MES side, peter said they will be minimal
Tom brought up the bypass actually needing support, they asked if we have submittals on our veritical supports since we are drilling into concrete.
Melanie Working through EMT Models, links needed repathed
Go Through EMT1 and EMT2 and make sure MES, TW and MP content are good
Also check MSA/FSHAC Piping
IF good, push to Revizto
EMT Does have IFC's for Base Build, Scott showed them yesteday, I coulda swore we didn't have any sheets, prob thinking of HRV
7/16/2026 - Melanie says our MP model doesn’t line up with Eng Model, we are using Lightning Shared Coordinates, Eng is using ETM100
She says archs did change the g datum model a while back, she had to repath it and that’s when things stopped lining up correctly
Abe - Attached Sign off schedule to summary email, have content populated and coordinated ahead of signoff dates highlighted in RED, these dates line up with Mortenson
I told her our content, mes content lines up in revizto, if you change anything, it will no longer line up
Download arch model, link our models in and see who lines up
7/17/2026 - Cancelled
7/20/2026 - Cancelled
7/22/2026 - Ryan says Mortenson is on the verge of issue stop work order with Meta due to electrical incompetetance
7/23/2026 - Cancelled
7/30/2026 - Cancelled
8/6/2026 - Adam said he will cover EMT, I will do the LEB Meeting
8/13/2026 - Cancelled
8/18/2026 - Missed, at EL PASO FOK/SOK
8/24/2026 - Went over WPI and hac frames, new DCIS about SKU Numbering, Updating the model to make sure its accurate.
9/1/26 - I told Abe I am aligning and cleaning up EMT1, will tell Nicole about a workset thats turned on showing duplicate bypasses.
9/1/26 - Currently EOLs are installed at Near Site, it makes sense to install these prior to arrival on site
The Bypasses could pose an obstruction to installing the ESA frames at the end of the FSHAC and cause a new path to be incorporated
Adam asked if the bypass could be installed on MCDean site after the panel is installed. Then need to worry about the bypass interferring with the travel path of the ESA Frame
Gelu says there are too many issues, hard to understand. Isabella explained we were exploring strategies to ease the difficulties of installing bypasses in the field where rigging and access are main concerned.
The Team will be taking a look at the FOK to go over the discussion again around 9/15
9/1/26 - Arthur brought up flipping the leg on the MSA 180deg to clear the clash with the MES Anchor, we wouldn't have to move anything!
Use the MDI model for FSHAC steel, the ENG model is for design and doesn't show steel
Need to go through the excel report from Darren to clear and check clashes
Darren will clear the FCU clashes since they will only be 1/8" and get cleared
Isabella did find out cable trays will be installed before flush fill according to schedule, april of next year, just before our day 0, MCDean Darren said he will get with them also to make sure they dont impede in drive aisle
Adam brought up the Bypass clash with FCU and cable and having to rotate valves, Darren said if they are there for next clash report, he will flag them
Follow up on HAC Panel clashes with Patrick Brinnehal
Meeting to go over stratus and models with all PMs, Adam, Scott, Supers sometime next week, look at schedules
Chris Chase is the PM of EMT
5/26/2026 - Check if Adam got the 4" Welded Bypass to Shop, from 5/5/25 email in Inbox "Im shooting to have the LTG build out scope package done by end of week (For Review only not for construction). "
Verify what spools have been put on stratus for TIA/TOM Lightning huddle
Need meeting to discuss, txe10 anchor clashing with interior of walls, adam sent info out about conflicting models, but as of today, there is still clashes
RFI says they are changing wall to Gypsm board and expanding toward corridor 2.5"
6/2/2026 - We did get 2 more sites in Ohio
Adam said they are moving the walls away from anchors so we are clear
only 2 walls changed from IMP, 2 others are still IMP
Michael said Greg told him they are putting walls up next week
Adam said we are 1/2" clear from plate, it will be a field issue installing the plate
Michael said he will talk to paul, he doesn't know what to do, he will call greg
Told Tia I sent snip of Dog Leg Metraflex in chat, didn’t get any smiles
Let her know we have LEB complete, TXE10,1,2 is complete
Adam said he will give link to CIAs, TXE3-12 and LEB3-12 not ready
Adam had meeting with HRV, told them to start using our coordination models for coordination
Quick hello, this is who we are meeting
with MC Dean
Mealnie says they will be updating projects to new architect model
SI will be integrator
Heath introduced Peyton Steveons as VDC supervisor
Starting with HRV
Type F - 4 buildings
Type G - 2 buildings
Melanie introduced Vasi, VDC specialist helping out ron and melanie
Tia went over deliverable schedules
She setup a break out meeting
Per site, per building
6/9/2026 - Adam said they are going to move the MSA, HAC spools to the Lighting Program, for one source
Melanie and Keylan said it can be done
6/30/2026 - FTI wants scanners badged
HRV supposed to get linked in models setup so we can coordinate ug
Need to verify LEB and TXE CIA points
SS Headers are in fab per EAN
John Rhee asked about Waldinger misaligned, we are now good, sending email showing HDR is off
Toms Eng review comments will be looking at doing updates next week
Michael said they have drug test this week, orientation on Monday
HRV Embed Dims, ryan says he has, I have Angle working on them now, wtf?!!!
PIQ, melanie is setting up, I asked her to keep an eye out for the BIM ex plan and contact list
TXE1 special Support approved
H Support hanger, supposed to get stamped this week
7/7/2026 - Cancelled
7/14/2026 - Melanie is going through EMT with cupertino to verify alignment
Isabella asked about clashing HRV, Peyton will be running coordination model for HRV as well as EMT
HRV Embed sheets need to be sent to Basebuild, adam mentioned
Still waiting on word a
7/27/2026 - Adam said Zach gave him the low down on the CIA, it is not a contractual document, it was sebastian telling faith to do it
8/4/2026
8/11/2026 - Michael says all walls are off, asked me and adam to comment, I said get us the points, we can drop them in model, create a document to be used to create an issue and escalate it
HRV, MCD Dean working through hac and pipe clash
I brought up the control point issue at TXE
Metas involved with their surveyors according to Louis Saldana, FTI was supposed to verify with Jennifer
John Rhee says they will need to bring up the bypass support in their next meeting when Tia relayed toms concerened about it
LEB only wants 2 14" skids, need to update maps and bom
John verified there were 11 8" and 6" skids on the BOM package for LEB
He dropped Trimble information into chat
8/25/26 - I updated the Support on Basebuild bypass, said I emailed Trevor at Cerris, no responde
If tom wants more info, we may need to issue an RFI
9/1/26 - Michael was there. I gave a break down of what hensel phelps said in last meeting. They will adjust existing walls for anchors, adjust existing layout for anchors, create cut outs and leave outs for drilling and installing bolts
Michael said they have anchors being sent to site on 9/9 and will start drilling and installing
I gave a break down of the HRV HDPE stub ups, thickening of the slab and anchoring of the UG FW Stubups to compensate for the 6" expansion/ 30k Thrust issues from the HDPE, could affect all jobs
Adam brought up the note from TOm C about Diana re calcing the embeds and causing a change in layout
Phil said he will get with Diana, Michael at TXE said they are installing building 8 right now and looking at installing epoxy anchors in a few weeks.
Neema says stub ups need to be slurried, underground pipes need to be verified for undergound thrust and that passive soil will be sufficient
Above ground thrust will be satisfied by slurry and surrounding footers
Gave thrust block info
MC Dean Bridged files
ENG has electrical equipment
They both have all links turned on, these need turned off
mcd plan for trench moving, not relating to Southland
Danton Wein with MC Dean
MDI has steel and skids, fabrication
Southland
MP Model connections to FW UG Stub ups
Need CWC Bypass, will they be included in the CWC Model we already have or in a separate above ground model?
Ben verified the models are good
Ben then went to stub ups and neema took the convo to RFI something, I said we were going to take a first pass at matching CWC Stub ups
Neema was talking about some kind of trnech shit moving that didn’t apply
7/15/2026 - Adam CWC said no update on the bypass for CWC
7/22/2026 - Talked FWM and MCUP issues mainly
Eli from Colonial was present
Neema says they need to move FW Stup ups away from footer about 5"
Ben and Neema both pointed out CWC can rotate bypass valve to the front, one of the bypasses was already rotated this direction, CWC started to fight back a little bit
This means CW Will need to move their stub ups to get out of way of footers
I mentioned they need to hit the critical North south dimension of 6'-1 5/8" to match the mes skid line, but we can match whatever movement they do east and west
Danton affirmed that the 2 MDC ENG and MCD MDI Models are the current models for the FSHAC
Storefont issues
7/29/2026 - Ben gave dimesnions of shift in DCB2, around 4" toward wall, and will rotate valve
Ben said they are doing things in the field to make sure they hit the 6' - 1 5/8"
Once the shift is completed in DCB2, Ben will ping us
8/12/2026 - Architect asked about information for the Access panel layout, Ben let them know they have been distributed and they were on the email chain
Ben talked about scanning, I brought up us aligning to 3d scan after bypass installed and 3d scans complete
Isabella brought up Wall and anchor proximity, I told them what happened on another site, walls were put up, making it impossible to install anchors
Need to make sure the small distance between embed and wall is achieved
Walls were floating all over the place and not accurate
I told ben we were reconfiguring supports at MES loops so all the clashes with Valve handles will go away
I told team I had DCB90 aligned and published
8/19/2026 - Cancelled
8/26/26 - Cancelled
9/2/26 - Need to switch middle Supports to Cantilever
- Need to look at relocating Exp Tanks to clear fork lift and robotic paths
- Brought up the access panel clash with Cable tray at NWS CD, ben said they will look into it, do possible leave out if need be
- Ben asked about who is receiving embed deliveries, we are still in design stage for nws. Will southland have a representative? Isabella says dpr or concrete should receieve since they are installing. Ben asked for points to assist in install, adam said absolutely
- Isabella asked for verification of date of pour so we can make sure we get them delivered on time, she asked jackson for delivery date to make sure they aren't triple handling, he verified they will be receiving, SI needs to make sure they get packing slips
- Jackson verified february is looking like a good time line for embed delivery
LEB10 FLEX HOSE on 8" Flush skid hitting column, need to clear clashes
talked about email I sent about a list of which models to use for which trades as far as Walls, Wall Panels, Electrical, Arch, Structural etc
Kyle said he was still working on that
John Cowhey is asking about Lugs on the MES
I will chase this down, find who responded Johns email and start there
Robert Cheek responded on Monday saying he would get the answer same day, still waiting
I told Jay we are currently working through shop drawings and spools, while we are doing those we are paying attention to clashes and working through the clashes
I Brought up the FW underground being off and that we will be scanning and verifying CIA POC's, Should be doing this within a week
LUKE SAID HE WILL DISCUSS IN HIS MEETING WITH MORTENSON
JAY ADDED THIS AS AN ACTION ITEM
EMMA SENT EMAIL REQUESTING CLARIFICATION, TRISTEN WAS CONFUSED
5/27/2026 - I BROUGHT UP LEB1 COORDINATING WITH CRIDER NO MODEL, USING HDR FOR UNDERGROUND COORDINATION
JAY BROUGHT UP TXE10 ANCHOR CLASH WITH WALL, ADAM SENT EMAIL ASKING ABOUT IT, SOMEONE SAID THEY WERE CHANGING WALL IN A EMAIL RESPONSE, ADAM REQUESTED MEETING, NO ONE RESPONDED
JAY ADDED THIS AS AN ACTION ITEM
6/3/2026 - New LEB Mech and Plumbing meeting on Wed, John and Reece involved, going over FW stub up locations and F/F water gallery connections
Informed John of Convos with Greg to coordinate wall install with coring of anchor plate holes
Told Jay/John, Lance Holmes is coordinating with other trades on fix for LEB UG FW stubups not hitting POC points or dimensions
6/10/2026 - Verify Span models work on LEB10, 1, 2
6/17/2026 - Checked LEB1, Span_SS model is still only showing Labeled grids, no steel in revit linked model, 2models, same dates, different version, latest verison wont load, gives error
Bring up Walbringer as new MP contractor on LEB6, sent email out with dimension sheets for someone to get them the information
Coordination Sign off
Jay gave links to Turner and HP sign off locations
Clash Review
Jay said he will go through and filter out white noise, setup a meeting to over others. I told him whenever he wants and I will be there
Friday 6/19/22 9am
6/24/2026 - Check with Adam if he verified the lastest info from Crider lining up ug, LEB10
Check LEB1 model HDR Underground lining up with Model, We are lined up with HELM Bypass on LEB10
Luke will get with LEB and Turner for Verifying CIA Points
Louis will get with TXE and HP for Verifying CIA points
LEB6 - MP Model misalignment, I checked the Turner NWD, they are using a FTI Container that may have a misaligned MP NWC
I Put together and new NWD with current NWCs Available and everything lined up correctly
LEB, DCW Drops, Get with John to find out which way they want to go, then follow up with HDR and Helm and Waldinger
I sent John Rhee an email requesting update
7/1/2026 - Jay brought up LEB6 issue I emailed, I told them HDR still needs to update their pipe stup ups, they fixed the grid though
I brought up CIA from other GCs since they were talking about FTI Scanning HP elements, if HP didn't provide documented points what is FTI going to shoot?
Justin said yeah, it is a meta requirement but meta hasn’t really lined out what exactly is required
I told them FTI did such a great job on the document and spearheading it, I was wondering if the other GCs also maintained this document since we are connecting to systems from other trades
Jay follow up with Kyle on HP for going through HP clashing directly, can we access them, create issues, clear?
7/8/2026 - Brought up LEB10 turner models, stay with NWC, even though they have
Advised that I have moved our DCW POCs to match HELM and HDR
Advised of TXE10 Scanning schedule starting tomorrow
Waiting on Patrick B for response on HAC FCU orientation
7/15/2026 - Told Jay, I havent verified Turners FTI Container files are updated this week
TXE Told Jay, Adam noticed the Fan Coils may need rotated 180 degrees, sent email, waiting on Patrick B to look at it
Verify Bypass submittals to FTI for John Cowhey
Check LEB6 FTI Container updated
7/22/2026 - Patrick sent out email saying txe10 FCUs have been reorientated based on Adams email, he will be going to other buildings
John is still waiting for Submittal for EOL HAC Bypass, he is talking to Jacob onsite, need submittal approved and start releasing fab on those
Underground conduit was missed for TWMU Skids, they need to be run overhead, it’s a substantial amount of conduit
Sent John, Justin, Jay the Control Point Map
Told Jay I would do a fly through on Leb10, LEB2 and LEB6 checking for FTI Container alignment
Do we need to do an official submittal for the Dimensions for UG Stub ups and Bypass elevations?
Start using ACC Issues module for tthings like LEB10 Crider stub ups being off
7/29/2026 - John says, he still hasn’t received the Bypass Submittal
I told Jay I would send LEB Control point email from Richard Lopez
I said I would get with Jacob and Keylan to make sure he gets it
I gave low down of what we are scanning, including CP's, what happened with CSV from Kyle
I asked if FTI was doing Trimble next week, john said yes and they will check certain things
I explained how the columns were off, I thought HP should be verifying columns and grid lines, walls may be off
8/5/2026 - They need stub up information for Conduit for the TWMU skid
Alex Harpel says the control points may be off at TXE10, Jennifer will be going through and verifying points
I told Jay, Region 1 alignment looked good, Region 2 I will check at end of week
check leb6 slab elevations different
8/12/2026 - Jay said cerris will be adjusting model based off scans
I made comment in Blue Beam Session for Exp joint hitting MES anchors
Alec said Jennifer says she is ok with Control points at TXE, HP will remove extra brass medallions, once the buidling is turned over, she wwill verify again
I told Jay I will request building control points from Mortenson, Richard Lopez
Get jacob or check status of submittal on HAC Bypass EOL submittals, are they approved?
Verify if Cerris updated TXE10 to match scans
Meta is using XYZ to verify control points, Alec Harpel Verified this
John Cowhey asked if we can put some info together based off Nathan (SI) Trimble information regarding wall and anchor clashes
NO PM/ FIELD TEAM
8/19/26 - Missed, at El Paso FOK/SOK
8/26/26 - Jay is showing a note about EOL Hac Bypass, the last Note shows submittal about Pipe Grade
Need to bring up Bypass Handoff, final scan time, time to create spool, fabricate, deliver and install before Takt schedule, Is Cerris going to verify they are leaving the bypass at HENSEL PHELP scanned asbuilt dimension and do a sign off/ hand off
John asked for an email summarizing this
Jay has entry for TXE10 Anchor (HAC) Bolt coordination, meaning the MES EOL Anchor, John says its being field coordinated
Alec Harpel, asked about JE Dunn asking for Imbed Anchor info for all regions, saying they were pouring concrete, etc
NO FIELD TEAM OR PM TEAM PRESENT
I told jay I looked at LEB6 and alignment looks good, I also republished and exported all new NWC's so everything should be current
Get Luke Jost information from Garrett about the FWM model and sheets and making sure they are updated. Garretts email yesterday said the model was current, they still need to update sheets. He needs all the info for a call later with HDR
TXE CLASH between interior HAC bypass valve handles clashing with FCU frame
John Cowhey brought up floor elevations and having to shim equipment which would through off spools, need to keep randoms in mind
9/2/26 - Jay brought up no progress on in building control points at LEB
- Also brought up setting skids high, shimming up to those points if need be
- I brought up the TXE10/ TXE2 summary of the adjust existing walls, adjust existing layout and the cutouts and leave outs to make sure they were line itemed on the agenda, Jay already had them from the email I sent with the asbuilts
First of a series of daily check in calls between Mcdean, Tate and Southland to make sure we get steel updates from Tate and clash detection
Matt Mcconnell is the PM from Tate
Guin Yaprak verified this is the case, 10-11am tomorrow
Should see new update tomorrow morning
HRV FOK will be in the NWS
MSA will be included
This will be a recurring meeting everyday
8/3/2026 - Isabella told darren about Seths response to my request for consistent elevations, which was no, she said this is unacceptable. Darren said they went to Meta about this whole situation
Isabella said she doesn't understand why Meta got involved, that was unecessary
I informed Darren the current model they were viewing was outdated, the current model from last week shows updated alignment
8/10/2026 - Tom hammered down on Coordination for HAC and clashing, sign off dates
Isabella said we need work together to get this setup
Danton didn't have anything, he is doing MOFE coordination
Tom says we need to align
8/12/26 - Arthur stated the MES will not be moving, the MSA Frame will be adjusted to clear the clash between msa hac and mes anchor
Ryan got pissed that Darren wasn't available, saying this is such a broken proecess, arthur says hes out of his depth, Darren is double booked, Ryan said he needs to be there
Clash is showing flush access panels hitting bus duct on outside of wall
Isabella says since MCDean contracted with SJS to do clash and coordinating, they need to be present and hosting these meetings
Arthur asked Doowoo to assist in getting Darren participation and SJS participation
Ryan asked what kind of end was on the 8" flush skid, Arthur reminded it was hitting a timber column. I said it was a grooved end, we will get it through, even if we have to use a come a long, lol
He asked about the 8" TW Flex skid squeezing through column and mes, clashing, I let him know that was a temporary flush skid with flex pipe, we will get It through
Isabella stated that peyton will be putting together all information, and run through a list of clashing
Peyton showed the SI Duct clash with SI Mech pipe
8/14/26 - Cancelled
8/17/26 - They did a clash flythrough
Showed 6" FW Skid connector fittings hitting Steel frame, need to either turn MES Fiiting out, to face SKID or offset around Steel post
Also showed clashes with strut and supports, strut clamps need to be aligned to supports
Clash with pipe and steel frame, Tom asked why this clash is here but not in EMT and not the programmatic MES/HAC Steel
MCDean says they updated the steel based on CDD(?) before it is finalized, cart before the horse, they are going to do updates for tomorrow meeting
8/18/2026 - Missed, at El Paso for FOK/SOK
8/19/2026 - Missed, at El Paso FOK/ SOK
8/26/26 - This meeting was moved to Tues and Thur, HRV MECH MODEL COORDINATION REVIEW
Ryan said maybe we should be pulling back required dates from fabrication need by dates
Scott did his whole sign off and deliverable schedule rant
We are going to base our Coordination dates form DPRs precon schedule and sign off so that we are signed off with MCDean before DPRs dates
We are supposed to have approved submittals for anchors on 8/21
Document control, Isabella is the point of contact,
Scott explained , need one point of access for Sheets, we are still digging around looking for latest greatest
I obligated to once a week going through clashes, using HRV Forma
Isabella will submitt her stainless steel dog leg expansion for Tom to approve
Isabella will get with Tommy to Verify how many 14" skids they want
Scott asked for a full coordination schedule with dates to hit
Isabella sighed
Isabella said no, we don't have actual dates
7/29/2026
Explained the moving of embed to get out of wall, will move all embed together but will cause actual anchor to shift on the embed placement
Isabella Vesce Rivera
Tomas maxell and chirdon talking to structural engineer about eliminating the middle anchor on DCB100
Adam added couplings to MSA that will allevaite having to add welds for field install
Packages were created in stratus, should be able to get dates by EOW
MSA to HAC needs some couplings removed
Depending on if Ryan can put the couplings on GMP Field because Fab is hard bid
Adam will remove from on site scope, per Ryan
Adam Dial in how we want to name NWS MSA for spool sheets
Adam wants to name them so they are more in line with the stratus packing naming
Deliverables -
Sign off and install schedule
Bridged files from Colonial
Isabella will bring up we need bridged file
I requested to sit on base build coordination meetings with DPR/ Colonial
Adam wants form to access DPR, he will give it to all
8/5/2026
Adam had to push publish, I lost stratus addin, cant find download, gave up
I updated HRV DCB100 and replaced 07 couplings with 107v
Gave isabella the work flow for Layout sheets for hot items, Sign off, Eng Review, Shop Drawings, Spools
7/15/2026
Southland will be running our own Clash Coordination
MC Dean provides a NWC, but we are choosing to use DPRs NWD in our own Model Coordination due to being more current and includes more trades
Keith, Melanie and Peyton will be putting this together
Melanie says not to clash with their NWD, not good
Either we will use DPR Forma Model coordination, if not available, we will ask if we can bridge their models directly to our forma to run our own Model Coordination and clashes
DCB100 NWS1/4 signoff 9/22
DCB100 NWS2/3 signoff 9/29
Waiting on Corbon to yay or nay the middle small anchor
MC Dean is still making adj to hac steel, they did state it shouldn't affect any of our content, ian is supposed to be complete on 9/24
Adam is supposed to put couplings in MSA to stop field weld
Need this update in stratus per Ean
All packages are created in Stratus with Dates
Get with stone and scott about getting FCU in the HAC for HRV
7/22/2026
Gave run down to Thomas and Ryan of Colonial Stub ups
Trhomas says there will be a middle anchor
Peyton will be leading the Coordnation Model and space, will be issueing clashes
Will be running clashes today
Ryan did sent out an email to DPR and colonial web regarding the UG FW CWC Dim sheet showing critical dimensions
8/26/26 - Brought up the issue thats happened witht the bypasses, cerris moving the bypasses after the scans, waiting to see if cerris plans on verifying the final locations match HP's, or if we will need to do a rescan
waiting to hear from engineering as far as if the MES is moving, MC Dean is saying it will be moving, our Engineering has to ok, get submittals, move concrete pillars
Ryan asked Tom Maxwell to get impacts put together for the moving MES, Tom sent an impact out already along with mine
Scott is saying the DEAN MSA HAC was originally designed off a homemade MES from them, not ours, thats why the MSA HAC was 2" off along with the PSK Room being 4" different
Still waitng for approval on 2" expansion dog leg
Need to send Isabella email of Toms impact and mine from moving MES
9/2/26 - Need access to MCDean Coordinated model in order to clear clashes, submit issues, adam shared Files - Build
- Told Isabella DC90 access panels are good, no more changes
- Isabella confirmed EOL bypasses will not be installed at Fab Shop, still seeing if we can install at MC Dean site before delivered to site
- Told Isabella and Ean we need 8 weeks before day zero to finalize MES and Flush loop spools. Ean will be doing these, Vegas is doing skids
- Ian said he will need BOM info for the 2-1/2" SS since they dont have ss rollers
5/14/26 - - Joe Brought up the access panels for Flush system, asked about rating, I would have to check submittals to verify. Me and Lance holmes informed joe the flush systems are temporary, once done, they get removed and the access panel stay
I need to check on RO system, ACCess panel and it looks like location may be borked
Scott asked about sign offs for lighting scope to base build duct connections, Joe said they havent covered it, sign off is around end of June. They will be circling back to loop area not that they have certain paperwork available
Joe said any issue can be brought up at anytime
Anna said they were aware, but not the finalized locations, now they will be going through Valley for engineering, excel engineering to make sure everything is accounted for, engineered
Talked to Stefan, we are not providing the Access Panel, its GC2 wall, they are providing it
5/21/265 - No John Rhee, Brent, Thomas Holler, NO PM TEAM
They went over stud wall model, Lance asking about raceways for security and bus ducts
5/28/2026 - They went over electrical stuff, skid placement, wall leave outs
Turner wants a meeting with Helm and Southland to go over Wall penetrations
Joe D discussed Span model naming, keeping them the same and consistant.
Will need to relink LEB Span models since they have new models with Nucor suffix
6/4/2026 - Eduardo Ibanez brought up Status of Facility Water Stubups asking if Verification of Stubups with Mortenson needed. Had Crider submitted? Lance was saying Ryan would have this info and asking if Ryan was in meeting
NO PM Team present
I sent PM Team a summary email
I explained, Ryan used HDR model for coordination, I worked with HDR to get everything line up, we provided dimensions, everyone agreed to them, now stub ups are off, Lance Resposnded to John Rhees email asking what is being done
I said we need to start having meeting to go over this issue since its so critical
Luke Jost told eduardo to add an action item for this and lance said he will head this off
6/11/2026 - I brought up the FW UG being off again, told the group Ben Kozel with crider said they were backfilling in layers and trying to get the stub ups on the POC/CIA points
Building 6 MES loops are showing misalignment with Waldinger Bypass
NO PM Team present
I said I would like it added to this meetings notes, Joe Dorinsville basically shut it down, saying it was a field issue
I said it was our issue also since we are constantly being asked to do overlays, which were happy to help any way we can, but this was more of a helm situation since they are the responsible party to connect to the UG and provide us with accurate points of contact according to the CIA
Joe reiterated it was a field issue
Overhead Signoff is schedule for 6/30
Scott asked if it was entire building for NWB, Joe says yes
Joe Brought up IMP walls changing to Framed walls, Anna? Said it was still being worked on
Verify LEB10 POC For DCW
Verify DCW POCs line up with CIA
Lance said they are also providing a hose connection for discharge, I stated they are using the FLOOR Drains in center of gallery for discharge, Adam corrected me saying John has requested different discharge points. Wouldn've been nice to know.
Someone asked about the Flex piping from the 8" skid hitting the column, I told them it was flex pipe and temporary, that it will bend around the column
Vent in 6-19x6-D, adam told them to put in between MES Skid
Waldinger is doing the bypass on LEB6
6/18/2026 - Edwin Perez is showing Verification on stub ups w mortneson needed. Pending Submittal. Eng. Drawings to be submitted - Crider and Crider. He said this is still on going
Edwins model view still shows MP Shifted to plan right, access panels were to the right of the wall they are supposed to be in
LEB6 Arch Coordination model is showing everyhting off, MES Skid not lining up, mp is to the right, access panels are to the right of the walls they are supposed to be in.
LEB10, checked with Joe D, things line up there.
6/25/2026 - Joe, Greg, Luke Long, Greg went over Electrical coordination
I sent email to PM Team, no one was present
Eduardo Ibanez brought up Status of Facility Water Stubups asking if Verification of Stubups with Mortenson needed. Had Crider submitted? He brought this up again. I explained again that we provided dimensions for LEB10 and LEB1 to Mortensen, Crider and HDR, they all agreed
I told group that I also emailed these dimensions to Waldinger for Region 2, but havent received any comments or response from anyone.
Scott asked about tracking for signoff on 6/30, eduardo said yes
Luke Jost asked about LEB10 Embeds to make sure they are getting tracked by turner
Edwin Perez asked about Waldinger Bypass and alignment to SI MES Loop Connection
I told Edwin Perez I provided poc dimensions and elevations, but havent received any response
Edwin said he will bring up in next BIM meeting
7/2/2026 - Get with john as far as who is providing what cam lock adapt for fip drops
Lance Holman also provided additional dishcharges (Drains) for Flush/ fill per john
They showed model, HDR DWC Drops are on face of column, I told group IFC shows they are on Web side, HDR Model doesn’t match HDR IFCs
John Rhee is communicating changes from model to FTI, Turner that they are not telling us, Discharge drains, DCW changes
I missed the HDR IFCs showing the drops on the plan south side of corridor
The only reason I found out was because of the meeting flythrough, our pocs were on other side of corridor
John fucking totally ignored our information and didn't relay any information
I explained LEB6 model misalignment was fixed, publishing issue, I will double check mondays model after the Saturday auto publish
I told group about the FW UG Dimension sheet that has been distributed multiple times and it details where the FW UG stubs are supposed to be ever since LEB1
I will double check LEB2 misalignment
They showed LEB6 and the 8" skids were into the columns again
I explained the deep dive I did last week, it shows everything aligned. There are issues with the FTI Container model that Turner is using for coordination
7/9/2026 - Setup LEB2 SI MP View off turner LEB2 Overall Building NWD, Crider is still off at Grid 2-50/ 2-D
Eduardo Ibanez hosted
LEB10
All Content on slab will be created in a file, progress is ongoing. Jay Asked what does this entail? Above Slab content?
LEB6
With joes pulled in NWD that shows us and waldinger aligned, Crider was still off around 8-10"
SI Duct and Waldinger do not align
Justin verified that Turner is using NWC files NOT the revit
Our MP is still out of alignment in Turner LEB6 Overall Building.nwd, but Joe pulled in a recent nwd and it showed the FTI Container inside the Overall nwd is off
Southland MP looks good
Southland MP model is still a little older, but non-critical
7/16/2026 - Joe D brought up some issue about control joints at LEB10, luke jost and jay kaiser will update as necessary
7/22/2026 - Joe D brought up control joint proximity to MP anchors, they scooted 1 at grid 29ish, no TW Skid.
Checking Coord Space at LEB I see Stratus models getting exported again on 7/17, that was last Friday
The only MP model available is from april, what the fuck is going on with this fucking shit
The LBE10 Publish settings were set to stratus, talked to heath, he showed adam was the last one to do it. Adam said he didn’t know had to change settings back
Lance suggested a meeting with FTI and Southland to get power to TW Skids, Lance Long said they have a meeting setup with FTI Tomorrow, looking at junction box on the wall
Jay K at FTI created an issue with Crider Facility Water Alignment and was trying to add crider watchers, he can only add FTI watchers.
Joe D told him to use Triston with Helm, Mitch with Waldinger
Mitch with Waldinger said it looks like its going to work out with aligning their Bypasses with Southland MP
Jay K brought up container models having outdated southland models
Joe D says its tough to say when the FTI container was reloaded. The last update they show was july 13th, 10 days ago
I rbought up the TW Skids on each end of the building also to check, they have anchors also
I stated I found a recommendaiton of 3" distance between an anchor and a sawcut or concrete joint
7/30/2026 - Jay brought up getting control points from Turner
Jay brought up missing MES/ TW skids from LEB1, LEB2 FTI Container, the MP content was aligned
8/6/2026 - I affirmed with Jay, I have not seen any blue beam sessions
I verified LEB 6 in Navis, using the View I created with all trades
James (Turner) is setting up meeting next week to go over CIA points with FTI and Baker
Jay asked about established control points, joe said bring it up in the session
8/13/2026 - Helm modeled their bypasses to the current asbuilt points received Last Friday, This Monday
I told Joe we would wait for the actual asbuilt 3d scans before we do any further model aligning. It’s a waste of time right now, to turn around and have to do it again after scans are received.
8/20/2026 - I told them again we will be able to squeeze the 8" Flex skid around the column, its a flex pipe and not an issue
8/27/26 - Had to leave to go to EMT meeting due to current emt issues
9/3/26 - Eduardo Ibanez hosted
I told lance and Diogo that the Embed Layout shop drawings have been submitted a while ago, Luke Jost verified they have been submitted. They need to use that information for their anchor information
They couldn't see the MES Anchors, they were yellow, me and jay told them to zoom in and they were there.
issue 4250 Duct at leb 6 not aligning to Waldinger duct, sent chat to Stone, talked to him later, the LEB6 FTI Container.nwd is outdated, showing old duct work according to Stone
issue 4236, Joe was asking about our DCW on a column hitting a camera, but ours are just placeholders. The screen shot they showed had the DCW from Helm/ Waldinger on the other column so it was moved.
Melanie Working through EMT Models, links needed repathed
Go Through EMT1 and EMT2 and make sure MES, TW and MP content are good
Also check MSA/FSHAC Piping
IF good, push to Revizto
EMT Does have IFC's for Base Build, Scott showed them yesteday, I coulda swore we didn't have any sheets, prob thinking of HRV
7/16/2026 - Melanie says our MP model doesn’t line up with Eng Model, we are using Lightning Shared Coordinates, Eng is using ETM100
Abe - Attached Sign off schedule to summary email, have content populated and coordinated ahead of signoff dates highlighted in RED, these dates line up with Mortenson
I told her our content, mes content lines up in revizto, if you change anything, it will no longer line up
Download arch model, link our models in and see who lines up
She says archs did change the g datum model a while back, she had to repath it and that’s when things stopped lining up correctly
7/17/2026 - Cancelled
7/20/2026 - Cancelled
7/22/2026 - Ryan says Mortenson is on the verge of issue stop work order with Meta due to electrical incompetetance
7/23/2026 - Cancelled
7/30/2026 - Cancelled
8/6/2026 - Adam said he will cover EMT, I will do the LEB Meeting
8/13/2026 - Cancelled
8/20/2026 - Missed, went to FTI LEB Meeting
8/27/26 - Abe says Mortensen said they will go through and remove duplicate content
Brought up clashes issued to me were showing no clashes when I zoomed into them
also showed the Flush piping and access panels hitting cable tray
9/3/26 - Adam attended, I couldn't since I did the LEB Meeting at 630am
First of a series of daily check in calls between Mcdean, Tate and Southland to make sure we get steel updates from Tate and clash detection
Matt Mcconnell is the PM from Tate
Should see new update tomorrow morning
Guin Yaprak verified this is the case, 10-11am tomorrow
HRV FOK will be in the NWS
MSA will be included
This will be a recurring meeting everyday
8/17/2026 - They did a clash flythrough
Clash with pipe and steel frame, Tom asked why this clash is here but not in EMT and not the programmatic MES/HAC Steel
MCDean says they updated the steel based on CDD(?) before it is finalized, cart before the horse, they are going to do updates for tomorrow meeting
Showed 6" FW Skid connector fittings hitting Steel frame, need to either turn MES Fiiting out, to face SKID or offset around Steel post
Also showed clashes with strut and supports, strut clamps need to be aligned to supports
8/14/2026 - Cancelled
8/3/2026 - Isabella told darren about Seths response to my request for consistent elevations, which was no, she said this is unacceptable. Darren said they went to Meta about this whole situation
I informed Darren the current model they were viewing was outdated, the current model from last week shows updated alignment
Isabella said she doesn't understand why Meta got involved, that was unecessary
8/10/2026 - Tom hammered down on Coordination for HAC and clashing, sign off dates
Danton didn't have anything, he is doing MOFE coordination
Tom says we need to align
Isabella said we need work together to get this setup
8/12/2026 - Arthur stated the MES will not be moving, the MSA Frame will be adjusted to clear the clash between msa hac and mes anchor
Peyton showed the SI Duct clash with SI Mech pipe
Ryan got pissed that Darren wasn't available, saying this is such a broken proecess, arthur says hes out of his depth, Darren is double booked, Ryan said he needs to be there
Clash is showing flush access panels hitting bus duct on outside of wall
Isabella says since MCDean contracted with SJS to do clash and coordinating, they need to be present and hosting these meetings
Arthur asked Doowoo to assist in getting Darren participation and SJS participation
Ryan asked what kind of end was on the 8" flush skid, Arthur reminded it was hitting a timber column. I said it was a grooved end, we will get it through, even if we have to use a come a long, lol
He asked about the 8" TW Flex skid squeezing through column and mes, clashing, I let him know that was a temporary flush skid with flex pipe, we will get It through
Isabella stated that peyton will be putting together all information, and run through a list of clashing
8/17/2026 - No notes, cancelled?
8/18/2026 - Missed, at El Paso for FOK/SOK
8/19/2026 - Missed, at El Paso for FOK/ SOK
8/24/26 - MSA Support foot clash with MES 4.04 is in NWS and the MES 4.03 in the datahalls, datahall clash is smaller
MCDEAN is saying we will have to move the MES into the corridor
Tom and adam explained Anchor shifting 1.5" will cause new submittals, new spooling and parts for MES EOL loops and possibly redesign of the flush skids
MCdean, Danton and Arthur said the msa is 1" wider, they submitted to Meta, scott says the msa is 13'-2" and the other are 13'-0", thats 2"
Tom brough up shifting the MSA supports next to MES toward the FSHAC to clear the clash, MCDean was iffy about whether they looked at that
8/27/26 - TW at MES EOL is clashing with hac frame
Darren said they need to remove the MTR Frame, its still there
Need to check TW at MSA Supports dont line up, steel is missing support
Check Flushing misc piping and parts at NWS clashing on MES and HAC
I brought up the flush piping /access panel clash with cable tray which will be covered in the DPR coordination meeting that isnt happening right now
Darren said those cable trays should be getting installed after flush/ fill due to interfering with moving flush skids, he measured cable tray, it was 10-11 feet AFF
9/3/26 - Darren went through a few clashes, a lot of MSA legs still need rotated, most of those clashes will be cleard. Including a msa leg hitting anchor
Will need to look at rotating a few couplings to clear other clashes
Showed lifting lugs getting removed to clear clash with flush fittings
Some of the TW Header clamps were inside pipe and the pipe was hitting supports. MCDean said they did set hacs at about 1/2" high to compensate for concreate hi-low, they will shim
Kaushal Bagdekar with Turner ran the meeting, saying who to contact for what, I asked if he could send an email with that info
They went over underground clashes
5/28/2026 - Tristen with helm verified he is using LEB1 dimensions for LEB 2 elevations and locaitons for FW
6/11/2026 - No PM Team
Went Over UG issues, concrete pads
6/18/2026 - Kaushal Bagdekar
Did a flythrough for LEB2 going over exterior sectionalizers
LEB-2_SPAN_SS.rvt, verifying during meeting that the model is good, Checked LEB2 SPAN_SS model, couldn’t load content, says cant link in NuCOR
NO Interior Walls and framing, Valley, Diogo or Ruth said they will get with valley
No Interior Meta Wall Panels
6/25/2026 - NO PM TEAM
They went over UG issues for LEB2
7/2/2026 - LEB2, Showed model where Helm, SI and Crider not aligned, #2070
LEB2 Building Overall actually has Crider model, showing misaligned
Grid 1-50, 1-D is the only spot where Crider is off looking at Turners LEB2_Building_Overall model only
Everything else is aligned, MP, Duct, Steel, Walls, no issues
Sent email showing misaligned concrete and crider stub ups at 2-50
LEB-SI-MP-LEB2-R25 model lined up identical to LEB2-Building-Overall
Didn't see new DCW POC valves, did I update LEB2
Did see FLUSH VENTS AND DRAINS, VENT ON 2-50 IS OFF
7/9/2026 - Sent Email to Joe, Jay, Edwin, Eduardo and Joe forwarded to Kaushal
Kaushal asked about flush skids in front of door ways, need to send them a time frame for flushing before equipment gets removed
Concrete elevations different at Gird 2-29 and 2-32
Crider stub ups off at 2-50/2-D
Added to chat
7/16/2026 - Sent email to Triston with Jay and Kaushal cc'd about Helm bypass flanges not aligning to SI MP Flanges throughout building
LEB2 looked like it aligned good
7/22/2026 - No southland issues covered
7/30/2026 - Just went over non-southland issues
I dropped for LEB Mortenson meeting at 1000am
8/13/2026 - NO PM/ FIELD TEAM
Ouch, Kaushal called out Triston for not being in the meeting 3 weeks now
Had Kaushal remove the waiting on southland to add content we are waiting for, under MP Pipe - Triston, he labeled it closed
Dropped out at 10am for Mcdean Hac Meeting
8/20/2026 - They went over support pads in yards and clashes on exterior., I dropped for 10am LEB Mortenson meeting
8/27/26 - Just went over all other trades and issues, Triston said no issues from Helm, dropped early for LEB BIM Coordination Meeting with Richard lopez
8/20/26 - Asked Richard Lopez if anyone is using shared building Control Points, him and nick both deferred to turner. I said I am used to a site wide control point map that is shared with all trades. I understand this is a bit of unique job with 3 GCs though
Richard corrected his statement and said turner actually did have a meeting last week with him and Nick, he wasn't sure if it was a recurring meeting but would look at getting information dispersed.
Ryan Zoldan - Richard Lopez
I requested a schedule from Ryan, he has the sign off, region schedule, I brought up a pull plan, be he says that will be through Turner
Mortensen is the Base build GC, why aren't they leading a pull plan schedule
John Rhee nor Brent were in this meeting
LEB 6 due finalized next week
6/4/2026 - I brought up the LEB10 FW UG Stub ups totally missing the Dims, Ben Kozel was there and he stated they are bringing them back in to dimensions by backfilling a little and moving them, backfilling and moving them
He acknowledge that lance did contact him
6/11/2026 - Ben Kozel, said there were no issues that need to be talked about.
Richard lopez asked around the room for any issues regarding LEB10 or any others
NO PM Team
6/18/2026 - Richard Lopez Hosted, just asked for any issues with LEB10,1,2,3 Underground issues
Rantwiler asked when IWM for TXE10 was going to be signed off, Ethan says he will talke to kyle since they are not really split out
6/25/2026 - Going over LEB7,8
Ryan brought up LEB6, HDR model is not lining up with the Dimensions provided by SI
Ryan henderson said he will follow up
Ryan said we have all agreed to follow these dimesions, I added that I have distrubuted that dimesion sheet ot Waldinger and explained everything, but havent received a response yet
Ryan brought up LEB6, HDR model is not lining up and my email I sent out
Ryan said Crider is using civil 3d, but we can work it out to actually use their model for coordination and linking in so I don't have to use HDR
I updated, still waiting for HDR to align the stubups
7/9/2026 - No issues to cover, they went over UG clashing for elect, sanitary
7/23/2026 - Richard asked Triston about any alingment issues, he was good
Ben said LEB6 stil had some very minor HDR alignment issues to on udergoung
7/30/2026 - Bend said LEB6 looked good
I said we republished LEB6, there was some extra content we had to remove
8/6/2026 - I brought up the LEB10 FW UG Stub ups totally missing the Dims, Matt Schaff said they are doing repairs this week and lookingat getting into within an inch
I mentioned, for helms benefit of using Eccentric reducers on bypass in order to rotate the stubup to align with MES better
I also mentioned after slab is poured, bypasses installed, we look at doing 3d scans
8/27/26 - No issues were brought up. I was going to bring up control points, but Im done. Ive asked, sent out emails no one has responded except jay kaiser
TXE1 looks good for the loop area sign off next week
Same with TXE2
6/4/2026 - Own B ran the meeting going over TXE1 and 2
6/11/2026 - Owen B, says TXE10 Loop for sign off
TXE2 Core scheduled for next week
TXE10 AB Datahall and Loop are signed off
TXE3 Alan lopez is running region 2 for signe off
TXE2 Loop and AB South sign off
issue 2602 - Cerris Vent in corner is clashing with Technical water, Rantwiler is saying they don’t have our model, I told them our model has been there for 6 months, the fact that HP is viewing it, means the model is available. If it’s a bridging issue we will help Cerris work it out
Trevor said he will get with rantwiler and get the model bridged, they will offset that vent around our TW Piping
They made comments about the TW skid being so close to the FW valves. Its been this way for over 6 months. Trevor also stated the vent will need an accessible cleanout
6/25/2026 - They just went over IWM and specific Electrical clashes
7/9/2026 - TXE 2 all docs are out, all sign offs are out
TXE1, 2 sign offs left
DHCD 2 weeks from now
7/22/2026 - No Issues
8/20/2026 - They didn't cover anything relevant to us.
Verify 107V and 07 Couplings on Pup pieces, region 1
Adam said we are still working through comments, still waiting on cantilever approval.
LEB10,1,2 will be good to push out to submit to tom
Need to update regions to datahall A,B,C,D
Day zero is 2/25/27
Need spools before 1/5/27, Adam said we wiill shoot for 6-8 weeks before then to allow for review, updates, etc
8/28/26 - Cancelled
Scott says EORs get officially submitted to Tom, he approves, they get submitted to FTI. Not sure if EORs get submitted to Meta or not as part of record drawings
Scott says by Friday the 14th they will publish to stratus
Embed Layout Drawings
We gave drawings, we will have
Crider and Mortenson will provide scans once they are finished, so that helm can update their bypass.
Flush Skid BOM, Curtis used TXE Counts and ordered the material
Hose Carts are still being finalized
Get Reece copies of TXE Flush skid BOM information
Hose Carts will be finalized once FOK and SOK are done
No pour until november
Schedule model? Can we incorporate this?
LEB10 UG Stubup status
Crider, Mike Schaff said they were doing repairs this week
Make sure LEB PM Team knows we need to scan after slab, after bypasses installed, then we align, update spools
8/14/2026 - Cancelled
8/21/2026 - Bring up mentioning Control Points in Meeting yesterday with Richard Lopez (Mortneson), says they dont have any Interior building control points, get with Turner, then said they had a meeting last week with turner, he will check if its recurring
Talked about the 30 email chains from Lance, Jake Wright, Casey, Triston and Ben. The lastest is from Helm asking if their points are good.
Talk to triston about their flush fill, are they using the existing bypass or adding a temp one?
9/4/26 - Adam resubmitting 18" Foot on Cantilever since approved 16" is hitting wall
Adam is asking tom to put small feet on anchors to be welded onto embeds, havent heard anything back from Tom
Need to bring up Control Points - Last I heard from Richard Lopez, he said they had previous meetings between Mortenson and Turner, he was going to check if it was recurring and get us invited. He said they DO NOT have any shared interior building CP's
I relayed this info to Jay Kaiser and Justin Jenkins at FTI, haven't heard anything back
Look up Helms last email on the FW UG Stub ups
November is pour date for LEB10
Reece said he will get with HELM on if they are using Temp Bypass for their flush and fill
Reece said he will coordinate with Richard Lopez, Lance Holman, Jay K, Justin J on control points and getting shared points establishes and shared
Stainless headers will be used in LEB2 from Reece, the stainless headers are bigger, clash with supports, FTI will need to adjust supports for Stainless headers. Reece will get with Keylan at TXE10
Jake brought up the added ports, I explained the email and the status, need all PMs to agree on adding over 500 ball valves per project
8/17/26 - Ryan Ran the meeting, couldnt get the agenda up, lol, asked peyton to go over clashes, peyton said he wasn't ready, then Ryan did a round table, no body had anything to
8/24/26 - Didn't really go over anything, Ryan Warner, we ended early. Ryan Warner started a new meeting at 712am, he was late
Peyton showing MES MP Pipeing into duct and framing, mic didn't work so I couldn’t talk to verify MES Elevations
8/3/2026 - Abe said UCO3 UG Signoff is pushed to next week
Peyton going over clashes
#816 shows vesda FP content going through our bypass at hac, adam modeled the vesda
MH Duct at EMT1 was low, scott said he will take a look
8/10/2026 - Melanie says she will look at MES Alignment, I said on Saturday mes was mis-aligned again
Adam said he will fix Vesda Clash with HAC EOL Bypass
I said the MES Loop/ Flush Loop piping needs to be reconfigured, its clashing with TWMU Skid, the tee will get rolled to vertical and cantilever pipe supports will be brought in
First of a series of daily check in calls between Mcdean, Tate and Southland to make sure we get steel updates from Tate and clash detection
Matt Mcconnell is the PM from Tate
Should see new update tomorrow morning
Guin Yaprak verified this is the case, 10-11am tomorrow
HRV FOK will be in the NWS
MSA will be included
This will be a recurring meeting everyday
8/3/2026 - Isabella told darren about Seths response to my request for consistent elevations, which was no, she said this is unacceptable. Darren said they went to Meta about this whole situation
I informed Darren the current model they were viewing was outdated, the current model from last week shows updated alignment
Isabella said she doesn't understand why Meta got involved, that was unecessary
8/10/2026 - Tom hammered down on Coordination for HAC and clashing, sign off dates
Danton didn't have anything, he is doing MOFE coordination
Tom says we need to align
Isabella said we need work together to get this setup
8/12/2026 - Arthur stated the MES will not be moving, the MSA Frame will be adjusted to clear the clash between msa hac and mes anchor
Ryan asked what kind of end was on the 8" flush skid, Arthur reminded it was hitting a timber column. I said it was a grooved end, we will get it through, even if we have to use a come a long, lol
He asked about the 8" TW Flex skid squeezing through column and mes, clashing, I let him know that was a temporary flush skid with flex pipe, we will get It through
Isabella stated that peyton will be putting together all information, and run through a list of clashing
Peyton showed the SI Duct clash with SI Mech pipe
Ryan got pissed that Darren wasn't available, saying this is such a broken proecess, arthur says hes out of his depth, Darren is double booked, Ryan said he needs to be there
Clash is showing flush access panels hitting bus duct on outside of wall
Isabella says since MCDean contracted with SJS to do clash and coordinating, they need to be present and hosting these meetings
Arthur asked Doowoo to assist in getting Darren participation and SJS participation
8/14/2026 - Cancelled
8/17/2026 - They did a clash flythrough
Showed 6" FW Skid connector fittings hitting Steel frame, need to either turn MES Fiiting out, to face SKID or offset around Steel post
Also showed clashes with strut and supports, strut clamps need to be aligned to supports
Clash with pipe and steel frame, Tom asked why this clash is here but not in EMT and not the programmatic MES/HAC Steel
MCDean says they updated the steel based on CDD(?) before it is finalized, cart before the horse, they are going to do updates for tomorrow meeting
6/1/2026 - Noel Nunez says Alehandro Chew will be safety manager
Michael said he sent TXE3 embeds along with PDF dimension in mid April
Doesn’t think TXE3 has been poured, think they are behind schedule
Says we havent been funded for Region 2, he is sending out embeds as needed
Michael asked what the question was about RO and TW, I said it was going over how to connect to the RO skid, from DCW and to TW MES
Michael asked if MES Loops were completed, adam said yes, he created new BOMs
Michael said his goal is to get everything ordered
Michale Paul said they thought the walls weren't going to be in until they could do anchor
They said that was what was agreed to
6/8/2026 - Michael said they had a PM Coins Mandatory meeting and couldn't host the meeting
6/15/2026 - Chris Moss came on board from TSMC, Pipe fitter, GF
Jose Alejandro Chew, new Safety Manager for TXE
6/22/2026 - Shop drawings (Engineer Drawings) looking at submittal on Frid, 6/26
6/29/2026 - Keylan Cancelled
7/6/2026 - Carson will scan on Thursday
7/13/2026 - Scans on TXE10 complete, should have done this week, EOW
Jacob will be pulling field measurements of FW Stub ups
Adam will overlay scans to see how they match up with our Stub Ups
SOK will be starting next week, 27th will have more setup covered
7/16/2026 - Zach wants scanning sent back out, scan off control points, need to get CPs from Greg, put in model, talk to carson to see what they need from us
Control points were requested on 6/12 meeting with Greg H, it was stated they would be sent to Michal and James Homrighausen
I also asked for control points from Luke Justice on 5/21, he said he would get with Greg H.
They made it out like it was detailing fault they scanned without using control points
Paul asked how soon I can get the points into model, I said immediately, but Im not sure scanning needs anything from us, they may input control points into the rcap software maually but we will have it the model if they need it
7/27/2026 - Scanning this week
FTI Will be doing Trimble next week
8/3/2026 - Adam brought up new pipe supportts that were sent to Tom due to more access to mes loop valves
Adam asked about tapped caps for mes connections, michael said it was a miss on them so they will cover it
Trimble is shooting wall points tomorrow and Wednesday
8/10/2026 - Asked about txe2, keylan said they have bottom plate down, trimble is showing walls off
Asked about info for points from trimble, is this for field use only, are they showing HP where walls are off
Keylan says they are using the info to show HP were walls are off, TXE1 had walls off, HP is still working on solutions
I asked for TXE2 Cerris bypass schedule so we can get scanning out
He said he would get me that info
Need to ask about Access panels, whos providing?
Need to ask about info for HP saying they are having issues with control point discrepancies
Keylan said he will double shcek with paul and nate
Paul says he hasn't heard anything about control points, alec says HP is suggesting we move our anchors
FTI says Jennifer is gong to get involved and veriy, Meta says they will send their own Surveyors out to verify, this was last I heard
I will put together an email of who said what in which meeting and send to keylan to start a chain
8/17/2026 - Cancelled
8/24/26 - Jacob went through agenda. Boots on the ground "soon", they had exterior and interior walls up on TXE2, how do we not have boots on the ground now?
Nate is supposed to be trimbling the rest of TXE1, I didn't know TXE1 was even poured and ready
Keylan said he has to verify Control points. They were going to take it off agenda. I told them the medallions werent identified or center punched, Keylan told jacob he needs to get with Alec, I suggested filling out an issue on FTI site abou this, keylan agreed
8/31/26 - Keylan said he hasn't followed up with Alex about center punching Control point medallions and identifying them
day zero is 12/14/26, this got pushed from 11/14, they may be able to get an early start on 11/14
I was late talking to Isabella, caught tail end of meeting.
7/27/2026 - Missed, went to Cameron Shop to meet Mid Atlantic Crew
8/10/2026 - Start detaiing on Texas Carusoe for Engineering
Ed Meza doing tips and tricks on Revizto
8/17/2026 - Cancelled
8/24/26 - Cancelled
8/31/26 - Asking about AVD Issues
Be careful of what you say or do in Teams, its always a reflection of Southland.
We will be starting a new detailing job at San Jose New Mexico, also looked at a sister project at Las Vegas. If anyone knows someone with detailing experience, Southland is hiring
Jaime is up for Tips and Tricks - using ribbon for quick commands
Ed Meza also shared section views and how to shorten it up quicker,
7/27/2026 - Missed, went to Cameron Shop to meet Mid Atlantic Crew
8/17/2026 - Went over UG and sign off dates. EMT1 Sign off on hold due to CDD1 change, looking to still start coordinating knowing they will need to incorporate the changes after the fact
8/24/2026 - Going over drone shots, showing UG progress
Melanie Working through EMT Models, links needed repathed
Go Through EMT1 and EMT2 and make sure MES, TW and MP content are good
IF good, push to Revizto
Also check MSA/FSHAC Piping
EMT Does have IFC's for Base Build, Scott showed them yesteday, I coulda swore we didn't have any sheets, prob thinking of HRV
7/16/2026 - Melanie says our MP model doesn’t line up with Eng Model, we are using Lightning Shared Coordinates, Eng is using ETM100
Abe - Attached Sign off schedule to summary email, have content populated and coordinated ahead of signoff dates highlighted in RED, these dates line up with Mortenson
I told her our content, mes content lines up in revizto, if you change anything, it will no longer line up
Download arch model, link our models in and see who lines up
She says archs did change the g datum model a while back, she had to repath it and that’s when things stopped lining up correctly
7/17/2026 - Cancelled
7/20/2026 - Cancelled
7/22/2026 - Ryan says Mortenson is on the verge of issue stop work order with Meta due to electrical incompetetance
7/23/2026 - Cancelled
7/30/2026 - Cancelled
8/6/2026 - Adam said he will cover EMT, I will do the LEB Meeting
8/13/2026 - Cancelled
8/18/2026 - Missed, at EL PASO FOK/SOK
8/24/2026 - Went over WPI and hac frames, new DCIS about SKU Numbering, Updating the model to make sure its accurate.
First of a series of daily check in calls between Mcdean, Tate and Southland to make sure we get steel updates from Tate and clash detection
Matt Mcconnell is the PM from Tate
Should see new update tomorrow morning
Guin Yaprak verified this is the case, 10-11am tomorrow
HRV FOK will be in the NWS
MSA will be included
This will be a recurring meeting everyday
8/17/2026 - They did a clash flythrough
Showed 6" FW Skid connector fittings hitting Steel frame, need to either turn MES Fiiting out, to face SKID or offset around Steel post
Also showed clashes with strut and supports, strut clamps need to be aligned to supports
Clash with pipe and steel frame, Tom asked why this clash is here but not in EMT and not the programmatic MES/HAC Steel
MCDean says they updated the steel based on CDD(?) before it is finalized, cart before the horse, they are going to do updates for tomorrow meeting
8/14/2026 - Cancelled
8/3/2026 - Isabella told darren about Seths response to my request for consistent elevations, which was no, she said this is unacceptable. Darren said they went to Meta about this whole situation
I informed Darren the current model they were viewing was outdated, the current model from last week shows updated alignment
Isabella said she doesn't understand why Meta got involved, that was unecessary
8/10/2026 - Tom hammered down on Coordination for HAC and clashing, sign off dates
Danton didn't have anything, he is doing MOFE coordination
Tom says we need to align
Isabella said we need work together to get this setup
8/12/2026 - Arthur stated the MES will not be moving, the MSA Frame will be adjusted to clear the clash between msa hac and mes anchor
He asked about the 8" TW Flex skid squeezing through column and mes, clashing, I let him know that was a temporary flush skid with flex pipe, we will get It through
Isabella stated that peyton will be putting together all information, and run through a list of clashing
Peyton showed the SI Duct clash with SI Mech pipe
Ryan got pissed that Darren wasn't available, saying this is such a broken proecess, arthur says hes out of his depth, Darren is double booked, Ryan said he needs to be there
Clash is showing flush access panels hitting bus duct on outside of wall
Isabella says since MCDean contracted with SJS to do clash and coordinating, they need to be present and hosting these meetings
Arthur asked Doowoo to assist in getting Darren participation and SJS participation
Ryan asked what kind of end was on the 8" flush skid, Arthur reminded it was hitting a timber column. I said it was a grooved end, we will get it through, even if we have to use a come a long, lol
8/17/2026 - No notes, cancelled?
8/18/2026 - Missed, at El Paso for FOK/SOK
8/19/2026 - Missed, at El Paso for FOK/ SOK
8/24/26 - MSA Support foot clash with MES 4.04 is in NWS and the MES 4.03 in the datahalls, datahall clash is smaller
MCDEAN is saying we will have to move the MES into the corridor
Tom and adam explained Anchor shifting 1.5" will cause new submittals, new spooling and parts for MES EOL loops and possibly redesign of the flush skids
MCdean, Danton and Arthur said the msa is 1" wider, they submitted to Meta, scott says the msa is 13'-2" and the other are 13'-0", thats 2"
Tom brough up shifting the MSA supports next to MES toward the FSHAC to clear the clash, MCDean was iffy about whether they looked at that
Follow up on HAC Panel clashes with Patrick Brinnehal
Meeting to go over stratus and models with all PMs, Adam, Scott, Supers sometime next week, look at schedules
Chris Chase is the PM of EMT
5/26/2026 - Check if Adam got the 4" Welded Bypass to Shop, from 5/5/25 email in Inbox "Im shooting to have the LTG build out scope package done by end of week (For Review only not for construction). "
Need meeting to discuss, txe10 anchor clashing with interior of walls, adam sent info out about conflicting models, but as of today, there is still clashes
RFI says they are changing wall to Gypsm board and expanding toward corridor 2.5"
Verify what spools have been put on stratus for TIA/TOM Lightning huddle
6/2/2026 - We did get 2 more sites in Ohio
Melanie introduced Vasi, VDC specialist helping out ron and melanie
Tia went over deliverable schedules
Per site, per building
She setup a break out meeting
Adam said they are moving the walls away from anchors so we are clear
Adam said we are 1/2" clear from plate, it will be a field issue installing the plate
Michael said he will talk to paul, he doesn't know what to do, he will call greg
only 2 walls changed from IMP, 2 others are still IMP
Michael said Greg told him they are putting walls up next week
Told Tia I sent snip of Dog Leg Metraflex in chat, didn’t get any smiles
Let her know we have LEB complete, TXE10,1,2 is complete
Adam said he will give link to CIAs, TXE3-12 and LEB3-12 not ready
Adam had meeting with HRV, told them to start using our coordination models for coordination
Quick hello, this is who we are meeting
with MC Dean
Mealnie says they will be updating projects to new architect model
SI will be integrator
Heath introduced Peyton Steveons as VDC supervisor
Starting with HRV
Type F - 4 buildings
Type G - 2 buildings
6/9/2026 - Adam said they are going to move the MSA, HAC spools to the Lighting Program, for one source
Melanie and Keylan said it can be done
6/30/2026 - FTI wants scanners badged
HRV Embed Dims, ryan says he has, I have Angle working on them now, wtf?!!!
PIQ, melanie is setting up, I asked her to keep an eye out for the BIM ex plan and contact list
TXE1 special Support approved
H Support hanger, supposed to get stamped this week
HRV supposed to get linked in models setup so we can coordinate ug
Need to verify LEB and TXE CIA points
SS Headers are in fab per EAN
John Rhee asked about Waldinger misaligned, we are now good, sending email showing HDR is off
Toms Eng review comments will be looking at doing updates next week
Michael said they have drug test this week, orientation on Monday
7/7/2026 - Cancelled
7/14/2026 - Melanie is going through EMT with cupertino to verify alignment
Isabella asked about clashing HRV, Peyton will be running coordination model for HRV as well as EMT
HRV Embed sheets need to be sent to Basebuild, adam mentioned
Still waiting on word a
7/27/2026 - Adam said Zach gave him the low down on the CIA, it is not a contractual document, it was sebastian telling faith to do it
8/4/2026
8/11/2026 - Michael says all walls are off, asked me and adam to comment, I said get us the points, we can drop them in model, create a document to be used to create an issue and escalate it
HRV, MCD Dean working through hac and pipe clash
I brought up the control point issue at TXE
Metas involved with their surveyors according to Louis Saldana, FTI was supposed to verify with Jennifer
John Rhee says they will need to bring up the bypass support in their next meeting when Tia relayed toms concerened about it
LEB only wants 2 14" skids, need to update maps and bom
John verified there were 11 8" and 6" skids on the BOM package for LEB
He dropped Trimble information into chat
8/25/26 - I updated the Support on Basebuild bypass, said I emailed Trevor at Cerris, no responde
If tom wants more info, we may need to issue an RFI
Neema says stub ups need to be slurried, underground pipes need to be verified for undergound thrust and that passive soil will be sufficient
Above ground thrust will be satisfied by slurry and surrounding footers
MC Dean Bridged files
Danton Wein with MC Dean
MDI has steel and skids, fabrication
ENG has electrical equipment
They both have all links turned on, these need turned off
mcd plan for trench moving, not relating to Southland
Southland
MP Model connections to FW UG Stub ups
Need CWC Bypass, will they be included in the CWC Model we already have or in a separate above ground model?
Ben verified the models are good
Ben then went to stub ups and neema took the convo to RFI something, I said we were going to take a first pass at matching CWC Stub ups
Neema was talking about some kind of trnech shit moving that didn’t apply
7/15/2026 - Adam CWC said no update on the bypass for CWC
7/22/2026 - Talked FWM and MCUP issues mainly
Eli from Colonial was present
Neema says they need to move FW Stup ups away from footer about 5"
I mentioned they need to hit the critical North south dimension of 6'-1 5/8" to match the mes skid line, but we can match whatever movement they do east and west
Ben and Neema both pointed out CWC can rotate bypass valve to the front, one of the bypasses was already rotated this direction, CWC started to fight back a little bit
This means CW Will need to move their stub ups to get out of way of footers
Danton affirmed that the 2 MDC ENG and MCD MDI Models are the current models for the FSHAC
Storefont issues
7/29/2026 - Ben gave dimesnions of shift in DCB2, around 4" toward wall, and will rotate valve
Ben said they are doing things in the field to make sure they hit the 6' - 1 5/8"
Once the shift is completed in DCB2, Ben will ping us
8/12/2026 - Architect asked about information for the Access panel layout, Ben let them know they have been distributed and they were on the email chain
Ben talked about scanning, I brought up us aligning to 3d scan after bypass installed and 3d scans complete
Isabella brought up Wall and anchor proximity, I told them what happened on another site, walls were put up, making it impossible to install anchors
Walls were floating all over the place and not accurate
Need to make sure the small distance between embed and wall is achieved
I told ben we were reconfiguring supports at MES loops so all the clashes with Valve handles will go away
LEB10 FLEX HOSE on 8" Flush skid hitting column, need to clear clashes
talked about email I sent about a list of which models to use for which trades as far as Walls, Wall Panels, Electrical, Arch, Structural etc
Kyle said he was still working on that
John Cowhey is asking about Lugs on the MES
I will chase this down, find who responded Johns email and start there
Robert Cheek responded on Monday saying he would get the answer same day, still waiting
I told Jay we are currently working through shop drawings and spools, while we are doing those we are paying attention to clashes and working through the clashes
I Brought up the FW underground being off and that we will be scanning and verifying CIA POC's, Should be doing this within a week
LUKE SAID HE WILL DISCUSS IN HIS MEETING WITH MORTENSON
JAY ADDED THIS AS AN ACTION ITEM
EMMA SENT EMAIL REQUESTING CLARIFICATION, TRISTEN WAS CONFUSED
5/27/2026 - I BROUGHT UP LEB1 COORDINATING WITH CRIDER NO MODEL, USING HDR FOR UNDERGROUND COORDINATION
JAY BROUGHT UP TXE10 ANCHOR CLASH WITH WALL, ADAM SENT EMAIL ASKING ABOUT IT, SOMEONE SAID THEY WERE CHANGING WALL IN A EMAIL RESPONSE, ADAM REQUESTED MEETING, NO ONE RESPONDED
JAY ADDED THIS AS AN ACTION ITEM
6/3/2026 - New LEB Mech and Plumbing meeting on Wed, John and Reece involved, going over FW stub up locations and F/F water gallery connections
Informed John of Convos with Greg to coordinate wall install with coring of anchor plate holes
Told Jay/John, Lance Holmes is coordinating with other trades on fix for LEB UG FW stubups not hitting POC points or dimensions
6/10/2026 - Verify Span models work on LEB10, 1, 2
6/17/2026 - Checked LEB1, Span_SS model is still only showing Labeled grids, no steel in revit linked model, 2models, same dates, different version, latest verison wont load, gives error
Bring up Walbringer as new MP contractor on LEB6, sent email out with dimension sheets for someone to get them the information
Coordination Sign off
Jay gave links to Turner and HP sign off locations
Clash Review
Jay said he will go through and filter out white noise, setup a meeting to over others. I told him whenever he wants and I will be there
Friday 6/19/22 9am
6/24/2026 - Check with Adam if he verified the lastest info from Crider lining up ug, LEB10
Check LEB1 model HDR Underground lining up with Model, We are lined up with HELM Bypass on LEB10
Luke will get with LEB and Turner for Verifying CIA Points
Louis will get with TXE and HP for Verifying CIA points
LEB6 - MP Model misalignment, I checked the Turner NWD, they are using a FTI Container that may have a misaligned MP NWC
I Put together and new NWD with current NWCs Available and everything lined up correctly
LEB, DCW Drops, Get with John to find out which way they want to go, then follow up with HDR and Helm and Waldinger
I sent John Rhee an email requesting update
7/1/2026 - Jay brought up LEB6 issue I emailed, I told them HDR still needs to update their pipe stup ups, they fixed the grid though
I brought up CIA from other GCs since they were talking about FTI Scanning HP elements, if HP didn't provide documented points what is FTI going to shoot?
Justin said yeah, it is a meta requirement but meta hasn’t really lined out what exactly is required
I told them FTI did such a great job on the document and spearheading it, I was wondering if the other GCs also maintained this document since we are connecting to systems from other trades
Jay follow up with Kyle on HP for going through HP clashing directly, can we access them, create issues, clear?
7/8/2026 - Brought up LEB10 turner models, stay with NWC, even though they have
Advised that I have moved our DCW POCs to match HELM and HDR
Advised of TXE10 Scanning schedule starting tomorrow
Waiting on Patrick B for response on HAC FCU orientation
7/15/2026 - Told Jay, I havent verified Turners FTI Container files are updated this week
TXE Told Jay, Adam noticed the Fan Coils may need rotated 180 degrees, sent email, waiting on Patrick B to look at it
Verify Bypass submittals to FTI for John Cowhey
Check LEB6 FTI Container updated
7/22/2026 - Patrick sent out email saying txe10 FCUs have been reorientated based on Adams email, he will be going to other buildings
John is still waiting for Submittal for EOL HAC Bypass, he is talking to Jacob onsite, need submittal approved and start releasing fab on those
Underground conduit was missed for TWMU Skids, they need to be run overhead, it’s a substantial amount of conduit
Sent John, Justin, Jay the Control Point Map
Told Jay I would do a fly through on Leb10, LEB2 and LEB6 checking for FTI Container alignment
Do we need to do an official submittal for the Dimensions for UG Stub ups and Bypass elevations?
Start using ACC Issues module for tthings like LEB10 Crider stub ups being off
7/29/2026 - John says, he still hasn’t received the Bypass Submittal
I told Jay I would send LEB Control point email from Richard Lopez
I said I would get with Jacob and Keylan to make sure he gets it
I gave low down of what we are scanning, including CP's, what happened with CSV from Kyle
I asked if FTI was doing Trimble next week, john said yes and they will check certain things
I explained how the columns were off, I thought HP should be verifying columns and grid lines, walls may be off
8/5/2026 - They need stub up information for Conduit for the TWMU skid
Alex Harpel says the control points may be off at TXE10, Jennifer will be going through and verifying points
I told Jay, Region 1 alignment looked good, Region 2 I will check at end of week
check leb6 slab elevations different
8/12/2026 - Jay said cerris will be adjusting model based off scans
I made comment in Blue Beam Session for Exp joint hitting MES anchors
Alec said Jennifer says she is ok with Control points at TXE, HP will remove extra brass medallions, once the buidling is turned over, she wwill verify again
I told Jay I will request building control points from Mortenson, Richard Lopez
Get jacob or check status of submittal on HAC Bypass EOL submittals, are they approved?
Verify if Cerris updated TXE10 to match scans
Meta is using XYZ to verify control points, Alec Harpel Verified this
John Cowhey asked if we can put some info together based off Nathan (SI) Trimble information regarding wall and anchor clashes
NO PM/ FIELD TEAM
8/19/26 - Missed, at El Paso FOK/SOK
8/26/26 - Jay is showing a note about EOL Hac Bypass, the last Note shows submittal about Pipe Grade
Need to bring up Bypass Handoff, final scan time, time to create spool, fabricate, deliver and install before Takt schedule, Is Cerris going to verify they are leaving the bypass at HENSEL PHELP scanned asbuilt dimension and do a sign off/ hand off
John asked for an email summarizing this
Jay has entry for TXE10 Anchor (HAC) Bolt coordination, meaning the MES EOL Anchor, John says its being field coordinated
Alec Harpel, asked about JE Dunn asking for Imbed Anchor info for all regions, saying they were pouring concrete, etc
NO FIELD TEAM OR PM TEAM PRESENT
I told jay I looked at LEB6 and alignment looks good, I also republished and exported all new NWC's so everything should be current
Get Luke Jost information from Garrett about the FWM model and sheets and making sure they are updated. Garretts email yesterday said the model was current, they still need to update sheets. He needs all the info for a call later with HDR
TXE CLASH between interior HAC bypass valve handles clashing with FCU frame
John Cowhey brought up floor elevations and having to shim equipment which would through off spools, need to keep randoms in mind
First of a series of daily check in calls between Mcdean, Tate and Southland to make sure we get steel updates from Tate and clash detection
Matt Mcconnell is the PM from Tate
Should see new update tomorrow morning
Guin Yaprak verified this is the case, 10-11am tomorrow
HRV FOK will be in the NWS
MSA will be included
This will be a recurring meeting everyday
8/3/2026 - Isabella told darren about Seths response to my request for consistent elevations, which was no, she said this is unacceptable. Darren said they went to Meta about this whole situation
I informed Darren the current model they were viewing was outdated, the current model from last week shows updated alignment
Isabella said she doesn't understand why Meta got involved, that was unecessary
8/10/2026 - Tom hammered down on Coordination for HAC and clashing, sign off dates
Danton didn't have anything, he is doing MOFE coordination
Tom says we need to align
Isabella said we need work together to get this setup
8/12/26 - Arthur stated the MES will not be moving, the MSA Frame will be adjusted to clear the clash between msa hac and mes anchor
He asked about the 8" TW Flex skid squeezing through column and mes, clashing, I let him know that was a temporary flush skid with flex pipe, we will get It through
Isabella stated that peyton will be putting together all information, and run through a list of clashing
Peyton showed the SI Duct clash with SI Mech pipe
Ryan got pissed that Darren wasn't available, saying this is such a broken proecess, arthur says hes out of his depth, Darren is double booked, Ryan said he needs to be there
Clash is showing flush access panels hitting bus duct on outside of wall
Isabella says since MCDean contracted with SJS to do clash and coordinating, they need to be present and hosting these meetings
Arthur asked Doowoo to assist in getting Darren participation and SJS participation
Ryan asked what kind of end was on the 8" flush skid, Arthur reminded it was hitting a timber column. I said it was a grooved end, we will get it through, even if we have to use a come a long, lol
8/14/26 - Cancelled
8/17/26 - They did a clash flythrough
Showed 6" FW Skid connector fittings hitting Steel frame, need to either turn MES Fiiting out, to face SKID or offset around Steel post
Also showed clashes with strut and supports, strut clamps need to be aligned to supports
Clash with pipe and steel frame, Tom asked why this clash is here but not in EMT and not the programmatic MES/HAC Steel
MCDean says they updated the steel based on CDD(?) before it is finalized, cart before the horse, they are going to do updates for tomorrow meeting
8/18/2026 - Missed, at El Paso for FOK/SOK
8/19/2026 - Missed, at El Paso FOK/ SOK
8/26/26 - This meeting was moved to Tues and Thur, HRV MECH MODEL COORDINATION REVIEW
Scott asked for a full coordination schedule with dates to hit
Isabella sighed
Isabella said no, we don't have actual dates
Ryan said maybe we should be pulling back required dates from fabrication need by dates
Scott did his whole sign off and deliverable schedule rant
We are going to base our Coordination dates form DPRs precon schedule and sign off so that we are signed off with MCDean before DPRs dates
We are supposed to have approved submittals for anchors on 8/21
Document control, Isabella is the point of contact,
Scott explained , need one point of access for Sheets, we are still digging around looking for latest greatest
I obligated to once a week going through clashes, using HRV Forma
Isabella will submitt her stainless steel dog leg expansion for Tom to approve
Isabella will get with Tommy to Verify how many 14" skids they want
7/29/2026
Explained the moving of embed to get out of wall, will move all embed together but will cause actual anchor to shift on the embed placement
Isabella Vesce Rivera
Bridged files from Colonial
Isabella will bring up we need bridged file
I requested to sit on base build coordination meetings with DPR/ Colonial
Adam wants form to access DPR, he will give it to all
Tomas maxell and chirdon talking to structural engineer about eliminating the middle anchor on DCB100
Adam added couplings to MSA that will allevaite having to add welds for field install
Packages were created in stratus, should be able to get dates by EOW
MSA to HAC needs some couplings removed
Depending on if Ryan can put the couplings on GMP Field because Fab is hard bid
Adam will remove from on site scope, per Ryan
Adam Dial in how we want to name NWS MSA for spool sheets
Adam wants to name them so they are more in line with the stratus packing naming
Deliverables -
Sign off and install schedule
8/5/2026
Adam had to push publish, I lost stratus addin, cant find download, gave up
I updated HRV DCB100 and replaced 07 couplings with 107v
Gave isabella the work flow for Layout sheets for hot items, Sign off, Eng Review, Shop Drawings, Spools
7/15/2026
Waiting on Corbon to yay or nay the middle small anchor
MC Dean is still making adj to hac steel, they did state it shouldn't affect any of our content, ian is supposed to be complete on 9/24
Adam is supposed to put couplings in MSA to stop field weld
Need this update in stratus per Ean
All packages are created in Stratus with Dates
Get with stone and scott about getting FCU in the HAC for HRV
Southland will be running our own Clash Coordination
MC Dean provides a NWC, but we are choosing to use DPRs NWD in our own Model Coordination due to being more current and includes more trades
Keith, Melanie and Peyton will be putting this together
Melanie says not to clash with their NWD, not good
Either we will use DPR Forma Model coordination, if not available, we will ask if we can bridge their models directly to our forma to run our own Model Coordination and clashes
DCB100 NWS1/4 signoff 9/22
DCB100 NWS2/3 signoff 9/29
7/22/2026
Gave run down to Thomas and Ryan of Colonial Stub ups
Trhomas says there will be a middle anchor
Peyton will be leading the Coordnation Model and space, will be issueing clashes
Will be running clashes today
Ryan did sent out an email to DPR and colonial web regarding the UG FW CWC Dim sheet showing critical dimensions
8/26/26 - Brought up the issue thats happened witht the bypasses, cerris moving the bypasses after the scans, waiting to see if cerris plans on verifying the final locations match HP's, or if we will need to do a rescan
waiting to hear from engineering as far as if the MES is moving, MC Dean is saying it will be moving, our Engineering has to ok, get submittals, move concrete pillars
Ryan asked Tom Maxwell to get impacts put together for the moving MES, Tom sent an impact out already along with mine
Scott is saying the DEAN MSA HAC was originally designed off a homemade MES from them, not ours, thats why the MSA HAC was 2" off along with the PSK Room being 4" different
Still waitng for approval on 2" expansion dog leg
Need to send Isabella email of Toms impact and mine from moving MES
5/14/26 - - Joe Brought up the access panels for Flush system, asked about rating, I would have to check submittals to verify. Me and Lance holmes informed joe the flush systems are temporary, once done, they get removed and the access panel stay
Anna said they were aware, but not the finalized locations, now they will be going through Valley for engineering, excel engineering to make sure everything is accounted for, engineered
Talked to Stefan, we are not providing the Access Panel, its GC2 wall, they are providing it
I need to check on RO system, ACCess panel and it looks like location may be borked
Scott asked about sign offs for lighting scope to base build duct connections, Joe said they havent covered it, sign off is around end of June. They will be circling back to loop area not that they have certain paperwork available
Joe said any issue can be brought up at anytime
5/21/265 - No John Rhee, Brent, Thomas Holler, NO PM TEAM
They went over stud wall model, Lance asking about raceways for security and bus ducts
5/28/2026 - They went over electrical stuff, skid placement, wall leave outs
Turner wants a meeting with Helm and Southland to go over Wall penetrations
Joe D discussed Span model naming, keeping them the same and consistant.
Will need to relink LEB Span models since they have new models with Nucor suffix
6/4/2026 - Eduardo Ibanez brought up Status of Facility Water Stubups asking if Verification of Stubups with Mortenson needed. Had Crider submitted? Lance was saying Ryan would have this info and asking if Ryan was in meeting
NO PM Team present
I sent PM Team a summary email
I explained, Ryan used HDR model for coordination, I worked with HDR to get everything line up, we provided dimensions, everyone agreed to them, now stub ups are off, Lance Resposnded to John Rhees email asking what is being done
I said we need to start having meeting to go over this issue since its so critical
Luke Jost told eduardo to add an action item for this and lance said he will head this off
6/11/2026 - I brought up the FW UG being off again, told the group Ben Kozel with crider said they were backfilling in layers and trying to get the stub ups on the POC/CIA points
Overhead Signoff is schedule for 6/30
Scott asked if it was entire building for NWB, Joe says yes
Joe Brought up IMP walls changing to Framed walls, Anna? Said it was still being worked on
Verify LEB10 POC For DCW
Verify DCW POCs line up with CIA
Lance said they are also providing a hose connection for discharge, I stated they are using the FLOOR Drains in center of gallery for discharge, Adam corrected me saying John has requested different discharge points. Wouldn've been nice to know.
Someone asked about the Flex piping from the 8" skid hitting the column, I told them it was flex pipe and temporary, that it will bend around the column
Vent in 6-19x6-D, adam told them to put in between MES Skid
Waldinger is doing the bypass on LEB6
Building 6 MES loops are showing misalignment with Waldinger Bypass
NO PM Team present
I said I would like it added to this meetings notes, Joe Dorinsville basically shut it down, saying it was a field issue
I said it was our issue also since we are constantly being asked to do overlays, which were happy to help any way we can, but this was more of a helm situation since they are the responsible party to connect to the UG and provide us with accurate points of contact according to the CIA
Joe reiterated it was a field issue
6/18/2026 - Edwin Perez is showing Verification on stub ups w mortneson needed. Pending Submittal. Eng. Drawings to be submitted - Crider and Crider. He said this is still on going
Edwins model view still shows MP Shifted to plan right, access panels were to the right of the wall they are supposed to be in
LEB6 Arch Coordination model is showing everyhting off, MES Skid not lining up, mp is to the right, access panels are to the right of the walls they are supposed to be in.
LEB10, checked with Joe D, things line up there.
6/25/2026 - Joe, Greg, Luke Long, Greg went over Electrical coordination
I sent email to PM Team, no one was present
Eduardo Ibanez brought up Status of Facility Water Stubups asking if Verification of Stubups with Mortenson needed. Had Crider submitted? He brought this up again. I explained again that we provided dimensions for LEB10 and LEB1 to Mortensen, Crider and HDR, they all agreed
I told group that I also emailed these dimensions to Waldinger for Region 2, but havent received any comments or response from anyone.
Scott asked about tracking for signoff on 6/30, eduardo said yes
Luke Jost asked about LEB10 Embeds to make sure they are getting tracked by turner
Edwin Perez asked about Waldinger Bypass and alignment to SI MES Loop Connection
I told Edwin Perez I provided poc dimensions and elevations, but havent received any response
Edwin said he will bring up in next BIM meeting
7/2/2026 - Get with john as far as who is providing what cam lock adapt for fip drops
Lance Holman also provided additional dishcharges (Drains) for Flush/ fill per john
They showed model, HDR DWC Drops are on face of column, I told group IFC shows they are on Web side, HDR Model doesn’t match HDR IFCs
John Rhee is communicating changes from model to FTI, Turner that they are not telling us, Discharge drains, DCW changes
The only reason I found out was because of the meeting flythrough, our pocs were on other side of corridor
John fucking totally ignored our information and didn't relay any information
I missed the HDR IFCs showing the drops on the plan south side of corridor
I explained LEB6 model misalignment was fixed, publishing issue, I will double check mondays model after the Saturday auto publish
I told group about the FW UG Dimension sheet that has been distributed multiple times and it details where the FW UG stubs are supposed to be ever since LEB1
I will double check LEB2 misalignment
They showed LEB6 and the 8" skids were into the columns again
I explained the deep dive I did last week, it shows everything aligned. There are issues with the FTI Container model that Turner is using for coordination
7/9/2026 - Setup LEB2 SI MP View off turner LEB2 Overall Building NWD, Crider is still off at Grid 2-50/ 2-D
Eduardo Ibanez hosted
LEB10
All Content on slab will be created in a file, progress is ongoing. Jay Asked what does this entail? Above Slab content?
LEB6
Our MP is still out of alignment in Turner LEB6 Overall Building.nwd, but Joe pulled in a recent nwd and it showed the FTI Container inside the Overall nwd is off
With joes pulled in NWD that shows us and waldinger aligned, Crider was still off around 8-10"
SI Duct and Waldinger do not align
Justin verified that Turner is using NWC files NOT the revit
Southland MP looks good
Southland MP model is still a little older, but non-critical
7/16/2026 - Joe D brought up some issue about control joints at LEB10, luke jost and jay kaiser will update as necessary
7/22/2026 - Joe D brought up control joint proximity to MP anchors, they scooted 1 at grid 29ish, no TW Skid.
Checking Coord Space at LEB I see Stratus models getting exported again on 7/17, that was last Friday
The only MP model available is from april, what the fuck is going on with this fucking shit
The LBE10 Publish settings were set to stratus, talked to heath, he showed adam was the last one to do it. Adam said he didn’t know had to change settings back
Lance suggested a meeting with FTI and Southland to get power to TW Skids, Lance Long said they have a meeting setup with FTI Tomorrow, looking at junction box on the wall
Jay K at FTI created an issue with Crider Facility Water Alignment and was trying to add crider watchers, he can only add FTI watchers.
Joe D told him to use Triston with Helm, Mitch with Waldinger
Mitch with Waldinger said it looks like its going to work out with aligning their Bypasses with Southland MP
Jay K brought up container models having outdated southland models
Joe D says its tough to say when the FTI container was reloaded. The last update they show was july 13th, 10 days ago
I rbought up the TW Skids on each end of the building also to check, they have anchors also
I stated I found a recommendaiton of 3" distance between an anchor and a sawcut or concrete joint
7/30/2026 - Jay brought up getting control points from Turner
Jay brought up missing MES/ TW skids from LEB1, LEB2 FTI Container, the MP content was aligned
8/6/2026 - I affirmed with Jay, I have not seen any blue beam sessions
I verified LEB 6 in Navis, using the View I created with all trades
James (Turner) is setting up meeting next week to go over CIA points with FTI and Baker
Jay asked about established control points, joe said bring it up in the session
8/13/2026 - Helm modeled their bypasses to the current asbuilt points received Last Friday, This Monday
I told Joe we would wait for the actual asbuilt 3d scans before we do any further model aligning. It’s a waste of time right now, to turn around and have to do it again after scans are received.
8/20/2026 - I told them again we will be able to squeeze the 8" Flex skid around the column, its a flex pipe and not an issue
8/27/26 - Had to leave to go to EMT meeting due to current emt issues
Melanie Working through EMT Models, links needed repathed
Go Through EMT1 and EMT2 and make sure MES, TW and MP content are good
IF good, push to Revizto
Also check MSA/FSHAC Piping
EMT Does have IFC's for Base Build, Scott showed them yesteday, I coulda swore we didn't have any sheets, prob thinking of HRV
7/16/2026 - Melanie says our MP model doesn’t line up with Eng Model, we are using Lightning Shared Coordinates, Eng is using ETM100
Abe - Attached Sign off schedule to summary email, have content populated and coordinated ahead of signoff dates highlighted in RED, these dates line up with Mortenson
I told her our content, mes content lines up in revizto, if you change anything, it will no longer line up
Download arch model, link our models in and see who lines up
She says archs did change the g datum model a while back, she had to repath it and that’s when things stopped lining up correctly
7/17/2026 - Cancelled
7/20/2026 - Cancelled
7/22/2026 - Ryan says Mortenson is on the verge of issue stop work order with Meta due to electrical incompetetance
7/23/2026 - Cancelled
7/30/2026 - Cancelled
8/6/2026 - Adam said he will cover EMT, I will do the LEB Meeting
8/13/2026 - Cancelled
8/20/2026 - Missed, went to FTI LEB Meeting
8/27/26 - Abe says Mortensen said they will go through and remove duplicate content
Brought up clashes issued to me were showing no clashes when I zoomed into them
also showed the Flush piping and access panels hitting cable tray
First of a series of daily check in calls between Mcdean, Tate and Southland to make sure we get steel updates from Tate and clash detection
Matt Mcconnell is the PM from Tate
Guin Yaprak verified this is the case, 10-11am tomorrow
Should see new update tomorrow morning
HRV FOK will be in the NWS
MSA will be included
This will be a recurring meeting everyday
8/17/2026 - They did a clash flythrough
Also showed clashes with strut and supports, strut clamps need to be aligned to supports
Clash with pipe and steel frame, Tom asked why this clash is here but not in EMT and not the programmatic MES/HAC Steel
MCDean says they updated the steel based on CDD(?) before it is finalized, cart before the horse, they are going to do updates for tomorrow meeting
Showed 6" FW Skid connector fittings hitting Steel frame, need to either turn MES Fiiting out, to face SKID or offset around Steel post
8/14/2026 - Cancelled
8/3/2026 - Isabella told darren about Seths response to my request for consistent elevations, which was no, she said this is unacceptable. Darren said they went to Meta about this whole situation
I informed Darren the current model they were viewing was outdated, the current model from last week shows updated alignment
Isabella said she doesn't understand why Meta got involved, that was unecessary
8/10/2026 - Tom hammered down on Coordination for HAC and clashing, sign off dates
Danton didn't have anything, he is doing MOFE coordination
Tom says we need to align
Isabella said we need work together to get this setup
8/12/2026 - Arthur stated the MES will not be moving, the MSA Frame will be adjusted to clear the clash between msa hac and mes anchor
Isabella says since MCDean contracted with SJS to do clash and coordinating, they need to be present and hosting these meetings
Arthur asked Doowoo to assist in getting Darren participation and SJS participation
Ryan asked what kind of end was on the 8" flush skid, Arthur reminded it was hitting a timber column. I said it was a grooved end, we will get it through, even if we have to use a come a long, lol
He asked about the 8" TW Flex skid squeezing through column and mes, clashing, I let him know that was a temporary flush skid with flex pipe, we will get It through
Isabella stated that peyton will be putting together all information, and run through a list of clashing
Peyton showed the SI Duct clash with SI Mech pipe
Ryan got pissed that Darren wasn't available, saying this is such a broken proecess, arthur says hes out of his depth, Darren is double booked, Ryan said he needs to be there
Clash is showing flush access panels hitting bus duct on outside of wall
8/17/2026 - No notes, cancelled?
8/18/2026 - Missed, at El Paso for FOK/SOK
8/19/2026 - Missed, at El Paso for FOK/ SOK
8/24/26 - MSA Support foot clash with MES 4.04 is in NWS and the MES 4.03 in the datahalls, datahall clash is smaller
MCDEAN is saying we will have to move the MES into the corridor
Tom and adam explained Anchor shifting 1.5" will cause new submittals, new spooling and parts for MES EOL loops and possibly redesign of the flush skids
MCdean, Danton and Arthur said the msa is 1" wider, they submitted to Meta, scott says the msa is 13'-2" and the other are 13'-0", thats 2"
Tom brough up shifting the MSA supports next to MES toward the FSHAC to clear the clash, MCDean was iffy about whether they looked at that
8/27/26 - TW at MES EOL is clashing with hac frame
Darren said they need to remove the MTR Frame, its still there
Need to check TW at MSA Supports dont line up, steel is missing support
Check Flushing misc piping and parts at NWS clashing on MES and HAC
I brought up the flush piping /access panel clash with cable tray which will be covered in the DPR coordination meeting that isnt happening right now
Darren said those cable trays should be getting installed after flush/ fill due to interfering with moving flush skids, he measured cable tray, it was 10-11 feet AFF
Kaushal Bagdekar with Turner ran the meeting, saying who to contact for what, I asked if he could send an email with that info
They went over underground clashes
5/28/2026 - Tristen with helm verified he is using LEB1 dimensions for LEB 2 elevations and locaitons for FW
6/11/2026 - No PM Team
Went Over UG issues, concrete pads
6/18/2026 - Kaushal Bagdekar
Did a flythrough for LEB2 going over exterior sectionalizers
LEB-2_SPAN_SS.rvt, verifying during meeting that the model is good, Checked LEB2 SPAN_SS model, couldn’t load content, says cant link in NuCOR
NO Interior Walls and framing, Valley, Diogo or Ruth said they will get with valley
No Interior Meta Wall Panels
6/25/2026 - NO PM TEAM
They went over UG issues for LEB2
7/2/2026 - LEB2, Showed model where Helm, SI and Crider not aligned, #2070
LEB2 Building Overall actually has Crider model, showing misaligned
Grid 1-50, 1-D is the only spot where Crider is off looking at Turners LEB2_Building_Overall model only
Everything else is aligned, MP, Duct, Steel, Walls, no issues
Sent email showing misaligned concrete and crider stub ups at 2-50
LEB-SI-MP-LEB2-R25 model lined up identical to LEB2-Building-Overall
Didn't see new DCW POC valves, did I update LEB2
Did see FLUSH VENTS AND DRAINS, VENT ON 2-50 IS OFF
7/9/2026 - Sent Email to Joe, Jay, Edwin, Eduardo and Joe forwarded to Kaushal
Kaushal asked about flush skids in front of door ways, need to send them a time frame for flushing before equipment gets removed
Concrete elevations different at Gird 2-29 and 2-32
Crider stub ups off at 2-50/2-D
Added to chat
7/16/2026 - Sent email to Triston with Jay and Kaushal cc'd about Helm bypass flanges not aligning to SI MP Flanges throughout building
LEB2 looked like it aligned good
7/22/2026 - No southland issues covered
7/30/2026 - Just went over non-southland issues
I dropped for LEB Mortenson meeting at 1000am
8/13/2026 - NO PM/ FIELD TEAM
Ouch, Kaushal called out Triston for not being in the meeting 3 weeks now
Had Kaushal remove the waiting on southland to add content we are waiting for, under MP Pipe - Triston, he labeled it closed
Dropped out at 10am for Mcdean Hac Meeting
8/20/2026 - They went over support pads in yards and clashes on exterior., I dropped for 10am LEB Mortenson meeting
8/27/26 - Just went over all other trades and issues, Triston said no issues from Helm, dropped early for LEB BIM Coordination Meeting with Richard lopez
8/20/26 - Asked Richard Lopez if anyone is using shared building Control Points, him and nick both deferred to turner. I said I am used to a site wide control point map that is shared with all trades. I understand this is a bit of unique job with 3 GCs though
Richard corrected his statement and said turner actually did have a meeting last week with him and Nick, he wasn't sure if it was a recurring meeting but would look at getting information dispersed.
Ryan Zoldan - Richard Lopez
LEB 6 due finalized next week
I requested a schedule from Ryan, he has the sign off, region schedule, I brought up a pull plan, be he says that will be through Turner
Mortensen is the Base build GC, why aren't they leading a pull plan schedule
John Rhee nor Brent were in this meeting
6/4/2026 - I brought up the LEB10 FW UG Stub ups totally missing the Dims, Ben Kozel was there and he stated they are bringing them back in to dimensions by backfilling a little and moving them, backfilling and moving them
He acknowledge that lance did contact him
6/11/2026 - Ben Kozel, said there were no issues that need to be talked about.
Richard lopez asked around the room for any issues regarding LEB10 or any others
NO PM Team
6/18/2026 - Richard Lopez Hosted, just asked for any issues with LEB10,1,2,3 Underground issues
Rantwiler asked when IWM for TXE10 was going to be signed off, Ethan says he will talke to kyle since they are not really split out
6/25/2026 - Going over LEB7,8
Ryan brought up LEB6, HDR model is not lining up with the Dimensions provided by SI
Ryan henderson said he will follow up
Ryan said we have all agreed to follow these dimesions, I added that I have distrubuted that dimesion sheet ot Waldinger and explained everything, but havent received a response yet
Ryan brought up LEB6, HDR model is not lining up and my email I sent out
I updated, still waiting for HDR to align the stubups
Ryan said Crider is using civil 3d, but we can work it out to actually use their model for coordination and linking in so I don't have to use HDR
7/9/2026 - No issues to cover, they went over UG clashing for elect, sanitary
7/23/2026 - Richard asked Triston about any alingment issues, he was good
Ben said LEB6 stil had some very minor HDR alignment issues to on udergoung
7/30/2026 - Bend said LEB6 looked good
I said we republished LEB6, there was some extra content we had to remove
8/6/2026 - I brought up the LEB10 FW UG Stub ups totally missing the Dims, Matt Schaff said they are doing repairs this week and lookingat getting into within an inch
I mentioned, for helms benefit of using Eccentric reducers on bypass in order to rotate the stubup to align with MES better
I also mentioned after slab is poured, bypasses installed, we look at doing 3d scans
8/27/26 - No issues were brought up. I was going to bring up control points, but Im done. Ive asked, sent out emails no one has responded except jay kaiser
TXE1 looks good for the loop area sign off next week
Same with TXE2
6/4/2026 - Own B ran the meeting going over TXE1 and 2
6/11/2026 - Owen B, says TXE10 Loop for sign off
TXE2 Core scheduled for next week
TXE10 AB Datahall and Loop are signed off
TXE3 Alan lopez is running region 2 for signe off
TXE2 Loop and AB South sign off
issue 2602 - Cerris Vent in corner is clashing with Technical water, Rantwiler is saying they don’t have our model, I told them our model has been there for 6 months, the fact that HP is viewing it, means the model is available. If it’s a bridging issue we will help Cerris work it out
Trevor said he will get with rantwiler and get the model bridged, they will offset that vent around our TW Piping
They made comments about the TW skid being so close to the FW valves. Its been this way for over 6 months. Trevor also stated the vent will need an accessible cleanout
6/25/2026 - They just went over IWM and specific Electrical clashes
7/9/2026 - TXE 2 all docs are out, all sign offs are out
TXE1, 2 sign offs left
DHCD 2 weeks from now
7/22/2026 - No Issues
8/20/2026 - They didn't cover anything relevant to us.
8/25/26 - John gave a summary of what the issue is
7/8" on IMP wall and 1-3/4" on Drywall at TXE 10, the 2-1/2" bust is not framed yet
HP sounds like they are going to move walls, they are looking at getting an answer today
Anna Cummins will see what they can do with Hilti on the fire rated 2 hour drywalls, and the IMP walls
John suggested making this a recurring meeting
John says meet again Tuesday next week, He sent an email a short while later saying HP would be adjusting walls, no need to work up any solutions
8/28/26 - NO FUCKING PM or FIELD TEAM at meeting, I sent them links in chat, no response. Had to send adam one also, he didnt have it.
Greg and alex went over leave outs and cut outs so we can get anchors in and drill them
Greg didn't know about the corners due to that being the main part of the wall for support. Alex said brace it from elsewhere and get the corner out since we have bolts right at corner
I told them I would sent them an updated markup that shows wall info also
Verify 107V and 07 Couplings on Pup pieces, region 1
Adam said we are still working through comments, still waiting on cantilever approval.
LEB10,1,2 will be good to push out to submit to tom
Need to update regions to datahall A,B,C,D
Day zero is 2/25/27
Need spools before 1/5/27, Adam said we wiill shoot for 6-8 weeks before then to allow for review, updates, etc
Scott says EORs get officially submitted to Tom, he approves, they get submitted to FTI. Not sure if EORs get submitted to Meta or not as part of record drawings
Scott says by Friday the 14th they will publish to stratus
Embed Layout Drawings
We gave drawings, we will have
Crider and Mortenson will provide scans once they are finished, so that helm can update their bypass.
Flush Skid BOM, Curtis used TXE Counts and ordered the material
Hose Carts are still being finalized
Get Reece copies of TXE Flush skid BOM information
Hose Carts will be finalized once FOK and SOK are done
No pour until november
Schedule model? Can we incorporate this?
LEB10 UG Stubup status
Crider, Mike Schaff said they were doing repairs this week
Make sure LEB PM Team knows we need to scan after slab, after bypasses installed, then we align, update spools
8/14/2026 - Cancelled
8/21/2026 - Bring up mentioning Control Points in Meeting yesterday with Richard Lopez (Mortneson), says they dont have any Interior building control points, get with Turner, then said they had a meeting last week with turner, he will check if its recurring
Talked about the 30 email chains from Lance, Jake Wright, Casey, Triston and Ben. The lastest is from Helm asking if their points are good.
Talk to triston about their flush fill, are they using the existing bypass or adding a temp one?
8/17/26 - Ryan Ran the meeting, couldnt get the agenda up, lol, asked peyton to go over clashes, peyton said he wasn't ready, then Ryan did a round table, no body had anything to
Peyton showing MES MP Pipeing into duct and framing, mic didn't work so I couldn’t talk to verify MES Elevations
8/3/2026 - Abe said UCO3 UG Signoff is pushed to next week
Peyton going over clashes
#816 shows vesda FP content going through our bypass at hac, adam modeled the vesda
MH Duct at EMT1 was low, scott said he will take a look
8/10/2026 - Melanie says she will look at MES Alignment, I said on Saturday mes was mis-aligned again
Adam said he will fix Vesda Clash with HAC EOL Bypass
I said the MES Loop/ Flush Loop piping needs to be reconfigured, its clashing with TWMU Skid, the tee will get rolled to vertical and cantilever pipe supports will be brought in
Showed 6" FW Skid connector fittings hitting Steel frame, need to either turn MES Fiiting out, to face SKID or offset around Steel post
Also showed clashes with strut and supports, strut clamps need to be aligned to supports
Clash with pipe and steel frame, Tom asked why this clash is here but not in EMT and not the programmatic MES/HAC Steel
MCDean says they updated the steel based on CDD(?) before it is finalized, cart before the horse, they are going to do updates for tomorrow meeting
8/14/2026 - Cancelled
8/12/2026 - Arthur stated the MES will not be moving, the MSA Frame will be adjusted to clear the clash between msa hac and mes anchor
He asked about the 8" TW Flex skid squeezing through column and mes, clashing, I let him know that was a temporary flush skid with flex pipe, we will get It through
Isabella stated that peyton will be putting together all information, and run through a list of clashing
Peyton showed the SI Duct clash with SI Mech pipe
Ryan got pissed that Darren wasn't available, saying this is such a broken proecess, arthur says hes out of his depth, Darren is double booked, Ryan said he needs to be there
Clash is showing flush access panels hitting bus duct on outside of wall
Isabella says since MCDean contracted with SJS to do clash and coordinating, they need to be present and hosting these meetings
Arthur asked Doowoo to assist in getting Darren participation and SJS participation
Ryan asked what kind of end was on the 8" flush skid, Arthur reminded it was hitting a timber column. I said it was a grooved end, we will get it through, even if we have to use a come a long, lol
Arthur Foley (MC Dean)
First of a series of daily check in calls between Mcdean, Tate and Southland to make sure we get steel updates from Tate and clash detection
Matt Mcconnell is the PM from Tate
Should see new update tomorrow morning
Guin Yaprak verified this is the case, 10-11am tomorrow
HRV FOK will be in the NWS
MSA will be included
This will be a recurring meeting everyday
8/3/2026 - Isabella told darren about Seths response to my request for consistent elevations, which was no, she said this is unacceptable. Darren said they went to Meta about this whole situation
I informed Darren the current model they were viewing was outdated, the current model from last week shows updated alignment
Isabella said she doesn't understand why Meta got involved, that was unecessary
8/10/2026 - Tom hammered down on Coordination for HAC and clashing, sign off dates
Danton didn't have anything, he is doing MOFE coordination
Tom says we need to align
Isabella said we need work together to get this setup
6/1/2026 - Noel Nunez says Alehandro Chew will be safety manager
Michael said he sent TXE3 embeds along with PDF dimension in mid April
Doesn’t think TXE3 has been poured, think they are behind schedule
Says we havent been funded for Region 2, he is sending out embeds as needed
Michael asked what the question was about RO and TW, I said it was going over how to connect to the RO skid, from DCW and to TW MES
Michael asked if MES Loops were completed, adam said yes, he created new BOMs
Michael said his goal is to get everything ordered
Michale Paul said they thought the walls weren't going to be in until they could do anchor
They said that was what was agreed to
6/8/2026 - Michael said they had a PM Coins Mandatory meeting and couldn't host the meeting
6/15/2026 - Chris Moss came on board from TSMC, Pipe fitter, GF
Jose Alejandro Chew, new Safety Manager for TXE
6/22/2026 - Shop drawings (Engineer Drawings) looking at submittal on Frid, 6/26
6/29/2026 - Keylan Cancelled
7/6/2026 - Carson will scan on Thursday
7/13/2026 - Scans on TXE10 complete, should have done this week, EOW
Jacob will be pulling field measurements of FW Stub ups
Adam will overlay scans to see how they match up with our Stub Ups
SOK will be starting next week, 27th will have more setup covered
7/16/2026 - Zach wants scanning sent back out, scan off control points, need to get CPs from Greg, put in model, talk to carson to see what they need from us
Control points were requested on 6/12 meeting with Greg H, it was stated they would be sent to Michal and James Homrighausen
I also asked for control points from Luke Justice on 5/21, he said he would get with Greg H.
They made it out like it was detailing fault they scanned without using control points
Paul asked how soon I can get the points into model, I said immediately, but Im not sure scanning needs anything from us, they may input control points into the rcap software maually but we will have it the model if they need it
7/27/2026 - Scanning this week
FTI Will be doing Trimble next week
8/3/2026 - Adam brought up new pipe supportts that were sent to Tom due to more access to mes loop valves
Adam asked about tapped caps for mes connections, michael said it was a miss on them so they will cover it
Trimble is shooting wall points tomorrow and Wednesday
8/10/2026 - Asked about txe2, keylan said they have bottom plate down, trimble is showing walls off
Asked about info for points from trimble, is this for field use only, are they showing HP where walls are off
Keylan says they are using the info to show HP were walls are off, TXE1 had walls off, HP is still working on solutions
I asked for TXE2 Cerris bypass schedule so we can get scanning out
He said he would get me that info
Need to ask about Access panels, whos providing?
Need to ask about info for HP saying they are having issues with control point discrepancies
Keylan said he will double shcek with paul and nate
Paul says he hasn't heard anything about control points, alec says HP is suggesting we move our anchors
FTI says Jennifer is gong to get involved and veriy, Meta says they will send their own Surveyors out to verify, this was last I heard
I will put together an email of who said what in which meeting and send to keylan to start a chain
7/27/2026 - Missed, went to Cameron Shop to meet Mid Atlantic Crew
8/17/2026 - Went over UG and sign off dates. EMT1 Sign off on hold due to CDD1 change, looking to still start coordinating knowing they will need to incorporate the changes after the fact
Melanie Working through EMT Models, links needed repathed
Go Through EMT1 and EMT2 and make sure MES, TW and MP content are good
IF good, push to Revizto
Also check MSA/FSHAC Piping
EMT Does have IFC's for Base Build, Scott showed them yesteday, I coulda swore we didn't have any sheets, prob thinking of HRV
7/16/2026 - Melanie says our MP model doesn’t line up with Eng Model, we are using Lightning Shared Coordinates, Eng is using ETM100
Abe - Attached Sign off schedule to summary email, have content populated and coordinated ahead of signoff dates highlighted in RED, these dates line up with Mortenson
I told her our content, mes content lines up in revizto, if you change anything, it will no longer line up
Download arch model, link our models in and see who lines up
She says archs did change the g datum model a while back, she had to repath it and that’s when things stopped lining up correctly
7/17/2026 - Cancelled
7/20/2026 - Cancelled
7/22/2026 - Ryan says Mortenson is on the verge of issue stop work order with Meta due to electrical incompetetance
7/23/2026 - Cancelled
7/30/2026 - Cancelled
8/6/2026 - Adam said he will cover EMT, I will do the LEB Meeting
8/12/2026 - Arthur stated the MES will not be moving, the MSA Frame will be adjusted to clear the clash between msa hac and mes anchor
He asked about the 8" TW Flex skid squeezing through column and mes, clashing, I let him know that was a temporary flush skid with flex pipe, we will get It through
Isabella stated that peyton will be putting together all information, and run through a list of clashing
Peyton showed the SI Duct clash with SI Mech pipe
Ryan got pissed that Darren wasn't available, saying this is such a broken proecess, arthur says hes out of his depth, Darren is double booked, Ryan said he needs to be there
Clash is showing flush access panels hitting bus duct on outside of wall
Isabella says since MCDean contracted with SJS to do clash and coordinating, they need to be present and hosting these meetings
Arthur asked Doowoo to assist in getting Darren participation and SJS participation
Ryan asked what kind of end was on the 8" flush skid, Arthur reminded it was hitting a timber column. I said it was a grooved end, we will get it through, even if we have to use a come a long, lol
8/14/2026 - Cancelled
8/17/2026 - They did a clash flythrough
Showed 6" FW Skid connector fittings hitting Steel frame, need to either turn MES Fiiting out, to face SKID or offset around Steel post
Also showed clashes with strut and supports, strut clamps need to be aligned to supports
Clash with pipe and steel frame, Tom asked why this clash is here but not in EMT and not the programmatic MES/HAC Steel
MCDean says they updated the steel based on CDD(?) before it is finalized, cart before the horse, they are going to do updates for tomorrow meeting
Arthur Foley (MC Dean)
First of a series of daily check in calls between Mcdean, Tate and Southland to make sure we get steel updates from Tate and clash detection
Matt Mcconnell is the PM from Tate
Should see new update tomorrow morning
Guin Yaprak verified this is the case, 10-11am tomorrow
HRV FOK will be in the NWS
MSA will be included
This will be a recurring meeting everyday
8/3/2026 - Isabella told darren about Seths response to my request for consistent elevations, which was no, she said this is unacceptable. Darren said they went to Meta about this whole situation
I informed Darren the current model they were viewing was outdated, the current model from last week shows updated alignment
Isabella said she doesn't understand why Meta got involved, that was unecessary
8/10/2026 - Tom hammered down on Coordination for HAC and clashing, sign off dates
Danton didn't have anything, he is doing MOFE coordination
Tom says we need to align
Isabella said we need work together to get this setup
Neema says stub ups need to be slurried, underground pipes need to be verified for undergound thrust and that passive soil will be sufficient
Above ground thrust will be satisfied by slurry and surrounding footers
MC Dean Bridged files
Danton Wein with MC Dean
MDI has steel and skids, fabrication
ENG has electrical equipment
They both have all links turned on, these need turned off
mcd plan for trench moving, not relating to Southland
Southland
MP Model connections to FW UG Stub ups
Need CWC Bypass, will they be included in the CWC Model we already have or in a separate above ground model?
Ben verified the models are good
Ben then went to stub ups and neema took the convo to RFI something, I said we were going to take a first pass at matching CWC Stub ups
Neema was talking about some kind of trnech shit moving that didn’t apply
7/15/2026 - Adam CWC said no update on the bypass for CWC
7/22/2026 - Talked FWM and MCUP issues mainly
Eli from Colonial was present
Neema says they need to move FW Stup ups away from footer about 5"
I mentioned they need to hit the critical North south dimension of 6'-1 5/8" to match the mes skid line, but we can match whatever movement they do east and west
Ben and Neema both pointed out CWC can rotate bypass valve to the front, one of the bypasses was already rotated this direction, CWC started to fight back a little bit
This means CW Will need to move their stub ups to get out of way of footers
Danton affirmed that the 2 MDC ENG and MCD MDI Models are the current models for the FSHAC
Storefont issues
7/29/2026 - Ben gave dimesnions of shift in DCB2, around 4" toward wall, and will rotate valve
Ben said they are doing things in the field to make sure they hit the 6' - 1 5/8"
Once the shift is completed in DCB2, Ben will ping us
8/12/2026 - Architect asked about information for the Access panel layout, Ben let them know they have been distributed and they were on the email chain
Ben talked about scanning, I brought up us aligning to 3d scan after bypass installed and 3d scans complete
Isabella brought up Wall and anchor proximity, I told them what happened on another site, walls were put up, making it impossible to install anchors
Walls were floating all over the place and not accurate
Need to make sure the small distance between embed and wall is achieved
I told ben we were reconfiguring supports at MES loops so all the clashes with Valve handles will go away
LEB10 FLEX HOSE on 8" Flush skid hitting column, need to clear clashes
talked about email I sent about a list of which models to use for which trades as far as Walls, Wall Panels, Electrical, Arch, Structural etc
Kyle said he was still working on that
John Cowhey is asking about Lugs on the MES
I will chase this down, find who responded Johns email and start there
Robert Cheek responded on Monday saying he would get the answer same day, still waiting
I told Jay we are currently working through shop drawings and spools, while we are doing those we are paying attention to clashes and working through the clashes
I Brought up the FW underground being off and that we will be scanning and verifying CIA POC's, Should be doing this within a week
8/19/26 - Missed, at El Paso FOK/SOK
8/19/26 - Missed, at El Paso FOK/SOK
8/19/26 - Missed at EL Paso FOK/SOK
5/27/2026 - I BROUGHT UP LEB1 COORDINATING WITH CRIDER NO MODEL, USING HDR FOR UNDERGROUND COORDINATION
JAY BROUGHT UP TXE10 ANCHOR CLASH WITH WALL, ADAM SENT EMAIL ASKING ABOUT IT, SOMEONE SAID THEY WERE CHANGING WALL IN A EMAIL RESPONSE, ADAM REQUESTED MEETING, NO ONE RESPONDED
JAY ADDED THIS AS AN ACTION ITEM
EMMA SENT EMAIL REQUESTING CLARIFICATION, TRISTEN WAS CONFUSED
LUKE SAID HE WILL DISCUSS IN HIS MEETING WITH MORTENSON
JAY ADDED THIS AS AN ACTION ITEM
6/3/2026 - New LEB Mech and Plumbing meeting on Wed, John and Reece involved, going over FW stub up locations and F/F water gallery connections
Informed John of Convos with Greg to coordinate wall install with coring of anchor plate holes
Told Jay/John, Lance Holmes is coordinating with other trades on fix for LEB UG FW stubups not hitting POC points or dimensions
6/10/2026 - Verify Span models work on LEB10, 1, 2
6/17/2026 - Checked LEB1, Span_SS model is still only showing Labeled grids, no steel in revit linked model, 2models, same dates, different version, latest verison wont load, gives error
Bring up Walbringer as new MP contractor on LEB6, sent email out with dimension sheets for someone to get them the information
Coordination Sign off
Jay gave links to Turner and HP sign off locations
Clash Review
Jay said he will go through and filter out white noise, setup a meeting to over others. I told him whenever he wants and I will be there
Friday 6/19/22 9am
6/24/2026 - Check with Adam if he verified the lastest info from Crider lining up ug, LEB10
Check LEB1 model HDR Underground lining up with Model, We are lined up with HELM Bypass on LEB10
Luke will get with LEB and Turner for Verifying CIA Points
Louis will get with TXE and HP for Verifying CIA points
LEB6 - MP Model misalignment, I checked the Turner NWD, they are using a FTI Container that may have a misaligned MP NWC
I Put together and new NWD with current NWCs Available and everything lined up correctly
LEB, DCW Drops, Get with John to find out which way they want to go, then follow up with HDR and Helm and Waldinger
I sent John Rhee an email requesting update
7/1/2026 - Jay brought up LEB6 issue I emailed, I told them HDR still needs to update their pipe stup ups, they fixed the grid though
I brought up CIA from other GCs since they were talking about FTI Scanning HP elements, if HP didn't provide documented points what is FTI going to shoot?
Justin said yeah, it is a meta requirement but meta hasn’t really lined out what exactly is required
I told them FTI did such a great job on the document and spearheading it, I was wondering if the other GCs also maintained this document since we are connecting to systems from other trades
Jay follow up with Kyle on HP for going through HP clashing directly, can we access them, create issues, clear?
7/8/2026 - Brought up LEB10 turner models, stay with NWC, even though they have
Advised that I have moved our DCW POCs to match HELM and HDR
Advised of TXE10 Scanning schedule starting tomorrow
Waiting on Patrick B for response on HAC FCU orientation
7/15/2026 - Told Jay, I havent verified Turners FTI Container files are updated this week
TXE Told Jay, Adam noticed the Fan Coils may need rotated 180 degrees, sent email, waiting on Patrick B to look at it
Verify Bypass submittals to FTI for John Cowhey
Check LEB6 FTI Container updated
7/22/2026 - Patrick sent out email saying txe10 FCUs have been reorientated based on Adams email, he will be going to other buildings
John is still waiting for Submittal for EOL HAC Bypass, he is talking to Jacob onsite, need submittal approved and start releasing fab on those
Underground conduit was missed for TWMU Skids, they need to be run overhead, it’s a substantial amount of conduit
Sent John, Justin, Jay the Control Point Map
Told Jay I would do a fly through on Leb10, LEB2 and LEB6 checking for FTI Container alignment
Do we need to do an official submittal for the Dimensions for UG Stub ups and Bypass elevations?
Start using ACC Issues module for tthings like LEB10 Crider stub ups being off
7/29/2026 - John says, he still hasn’t received the Bypass Submittal
I told Jay I would send LEB Control point email from Richard Lopez
I said I would get with Jacob and Keylan to make sure he gets it
I gave low down of what we are scanning, including CP's, what happened with CSV from Kyle
I asked if FTI was doing Trimble next week, john said yes and they will check certain things
I explained how the columns were off, I thought HP should be verifying columns and grid lines, walls may be off
8/5/2026 - They need stub up information for Conduit for the TWMU skid
Alex Harpel says the control points may be off at TXE10, Jennifer will be going through and verifying points
I told Jay, Region 1 alignment looked good, Region 2 I will check at end of week
check leb6 slab elevations different
8/12/2026 - Jay said cerris will be adjusting model based off scans
I made comment in Blue Beam Session for Exp joint hitting MES anchors
Alec said Jennifer says she is ok with Control points at TXE, HP will remove extra brass medallions, once the buidling is turned over, she wwill verify again
I told Jay I will request building control points from Mortenson, Richard Lopez
Get jacob or check status of submittal on HAC Bypass EOL submittals, are they approved?
Verify if Cerris updated TXE10 to match scans
Meta is using XYZ to verify control points, Alec Harpel Verified this
John Cowhey asked if we can put some info together based off Nathan (SI) Trimble information regarding wall and anchor clashes
8/12/26 - Arthur stated the MES will not be moving, the MSA Frame will be adjusted to clear the clash between msa hac and mes anchor
He asked about the 8" TW Flex skid squeezing through column and mes, clashing, I let him know that was a temporary flush skid with flex pipe, we will get It through
Isabella stated that peyton will be putting together all information, and run through a list of clashing
Peyton showed the SI Duct clash with SI Mech pipe
Ryan got pissed that Darren wasn't available, saying this is such a broken proecess, arthur says hes out of his depth, Darren is double booked, Ryan said he needs to be there
Clash is showing flush access panels hitting bus duct on outside of wall
Isabella says since MCDean contracted with SJS to do clash and coordinating, they need to be present and hosting these meetings
Arthur asked Doowoo to assist in getting Darren participation and SJS participation
Ryan asked what kind of end was on the 8" flush skid, Arthur reminded it was hitting a timber column. I said it was a grooved end, we will get it through, even if we have to use a come a long, lol
8/14/26 - Cancelled
8/17/26 - They did a clash flythrough
Showed 6" FW Skid connector fittings hitting Steel frame, need to either turn MES Fiiting out, to face SKID or offset around Steel post
Also showed clashes with strut and supports, strut clamps need to be aligned to supports
Clash with pipe and steel frame, Tom asked why this clash is here but not in EMT and not the programmatic MES/HAC Steel
MCDean says they updated the steel based on CDD(?) before it is finalized, cart before the horse, they are going to do updates for tomorrow meeting
Arthur Foley (MC Dean)
First of a series of daily check in calls between Mcdean, Tate and Southland to make sure we get steel updates from Tate and clash detection
Matt Mcconnell is the PM from Tate
Should see new update tomorrow morning
Guin Yaprak verified this is the case, 10-11am tomorrow
HRV FOK will be in the NWS
MSA will be included
This will be a recurring meeting everyday
8/3/2026 - Isabella told darren about Seths response to my request for consistent elevations, which was no, she said this is unacceptable. Darren said they went to Meta about this whole situation
I informed Darren the current model they were viewing was outdated, the current model from last week shows updated alignment
Isabella said she doesn't understand why Meta got involved, that was unecessary
8/10/2026 - Tom hammered down on Coordination for HAC and clashing, sign off dates
Danton didn't have anything, he is doing MOFE coordination
Tom says we need to align
Isabella said we need work together to get this setup
I requested to sit on base build coordination meetings with DPR/ Colonial
Adam wants form to access DPR, he will give it to all
Tomas maxell and chirdon talking to structural engineer about eliminating the middle anchor on DCB100
Adam added couplings to MSA that will allevaite having to add welds for field install
Packages were created in stratus, should be able to get dates by EOW
MSA to HAC needs some couplings removed
Depending on if Ryan can put the couplings on GMP Field because Fab is hard bid
Adam will remove from on site scope, per Ryan
Adam Dial in how we want to name NWS MSA for spool sheets
Adam wants to name them so they are more in line with the stratus packing naming
Deliverables -
Sign off and install schedule
7/15/2026
Waiting on Corbon to yay or nay the middle small anchor
MC Dean is still making adj to hac steel, they did state it shouldn't affect any of our content, ian is supposed to be complete on 9/24
Adam is supposed to put couplings in MSA to stop field weld
Need this update in stratus per Ean
All packages are created in Stratus with Dates
Get with stone and scott about getting FCU in the HAC for HRV
Southland will be running our own Clash Coordination
MC Dean provides a NWC, but we are choosing to use DPRs NWD in our own Model Coordination due to being more current and includes more trades
Keith, Melanie and Peyton will be putting this together
Melanie says not to clash with their NWD, not good
Either we will use DPR Forma Model coordination, if not available, we will ask if we can bridge their models directly to our forma to run our own Model Coordination and clashes
DCB100 NWS1/4 signoff 9/22
DCB100 NWS2/3 signoff 9/29
7/22/2026
Gave run down to Thomas and Ryan of Colonial Stub ups
Trhomas says there will be a middle anchor
Peyton will be leading the Coordnation Model and space, will be issueing clashes
Will be running clashes today
Ryan did sent out an email to DPR and colonial web regarding the UG FW CWC Dim sheet showing critical dimensions
7/29/2026
Explained the moving of embed to get out of wall, will move all embed together but will cause actual anchor to shift on the embed placement
8/5/2026
Adam had to push publish, I lost stratus addin, cant find download, gave up
I updated HRV DCB100 and replaced 07 couplings with 107v
Gave isabella the work flow for Layout sheets for hot items, Sign off, Eng Review, Shop Drawings, Spools
8/12/2026
Scott asked for a full coordination schedule with dates to hit
Isabella sighed
Isabella said no, we don't have actual dates
Ryan said maybe we should be pulling back required dates from fabrication need by dates
Scott did his whole sign off and deliverable schedule rant
We are going to base our Coordination dates form DPRs precon schedule and sign off so that we are signed off with MCDean before DPRs dates
We are supposed to have approved submittals for anchors on 8/21
Document control, Isabella is the point of contact,
Scott explained , need one point of access for Sheets, we are still digging around looking for latest greatest
I obligated to once a week going through clashes, using HRV Forma
Isabella will submitt her stainless steel dog leg expansion for Tom to approve
Isabella will get with Tommy to Verify how many 14" skids they want
5/14/26 - - Joe Brought up the access panels for Flush system, asked about rating, I would have to check submittals to verify. Me and Lance holmes informed joe the flush systems are temporary, once done, they get removed and the access panel stay
Anna said they were aware, but not the finalized locations, now they will be going through Valley for engineering, excel engineering to make sure everything is accounted for, engineered
Talked to Stefan, we are not providing the Access Panel, its GC2 wall, they are providing it
I need to check on RO system, ACCess panel and it looks like location may be borked
Scott asked about sign offs for lighting scope to base build duct connections, Joe said they havent covered it, sign off is around end of June. They will be circling back to loop area not that they have certain paperwork available
Joe said any issue can be brought up at anytime
5/21/265 - No John Rhee, Brent, Thomas Holler, NO PM TEAM
They went over stud wall model, Lance asking about raceways for security and bus ducts
5/28/2026 - They went over electrical stuff, skid placement, wall leave outs
Turner wants a meeting with Helm and Southland to go over Wall penetrations
Joe D discussed Span model naming, keeping them the same and consistant.
Will need to relink LEB Span models since they have new models with Nucor suffix
6/4/2026 - Eduardo Ibanez brought up Status of Facility Water Stubups asking if Verification of Stubups with Mortenson needed. Had Crider submitted? Lance was saying Ryan would have this info and asking if Ryan was in meeting
NO PM Team present
I sent PM Team a summary email
I explained, Ryan used HDR model for coordination, I worked with HDR to get everything line up, we provided dimensions, everyone agreed to them, now stub ups are off, Lance Resposnded to John Rhees email asking what is being done
I said we need to start having meeting to go over this issue since its so critical
Luke Jost told eduardo to add an action item for this and lance said he will head this off
6/11/2026 - I brought up the FW UG being off again, told the group Ben Kozel with crider said they were backfilling in layers and trying to get the stub ups on the POC/CIA points
Overhead Signoff is schedule for 6/30
Scott asked if it was entire building for NWB, Joe says yes
Joe Brought up IMP walls changing to Framed walls, Anna? Said it was still being worked on
Verify LEB10 POC For DCW
Verify DCW POCs line up with CIA
Lance said they are also providing a hose connection for discharge, I stated they are using the FLOOR Drains in center of gallery for discharge, Adam corrected me saying John has requested different discharge points. Wouldn've been nice to know.
Someone asked about the Flex piping from the 8" skid hitting the column, I told them it was flex pipe and temporary, that it will bend around the column
Vent in 6-19x6-D, adam told them to put in between MES Skid
Waldinger is doing the bypass on LEB6
Building 6 MES loops are showing misalignment with Waldinger Bypass
NO PM Team present
I said I would like it added to this meetings notes, Joe Dorinsville basically shut it down, saying it was a field issue
I said it was our issue also since we are constantly being asked to do overlays, which were happy to help any way we can, but this was more of a helm situation since they are the responsible party to connect to the UG and provide us with accurate points of contact according to the CIA
Joe reiterated it was a field issue
6/18/2026 - Edwin Perez is showing Verification on stub ups w mortneson needed. Pending Submittal. Eng. Drawings to be submitted - Crider and Crider. He said this is still on going
Edwins model view still shows MP Shifted to plan right, access panels were to the right of the wall they are supposed to be in
LEB6 Arch Coordination model is showing everyhting off, MES Skid not lining up, mp is to the right, access panels are to the right of the walls they are supposed to be in.
LEB10, checked with Joe D, things line up there.
6/25/2026 - Joe, Greg, Luke Long, Greg went over Electrical coordination
I sent email to PM Team, no one was present
Eduardo Ibanez brought up Status of Facility Water Stubups asking if Verification of Stubups with Mortenson needed. Had Crider submitted? He brought this up again. I explained again that we provided dimensions for LEB10 and LEB1 to Mortensen, Crider and HDR, they all agreed
I told group that I also emailed these dimensions to Waldinger for Region 2, but havent received any comments or response from anyone.
Scott asked about tracking for signoff on 6/30, eduardo said yes
Luke Jost asked about LEB10 Embeds to make sure they are getting tracked by turner
Edwin Perez asked about Waldinger Bypass and alignment to SI MES Loop Connection
I told Edwin Perez I provided poc dimensions and elevations, but havent received any response
Edwin said he will bring up in next BIM meeting
7/2/2026 - Get with john as far as who is providing what cam lock adapt for fip drops
Lance Holman also provided additional dishcharges (Drains) for Flush/ fill per john
They showed model, HDR DWC Drops are on face of column, I told group IFC shows they are on Web side, HDR Model doesn’t match HDR IFCs
John Rhee is communicating changes from model to FTI, Turner that they are not telling us, Discharge drains, DCW changes
The only reason I found out was because of the meeting flythrough, our pocs were on other side of corridor
John fucking totally ignored our information and didn't relay any information
I missed the HDR IFCs showing the drops on the plan south side of corridor
I explained LEB6 model misalignment was fixed, publishing issue, I will double check mondays model after the Saturday auto publish
I told group about the FW UG Dimension sheet that has been distributed multiple times and it details where the FW UG stubs are supposed to be ever since LEB1
I will double check LEB2 misalignment
They showed LEB6 and the 8" skids were into the columns again
I explained the deep dive I did last week, it shows everything aligned. There are issues with the FTI Container model that Turner is using for coordination
7/9/2026 - Setup LEB2 SI MP View off turner LEB2 Overall Building NWD, Crider is still off at Grid 2-50/ 2-D
Eduardo Ibanez hosted
LEB10
All Content on slab will be created in a file, progress is ongoing. Jay Asked what does this entail? Above Slab content?
LEB6
Our MP is still out of alignment in Turner LEB6 Overall Building.nwd, but Joe pulled in a recent nwd and it showed the FTI Container inside the Overall nwd is off
With joes pulled in NWD that shows us and waldinger aligned, Crider was still off around 8-10"
SI Duct and Waldinger do not align
Justin verified that Turner is using NWC files NOT the revit
Southland MP looks good
Southland MP model is still a little older, but non-critical
7/16/2026 - Joe D brought up some issue about control joints at LEB10, luke jost and jay kaiser will update as necessary
7/22/2026 - Joe D brought up control joint proximity to MP anchors, they scooted 1 at grid 29ish, no TW Skid.
Checking Coord Space at LEB I see Stratus models getting exported again on 7/17, that was last Friday
The only MP model available is from april, what the fuck is going on with this fucking shit
The LBE10 Publish settings were set to stratus, talked to heath, he showed adam was the last one to do it. Adam said he didn’t know had to change settings back
Lance suggested a meeting with FTI and Southland to get power to TW Skids, Lance Long said they have a meeting setup with FTI Tomorrow, looking at junction box on the wall
Jay K at FTI created an issue with Crider Facility Water Alignment and was trying to add crider watchers, he can only add FTI watchers.
Joe D told him to use Triston with Helm, Mitch with Waldinger
Mitch with Waldinger said it looks like its going to work out with aligning their Bypasses with Southland MP
Jay K brought up container models having outdated southland models
Joe D says its tough to say when the FTI container was reloaded. The last update they show was july 13th, 10 days ago
I rbought up the TW Skids on each end of the building also to check, they have anchors also
I stated I found a recommendaiton of 3" distance between an anchor and a sawcut or concrete joint
7/30/2026 - Jay brought up getting control points from Turner
Jay brought up missing MES/ TW skids from LEB1, LEB2 FTI Container, the MP content was aligned
8/6/2026 - I affirmed with Jay, I have not seen any blue beam sessions
I verified LEB 6 in Navis, using the View I created with all trades
James (Turner) is setting up meeting next week to go over CIA points with FTI and Baker
Jay asked about established control points, joe said bring it up in the session
8/13/2026 - Helm modeled their bypasses to the current asbuilt points received Last Friday, This Monday
I told Joe we would wait for the actual asbuilt 3d scans before we do any further model aligning. It’s a waste of time right now, to turn around and have to do it again after scans are received.
8/20/2026 - I told them again we will be able to squeeze the 8" Flex skid around the column, its a flex pipe and not an issue
Melanie Working through EMT Models, links needed repathed
Go Through EMT1 and EMT2 and make sure MES, TW and MP content are good
IF good, push to Revizto
Also check MSA/FSHAC Piping
EMT Does have IFC's for Base Build, Scott showed them yesteday, I coulda swore we didn't have any sheets, prob thinking of HRV
7/16/2026 - Melanie says our MP model doesn’t line up with Eng Model, we are using Lightning Shared Coordinates, Eng is using ETM100
Abe - Attached Sign off schedule to summary email, have content populated and coordinated ahead of signoff dates highlighted in RED, these dates line up with Mortenson
I told her our content, mes content lines up in revizto, if you change anything, it will no longer line up
Download arch model, link our models in and see who lines up
She says archs did change the g datum model a while back, she had to repath it and that’s when things stopped lining up correctly
7/17/2026 - Cancelled
7/20/2026 - Cancelled
7/22/2026 - Ryan says Mortenson is on the verge of issue stop work order with Meta due to electrical incompetetance
7/23/2026 - Cancelled
7/30/2026 - Cancelled
8/6/2026 - Adam said he will cover EMT, I will do the LEB Meeting
8/20/26 - Asked Richard Lopez if anyone is using shared building Control Points, him and nick both deferred to turner. I said I am used to a site wide control point map that is shared with all trades. I understand this is a bit of unique job with 3 GCs though
Richard corrected his statement and said turner actually did have a meeting last week with him and Nick, he wasn't sure if it was a recurring meeting but would look at getting information dispersed.
Ryan Zoldan - Richard Lopez
LEB 6 due finalized next week
I requested a schedule from Ryan, he has the sign off, region schedule, I brought up a pull plan, be he says that will be through Turner
Mortensen is the Base build GC, why aren't they leading a pull plan schedule
John Rhee nor Brent were in this meeting
6/4/2026 - I brought up the LEB10 FW UG Stub ups totally missing the Dims, Ben Kozel was there and he stated they are bringing them back in to dimensions by backfilling a little and moving them, backfilling and moving them
He acknowledge that lance did contact him
6/11/2026 - Ben Kozel, said there were no issues that need to be talked about.
Richard lopez asked around the room for any issues regarding LEB10 or any others
NO PM Team
6/18/2026 - Richard Lopez Hosted, just asked for any issues with LEB10,1,2,3 Underground issues
Rantwiler asked when IWM for TXE10 was going to be signed off, Ethan says he will talke to kyle since they are not really split out
6/25/2026 - Going over LEB7,8
Ryan brought up LEB6, HDR model is not lining up with the Dimensions provided by SI
Ryan henderson said he will follow up
Ryan said we have all agreed to follow these dimesions, I added that I have distrubuted that dimesion sheet ot Waldinger and explained everything, but havent received a response yet
Ryan brought up LEB6, HDR model is not lining up and my email I sent out
I updated, still waiting for HDR to align the stubups
Ryan said Crider is using civil 3d, but we can work it out to actually use their model for coordination and linking in so I don't have to use HDR
7/9/2026 - No issues to cover, they went over UG clashing for elect, sanitary
7/23/2026 - Richard asked Triston about any alingment issues, he was good
Ben said LEB6 stil had some very minor HDR alignment issues to on udergoung
7/30/2026 - Bend said LEB6 looked good
I said we republished LEB6, there was some extra content we had to remove
8/6/2026 - I brought up the LEB10 FW UG Stub ups totally missing the Dims, Matt Schaff said they are doing repairs this week and lookingat getting into within an inch
I mentioned, for helms benefit of using Eccentric reducers on bypass in order to rotate the stubup to align with MES better
I also mentioned after slab is poured, bypasses installed, we look at doing 3d scans
TXE1 looks good for the loop area sign off next week
Same with TXE2
6/4/2026 - Own B ran the meeting going over TXE1 and 2
6/11/2026 - Owen B, says TXE10 Loop for sign off
TXE2 Core scheduled for next week
TXE10 AB Datahall and Loop are signed off
TXE3 Alan lopez is running region 2 for signe off
TXE2 Loop and AB South sign off
issue 2602 - Cerris Vent in corner is clashing with Technical water, Rantwiler is saying they don’t have our model, I told them our model has been there for 6 months, the fact that HP is viewing it, means the model is available. If it’s a bridging issue we will help Cerris work it out
Trevor said he will get with rantwiler and get the model bridged, they will offset that vent around our TW Piping
They made comments about the TW skid being so close to the FW valves. Its been this way for over 6 months. Trevor also stated the vent will need an accessible cleanout
6/25/2026 - They just went over IWM and specific Electrical clashes
7/9/2026 - TXE 2 all docs are out, all sign offs are out
TXE1, 2 sign offs left
DHCD 2 weeks from now
7/22/2026 - No Issues
8/20/2026 - They didn't cover anything relevant to us.
Verify 107V and 07 Couplings on Pup pieces, region 1
Adam said we are still working through comments, still waiting on cantilever approval.
LEB10,1,2 will be good to push out to submit to tom
Need to update regions to datahall A,B,C,D
Day zero is 2/25/27
Need spools before 1/5/27, Adam said we wiill shoot for 6-8 weeks before then to allow for review, updates, etc
Scott says EORs get officially submitted to Tom, he approves, they get submitted to FTI. Not sure if EORs get submitted to Meta or not as part of record drawings
Scott says by Friday the 14th they will publish to stratus
Embed Layout Drawings
We gave drawings, we will have
Crider and Mortenson will provide scans once they are finished, so that helm can update their bypass.
Flush Skid BOM, Curtis used TXE Counts and ordered the material
Hose Carts are still being finalized
Get Reece copies of TXE Flush skid BOM information
Hose Carts will be finalized once FOK and SOK are done
No pour until november
Schedule model? Can we incorporate this?
LEB10 UG Stubup status
Crider, Mike Schaff said they were doing repairs this week
Make sure LEB PM Team knows we need to scan after slab, after bypasses installed, then we align, update spools
8/14/2026 - Cancelled
8/21/2026 - Bring up mentioning Control Points in Meeting yesterday with Richard Lopez (Mortneson), says they dont have any Interior building control points, get with Turner, then said they had a meeting last week with turner, he will check if its recurring
Talked about the 30 email chains from Lance, Jake Wright, Casey, Triston and Ben. The lastest is from Helm asking if their points are good.
Talk to triston about their flush fill, are they using the existing bypass or adding a temp one?
Peyton showing MES MP Pipeing into duct and framing, mic didn't work so I couldn’t talk to verify MES Elevations
8/3/2026 - Abe said UCO3 UG Signoff is pushed to next week
Peyton going over clashes
#816 shows vesda FP content going through our bypass at hac, adam modeled the vesda
MH Duct at EMT1 was low, scott said he will take a look
8/10/2026 - Melanie says she will look at MES Alignment, I said on Saturday mes was mis-aligned again
Adam said he will fix Vesda Clash with HAC EOL Bypass
I said the MES Loop/ Flush Loop piping needs to be reconfigured, its clashing with TWMU Skid, the tee will get rolled to vertical and cantilever pipe supports will be brought in
830amMCD + Southland + Tate / FSHAC Coordination
Arthur Foley (MC Dean)
First of a series of daily check in calls between Mcdean, Tate and Southland to make sure we get steel updates from Tate and clash detection
Matt Mcconnell is the PM from Tate
Should see new update tomorrow morning
Guin Yaprak verified this is the case, 10-11am tomorrow
HRV FOK will be in the NWS
MSA will be included
This will be a recurring meeting everyday
8/3/2026 - Isabella told darren about Seths response to my request for consistent elevations, which was no, she said this is unacceptable. Darren said they went to Meta about this whole situation
I informed Darren the current model they were viewing was outdated, the current model from last week shows updated alignment
Isabella said she doesn't understand why Meta got involved, that was unecessary
8/10/2026 - Tom hammered down on Coordination for HAC and clashing, sign off dates
Danton didn't have anything, he is doing MOFE coordination
Tom says we need to align
Isabella said we need work together to get this setup
900amLightning TXE Staff Meeting | Meeting-Join | Microsoft Teams
Jacob Gelhousen
Will do scans after Cerris installs bypasses
6/1/2026 - Noel Nunez says Alehandro Chew will be safety manager
Michael said he sent TXE3 embeds along with PDF dimension in mid April
Doesn’t think TXE3 has been poured, think they are behind schedule
Says we havent been funded for Region 2, he is sending out embeds as needed
Michael asked what the question was about RO and TW, I said it was going over how to connect to the RO skid, from DCW and to TW MES
Michael asked if MES Loops were completed, adam said yes, he created new BOMs
Michael said his goal is to get everything ordered
Michale Paul said they thought the walls weren't going to be in until they could do anchor
They said that was what was agreed to
6/8/2026 - Michael said they had a PM Coins Mandatory meeting and couldn't host the meeting
6/15/2026 - Chris Moss came on board from TSMC, Pipe fitter, GF
Jose Alejandro Chew, new Safety Manager for TXE
6/22/2026 - Shop drawings (Engineer Drawings) looking at submittal on Frid, 6/26
6/29/2026 - Keylan Cancelled
7/6/2026 - Carson will scan on Thursday
7/13/2026 - Scans on TXE10 complete, should have done this week, EOW
Jacob will be pulling field measurements of FW Stub ups
Adam will overlay scans to see how they match up with our Stub Ups
SOK will be starting next week, 27th will have more setup covered
7/16/2026 - Zach wants scanning sent back out, scan off control points, need to get CPs from Greg, put in model, talk to carson to see what they need from us
Control points were requested on 6/12 meeting with Greg H, it was stated they would be sent to Michal and James Homrighausen
I also asked for control points from Luke Justice on 5/21, he said he would get with Greg H.
They made it out like it was detailing fault they scanned without using control points
Paul asked how soon I can get the points into model, I said immediately, but Im not sure scanning needs anything from us, they may input control points into the rcap software maually but we will have it the model if they need it
7/27/2026 - Scanning this week
FTI Will be doing Trimble next week
8/3/2026 - Adam brought up new pipe supportts that were sent to Tom due to more access to mes loop valves
Adam asked about tapped caps for mes connections, michael said it was a miss on them so they will cover it
Trimble is shooting wall points tomorrow and Wednesday
8/10/2026 - Asked about txe2, keylan said they have bottom plate down, trimble is showing walls off
Asked about info for points from trimble, is this for field use only, are they showing HP where walls are off
Keylan says they are using the info to show HP were walls are off, TXE1 had walls off, HP is still working on solutions
I asked for TXE2 Cerris bypass schedule so we can get scanning out
He said he would get me that info
Need to ask about Access panels, whos providing?
Need to ask about info for HP saying they are having issues with control point discrepancies
Keylan said he will double shcek with paul and nate
Paul says he hasn't heard anything about control points, alec says HP is suggesting we move our anchors
FTI says Jennifer is gong to get involved and veriy, Meta says they will send their own Surveyors out to verify, this was last I heard
I will put together an email of who said what in which meeting and send to keylan to start a chain
1130amMW Detailing Weekly Meeting
6/29/2026 - Marshall Cancelled
7/13/2026 - Missed, I thought it was cancelled
7/20/2026 - Armondo party on Friday
De Le Cruz tips and tricks, Title Blocks
7/27/2026 - Missed, went to Cameron Shop to meet Mid Atlantic Crew
8/10/2026 - Start detaiing on Texas Carusoe for Engineering
Ed Meza doing tips and tricks on Revizto
1200pmEMT BIM Look Ahead Meeting
Nate Black (Mortensen)
UCO3 OH Signoff 7/24
Went over drone map, EMT1 and 2 have UG FW
Went over sign off schedule
Showed Marcos Revizto Clash Workflow
Showed UCO3 Loop OH
7/20/2026 - Went over drone view of jobsite
Joseie with delta went over heat safety
no PM Team
Got UCO3 sign off for OH on 7/24
7/27/2026 - Missed, went to Cameron Shop to meet Mid Atlantic Crew
08/11/26 - TUE (+8 Meetings)
600amHRV Schedule Review/ Discussion
Curtis Robbins (DPR)
Went over no permits, permit submittal, job pushed out 81 days
No PM Team in meeting
8/11/2026 - No Meeting
630amEMT - Lightning BIM Weekly Coordination
Abe Hernandez
Printed IFC Addendum 1
Scott showed Mortenson schedule 7/6
Peyton Coordination Model - Meeting with Heath, model is setup, need to get heath input
Using forma coordination module for clash detection
Cupertino says they are fine using the Forma module
Ryan - wants the model defined as to which one to use and clash with for Cupertino
Scott says he is on it
I let abe know that the MES and MP constructability models are now in the Revizto publish
He told Cupertino they can use that
Scott asked about elec panels hitting columns, I shared a fly by on Revizto and it didn't show any issues on UCO3
I showed the team Temp Power and Skyline clashing with MES Loops
I also emailed Nate Black last Friday
Ryan Warner says there is tees clashing on underground with Cupertino in elec gallery
7/21/2026
7/28/2026 - Cancelled
8/4/2026 - Abe Hernandez
Alex Hubbard
NWS Has above ground changes due to elec bus work
8/11/2026 - I brought up the EMT Flush Skid Package, let everyone know what it was and if they get a chance to look it over, see if anything pops out.
Ryan said he will make sure Seth and Brandon put eyes on it
700amEMT Touch Base with Brandon
Adam Brown
Brandon Marse, Field Superintendant for EMT
2-3 Weeks needs UG Scanned for Facility Water, so they can see where they land and build bypasses of those scans and then scan again after bypasses installed
Said he would get us Control Point Information
Need to get Submittal #5 into Lightning Program Forma for EMT, Anchor Spool
Building bypass in Stainless, something about stopping any containmination of the HDPE
Adam showed where anchor layout was, the anchor embed template and is getting with tom to make sure Submittal #5 EMT specific Anchor approved submittal gets in the Lightning Forma
800amWeekly BIM Coordination Meeting - Region 2 (ZOOM)
Alan Lopez, Kyle Cummings (Hensel Phelps) / Ethen Berry
No one started the meeting, I sent an email, they said Alan was PTO and they started meeting late
They went over Region 2 underground, sign off later this week
5/26/26 - Allen Lopez Went over Region 2 again, said they were going to do a main signoff then a branch signoff. Covered a lot of UG clashes
6/2/2026
2 weeks sign off branch
6/9/2026
6/16/2026
Allen Lopez says he doesn't see Sure Steel model in TXE3, Kyle says also no Diversified, but Sure Steel model is there, needs added
Signoff schedule was not bridged, the one on FTI is outdated. Kyle and Justin said they would get the bridge up to date
Files - Data Management
6/23/2026
6/30/2026
7/7/2026
TXE3 Overhead Loop signoff next week
TXE3 Overhead Datahall signoff is July 27th
7/14/2026
7/21/2026
TXE3 Loop OH Signoff on Friday, DHA/B Following week
NO PM or Field Team present
8/4/2006
8/11/2026
Went over hac coordination with electrical
Electrical stub ups
Didn’t see any hac piping, got with adam, we need to get hac piping copied in
830amLEB - BIM Coordination Meeting (Tue) | Meeting-Join | Microsoft Teams
Ryan Zoldan, Mortenson (GC1), Richard Lopez (Mortenson)
Missed for the 8am meeting
6/16/2026
6/23/2026
6/30/2026
7/7/2026
Ryan brought up their grids were off, crider and crider will be aligned today and HDR will be aligned. For LEB6
Ben Kozel says all waldinger was missing a flange on their bypass, everything else looked good, crider was good
Ben says HDR looks good for UG and Grids
7/21/2026
Talked about LEB6 HDR not matching Soutland provided dimensions, bullet point #1, supposed to be covered in meeting tomorrow
Talked about Underground stuff
8/11/2026
Ben Kozel says there are new point files available as of Friday, he dropped in Chat
830amMCD + SOUTHLAND + TATE/FSHAC Coordination Check IN
Updates to MSA piping completed and pushed to ACC, cantilever supports, support changes
RFI 146, MOFE OFE
MES PIPING ALIGNMENT WITH MSA Alignment is different
04 MES skid, make sure MSA is aligning with MES 04 skid based on this RFI
MAKE sure MSA SKUS are updated
Make sure MES Skid 04 includes this RFI
Give Arthur and team updated info so they can verify steel is appropriate
Darrin says HRV1 and HRV2 Clashing models are complete
Running clashing through Navis, our VDC Team should be able to get access
I asked about Southland being able to view their clashes
Darrin said they were having disccussions about moving their clashing to ACC Model Coordination
I said we would touch base and peyton is spearing heading our clashing coordination to see what direction we will go
Scott Brought up HAC Alignment and things not centered
Arthur said they will check it out
We need to make sure the SOUTHLAND MES Model is bridged to MCDEAN so they can use that model
Follow up with Melanie, heath
I sent out a clarifying email that since the mes models are host on MCDean, they don’t need bridge. I told them the models we are using for coordination
8/11/2026
1000amLightning-Eng-Coord Huddle | Meeting-Join | Microsoft Teams
Tia/ Tom
Follow up on HAC Panel clashes with Patrick Brinnehal
Meeting to go over stratus and models with all PMs, Adam, Scott, Supers sometime next week, look at schedules
Chris Chase is the PM of EMT
5/26/2026 - Check if Adam got the 4" Welded Bypass to Shop, from 5/5/25 email in Inbox "Im shooting to have the LTG build out scope package done by end of week (For Review only not for construction). "
Verify what spools have been put on stratus for TIA/TOM Lightning huddle
Need meeting to discuss, txe10 anchor clashing with interior of walls, adam sent info out about conflicting models, but as of today, there is still clashes
RFI says they are changing wall to Gypsm board and expanding toward corridor 2.5"
6/2/2026 - We did get 2 more sites in Ohio
SI will be integrator
Heath introduced Peyton Steveons as VDC supervisor
Starting with HRV
Melanie introduced Vasi, VDC specialist helping out ron and melanie
Tia went over deliverable schedules
Per site, per building
She setup a break out meeting
Adam said they are moving the walls away from anchors so we are clear
Adam said we are 1/2" clear from plate, it will be a field issue installing the plate
Michael said he will talk to paul, he doesn't know what to do, he will call greg
only 2 walls changed from IMP, 2 others are still IMP
Michael said Greg told him they are putting walls up next week
Told Tia I sent snip of Dog Leg Metraflex in chat, didn’t get any smiles
Let her know we have LEB complete, TXE10,1,2 is complete
Adam said he will give link to CIAs, TXE3-12 and LEB3-12 not ready
Adam had meeting with HRV, told them to start using our coordination models for coordination
Quick hello, this is who we are meeting
with MC Dean
Mealnie says they will be updating projects to new architect model
Type F - 4 buildings
Type G - 2 buildings
6/9/2026 - Adam said they are going to move the MSA, HAC spools to the Lighting Program, for one source
Melanie and Keylan said it can be done
6/30/2026 - FTI wants scanners badged
TXE1 special Support approved
H Support hanger, supposed to get stamped this week
HRV supposed to get linked in models setup so we can coordinate ug
Need to verify LEB and TXE CIA points
SS Headers are in fab per EAN
John Rhee asked about Waldinger misaligned, we are now good, sending email showing HDR is off
Toms Eng review comments will be looking at doing updates next week
HRV Embed Dims, ryan says he has, I have Angle working on them now, wtf?!!!
PIQ, melanie is setting up, I asked her to keep an eye out for the BIM ex plan and contact list
Michael said they have drug test this week, orientation on Monday
7/7/2026 - Cancelled
7/14/2026 - Melanie is going through EMT with cupertino to verify alignment
Isabella asked about clashing HRV, Peyton will be running coordination model for HRV as well as EMT
HRV Embed sheets need to be sent to Basebuild, adam mentioned
Still waiting on word a
7/27/2026 - Adam said Zach gave him the low down on the CIA, it is not a contractual document, it was sebastian telling faith to do it
8/4/2026
8/11/2026 - Michael says all walls are off, asked me and adam to comment, I said get us the points, we can drop them in model, create a document to be used to create an issue and escalate it
HRV, MCD Dean working through hac and pipe clash
I brought up the control point issue at TXE
Metas involved with their surveyors according to Louis Saldana, FTI was supposed to verify with Jennifer
John Rhee says they will need to bring up the bypass support in their next meeting when Tia relayed toms concerened about it
LEB only wants 2 14" skids, need to update maps and bom
John verified there were 11 8" and 6" skids on the BOM package for LEB
He dropped Trimble information into chat
1200pmTXE-Region3 Coordination Meeting
Jade B Lowe (Hensel Phelps)
Jade is in charge of Region 3
Kyle cummins is in charge of site
Filll out contact excel sheet, put bim lead and project manager
Kyle - LOD 450 project, all installed elements are modeled, then asbuilts are fed back in to model
Indicate in the model some where that the asbuilt has been applied and model has been adjusted
6/16/2026 - Decided not to go to this one since its Region 3, TXE6,7 undergound
7/21/2026 - Missed meeting since they are covering base build
7/28/2026 - Missed meeting since they are covering base build
8/11/2026 - Missed meeting since they are covering base build
08/12/26 - WED (+6 Meetings)
700amHRV - EoR Coordination Call
Ben Speese
CWC Neema Faryar(ARUP)
Gave thrust block info
Carl and Seth are present from CWC
Neema says stub ups need to be slurried, underground pipes need to be verified for undergound thrust and that passive soil will be sufficient
Above ground thrust will be satisfied by slurry and surrounding footers
MC Dean Bridged files
Danton Wein with MC Dean
MDI has steel and skids, fabrication
ENG has electrical equipment
They both have all links turned on, these need turned off
mcd plan for trench moving, not relating to Southland
Southland
MP Model connections to FW UG Stub ups
Need CWC Bypass, will they be included in the CWC Model we already have or in a separate above ground model?
Ben verified the models are good
Ben then went to stub ups and neema took the convo to RFI something, I said we were going to take a first pass at matching CWC Stub ups
Neema was talking about some kind of trnech shit moving that didn’t apply
7/15/2026 - Adam CWC said no update on the bypass for CWC
7/22/2026 - Talked FWM and MCUP issues mainly
Eli from Colonial was present
Neema says they need to move FW Stup ups away from footer about 5"
I mentioned they need to hit the critical North south dimension of 6'-1 5/8" to match the mes skid line, but we can match whatever movement they do east and west
Ben and Neema both pointed out CWC can rotate bypass valve to the front, one of the bypasses was already rotated this direction, CWC started to fight back a little bit
This means CW Will need to move their stub ups to get out of way of footers
Danton affirmed that the 2 MDC ENG and MCD MDI Models are the current models for the FSHAC
Storefont issues
7/29/2026 - Ben gave dimesnions of shift in DCB2, around 4" toward wall, and will rotate valve
Ben said they are doing things in the field to make sure they hit the 6' - 1 5/8"
Once the shift is completed in DCB2, Ben will ping us
8/12/2026 - Architect asked about information for the Access panel layout, Ben let them know they have been distributed and they were on the email chain
Ben talked about scanning, I brought up us aligning to 3d scan after bypass installed and 3d scans complete
Isabella brought up Wall and anchor proximity, I told them what happened on another site, walls were put up, making it impossible to install anchors
Walls were floating all over the place and not accurate
Need to make sure the small distance between embed and wall is achieved
I told ben we were reconfiguring supports at MES loops so all the clashes with Valve handles will go away
I told team I had DCB90 aligned and published
800amTXE/LEB Weekly Internal BIM Coordination | Meeting-Join | Microsoft Teams
Jay Keiser - FTI
LEB10 RO Hitting Column
LEB10 FLEX HOSE on 8" Flush skid hitting column, need to clear clashes
talked about email I sent about a list of which models to use for which trades as far as Walls, Wall Panels, Electrical, Arch, Structural etc
Kyle said he was still working on that
John Cowhey is asking about Lugs on the MES
I will chase this down, find who responded Johns email and start there
Robert Cheek responded on Monday saying he would get the answer same day, still waiting
I told Jay we are currently working through shop drawings and spools, while we are doing those we are paying attention to clashes and working through the clashes
I Brought up the FW underground being off and that we will be scanning and verifying CIA POC's, Should be doing this within a week
5/27/2026 - I BROUGHT UP LEB1 COORDINATING WITH CRIDER NO MODEL, USING HDR FOR UNDERGROUND COORDINATION
JAY BROUGHT UP TXE10 ANCHOR CLASH WITH WALL, ADAM SENT EMAIL ASKING ABOUT IT, SOMEONE SAID THEY WERE CHANGING WALL IN A EMAIL RESPONSE, ADAM REQUESTED MEETING, NO ONE RESPONDED
JAY ADDED THIS AS AN ACTION ITEM
EMMA SENT EMAIL REQUESTING CLARIFICATION, TRISTEN WAS CONFUSED
LUKE SAID HE WILL DISCUSS IN HIS MEETING WITH MORTENSON
JAY ADDED THIS AS AN ACTION ITEM
6/3/2026 - New LEB Mech and Plumbing meeting on Wed, John and Reece involved, going over FW stub up locations and F/F water gallery connections
Informed John of Convos with Greg to coordinate wall install with coring of anchor plate holes
Told Jay/John, Lance Holmes is coordinating with other trades on fix for LEB UG FW stubups not hitting POC points or dimensions
6/10/2026 - Verify Span models work on LEB10, 1, 2
6/17/2026 - Checked LEB1, Span_SS model is still only showing Labeled grids, no steel in revit linked model, 2models, same dates, different version, latest verison wont load, gives error
Bring up Walbringer as new MP contractor on LEB6, sent email out with dimension sheets for someone to get them the information
Coordination Sign off
Jay gave links to Turner and HP sign off locations
Clash Review
Jay said he will go through and filter out white noise, setup a meeting to over others. I told him whenever he wants and I will be there
Friday 6/19/22 9am
6/24/2026 - Check with Adam if he verified the lastest info from Crider lining up ug, LEB10
Check LEB1 model HDR Underground lining up with Model, We are lined up with HELM Bypass on LEB10
Luke will get with LEB and Turner for Verifying CIA Points
Louis will get with TXE and HP for Verifying CIA points
LEB6 - MP Model misalignment, I checked the Turner NWD, they are using a FTI Container that may have a misaligned MP NWC
I Put together and new NWD with current NWCs Available and everything lined up correctly
LEB, DCW Drops, Get with John to find out which way they want to go, then follow up with HDR and Helm and Waldinger
I sent John Rhee an email requesting update
7/1/2026 - Jay brought up LEB6 issue I emailed, I told them HDR still needs to update their pipe stup ups, they fixed the grid though
I brought up CIA from other GCs since they were talking about FTI Scanning HP elements, if HP didn't provide documented points what is FTI going to shoot?
Justin said yeah, it is a meta requirement but meta hasn’t really lined out what exactly is required
I told them FTI did such a great job on the document and spearheading it, I was wondering if the other GCs also maintained this document since we are connecting to systems from other trades
Jay follow up with Kyle on HP for going through HP clashing directly, can we access them, create issues, clear?
7/8/2026 - Brought up LEB10 turner models, stay with NWC, even though they have
Advised that I have moved our DCW POCs to match HELM and HDR
Advised of TXE10 Scanning schedule starting tomorrow
Waiting on Patrick B for response on HAC FCU orientation
7/15/2026 - Told Jay, I havent verified Turners FTI Container files are updated this week
TXE Told Jay, Adam noticed the Fan Coils may need rotated 180 degrees, sent email, waiting on Patrick B to look at it
Verify Bypass submittals to FTI for John Cowhey
Check LEB6 FTI Container updated
7/22/2026 - Patrick sent out email saying txe10 FCUs have been reorientated based on Adams email, he will be going to other buildings
John is still waiting for Submittal for EOL HAC Bypass, he is talking to Jacob onsite, need submittal approved and start releasing fab on those
Underground conduit was missed for TWMU Skids, they need to be run overhead, it’s a substantial amount of conduit
Sent John, Justin, Jay the Control Point Map
Told Jay I would do a fly through on Leb10, LEB2 and LEB6 checking for FTI Container alignment
Do we need to do an official submittal for the Dimensions for UG Stub ups and Bypass elevations?
Start using ACC Issues module for tthings like LEB10 Crider stub ups being off
7/29/2026 - John says, he still hasn’t received the Bypass Submittal
I told Jay I would send LEB Control point email from Richard Lopez
I said I would get with Jacob and Keylan to make sure he gets it
I gave low down of what we are scanning, including CP's, what happened with CSV from Kyle
I asked if FTI was doing Trimble next week, john said yes and they will check certain things
I explained how the columns were off, I thought HP should be verifying columns and grid lines, walls may be off
8/5/2026 - They need stub up information for Conduit for the TWMU skid
Alex Harpel says the control points may be off at TXE10, Jennifer will be going through and verifying points
I told Jay, Region 1 alignment looked good, Region 2 I will check at end of week
check leb6 slab elevations different
8/12/2026 - Jay said cerris will be adjusting model based off scans
I made comment in Blue Beam Session for Exp joint hitting MES anchors
Alec said Jennifer says she is ok with Control points at TXE, HP will remove extra brass medallions, once the buidling is turned over, she wwill verify again
I told Jay I will request building control points from Mortenson, Richard Lopez
Get jacob or check status of submittal on HAC Bypass EOL submittals, are they approved?
Verify if Cerris updated TXE10 to match scans
Meta is using XYZ to verify control points, Alec Harpel Verified this
John Cowhey asked if we can put some info together based off Nathan (SI) Trimble information regarding wall and anchor clashes
NO PM/ FIELD TEAM
830amMCD + SOUTHLAND + TATE/FSHAC Coordination Check IN
Updates to MSA piping completed and pushed to ACC, cantilever supports, support changes
RFI 146, MOFE OFE
MES PIPING ALIGNMENT WITH MSA Alignment is different
04 MES skid, make sure MSA is aligning with MES 04 skid based on this RFI
MAKE sure MSA SKUS are updated
Make sure MES Skid 04 includes this RFI
Give Arthur and team updated info so they can verify steel is appropriate
Darrin says HRV1 and HRV2 Clashing models are complete
Running clashing through Navis, our VDC Team should be able to get access
I asked about Southland being able to view their clashes
Darrin said they were having disccussions about moving their clashing to ACC Model Coordination
I said we would touch base and peyton is spearing heading our clashing coordination to see what direction we will go
Scott Brought up HAC Alignment and things not centered
Arthur said they will check it out
We need to make sure the SOUTHLAND MES Model is bridged to MCDEAN so they can use that model
Follow up with Melanie, heath
I sent out a clarifying email that since the mes models are host on MCDean, they don’t need bridge. I told them the models we are using for coordination
7/29/2026 - Isabella said she talked to Tom Chirdon and Tom Maxwell, couldn’t determine where RFI 146 was, white its not in programmatic forma
Arthur wants to do same time tomorrow with USCE and Tom Chirdon so we can all get on the same page
It will be Wade from USCE
Isabella asked about clashing and updating steel model
Update tomorrow
Need hac model completed before we can finalize placement of Fan Coils
Peyton is talking to Darrin about seperating the models for clash coordination
What DCIS is it? 4374, is what this write up refers to
Arthur said he will get with meta and make sure it gets escalated to Meta so it gets handled on a programmatic level
8/12/2026 - Arthur stated the MES will not be moving, the MSA Frame will be adjusted to clear the clash between msa hac and mes anchor
He asked about the 8" TW Flex skid squeezing through column and mes, clashing, I let him know that was a temporary flush skid with flex pipe, we will get It through
Isabella stated that peyton will be putting together all information, and run through a list of clashing
Peyton showed the SI Duct clash with SI Mech pipe
Ryan got pissed that Darren wasn't available, saying this is such a broken proecess, arthur says hes out of his depth, Darren is double booked, Ryan said he needs to be there
Clash is showing flush access panels hitting bus duct on outside of wall
Isabella says since MCDean contracted with SJS to do clash and coordinating, they need to be present and hosting these meetings
Arthur asked Doowoo to assist in getting Darren participation and SJS participation
Ryan asked what kind of end was on the 8" flush skid, Arthur reminded it was hitting a timber column. I said it was a grooved end, we will get it through, even if we have to use a come a long, lol
900amLightning HRV - Internal Detailing Meeting
Isabella Vesce Rivera
Bridged files from Colonial
Isabella will bring up we need bridged file
I requested to sit on base build coordination meetings with DPR/ Colonial
Adam wants form to access DPR, he will give it to all
Tomas maxell and chirdon talking to structural engineer about eliminating the middle anchor on DCB100
Adam added couplings to MSA that will allevaite having to add welds for field install
Packages were created in stratus, should be able to get dates by EOW
MSA to HAC needs some couplings removed
Depending on if Ryan can put the couplings on GMP Field because Fab is hard bid
Adam will remove from on site scope, per Ryan
Adam Dial in how we want to name NWS MSA for spool sheets
Adam wants to name them so they are more in line with the stratus packing naming
Deliverables -
Sign off and install schedule
7/15/2026
Waiting on Corbon to yay or nay the middle small anchor
MC Dean is still making adj to hac steel, they did state it shouldn't affect any of our content, ian is supposed to be complete on 9/24
Adam is supposed to put couplings in MSA to stop field weld
Need this update in stratus per Ean
All packages are created in Stratus with Dates
Get with stone and scott about getting FCU in the HAC for HRV
Southland will be running our own Clash Coordination
MC Dean provides a NWC, but we are choosing to use DPRs NWD in our own Model Coordination due to being more current and includes more trades
Keith, Melanie and Peyton will be putting this together
Melanie says not to clash with their NWD, not good
Either we will use DPR Forma Model coordination, if not available, we will ask if we can bridge their models directly to our forma to run our own Model Coordination and clashes
DCB100 NWS1/4 signoff 9/22
DCB100 NWS2/3 signoff 9/29
7/22/2026
Gave run down to Thomas and Ryan of Colonial Stub ups
Trhomas says there will be a middle anchor
Peyton will be leading the Coordnation Model and space, will be issueing clashes
Will be running clashes today
Ryan did sent out an email to DPR and colonial web regarding the UG FW CWC Dim sheet showing critical dimensions
7/29/2026
Explained the moving of embed to get out of wall, will move all embed together but will cause actual anchor to shift on the embed placement
8/5/2026
Adam had to push publish, I lost stratus addin, cant find download, gave up
I updated HRV DCB100 and replaced 07 couplings with 107v
Gave isabella the work flow for Layout sheets for hot items, Sign off, Eng Review, Shop Drawings, Spools
8/12/2026
Scott asked for a full coordination schedule with dates to hit
Isabella sighed
Isabella said no, we don't have actual dates
Ryan said maybe we should be pulling back required dates from fabrication need by dates
Scott did his whole sign off and deliverable schedule rant
We are going to base our Coordination dates form DPRs precon schedule and sign off so that we are signed off with MCDean before DPRs dates
We are supposed to have approved submittals for anchors on 8/21
Document control, Isabella is the point of contact,
Scott explained , need one point of access for Sheets, we are still digging around looking for latest greatest
I obligated to once a week going through clashes, using HRV Forma
Isabella will submitt her stainless steel dog leg expansion for Tom to approve
Isabella will get with Tommy to Verify how many 14" skids they want
1030amEMT - Mortenson BIM Coordination Meeting
Nate Black (Mortenson)
UCO3 Loop OH Coordiantion Sign off 7/24
Nate pointed to coordination models that will b
Scott asked about the container models and who is creating it
nate said if we can push our models to revizto directly, that would be great
Heath said he can do this
Need to notify heath when they
7/22/2026 - Went over Drone Fly through
FCW is being dropped in EMT2
Skyline safety share
Alex Eismore, mental health
7/22/2026 - Just covered based build items
8/12/2026 - Just covered based build items
1130amEMT - Mortenson BIM Component Call
Nate Black (Mortenson)
7/15/2026 - Cancelled
7/22/2026 - Meeting is still listed in Calendar, mainly Southland BIM team in invite
8/12/2026 - Missed
08/13/26 - THU (+11 Meetings)
600amTXE10 Facility Water Tolerance Issue
Jake Williams (Hensel Phelps)
Waited for Brock from Cerris, once he showed, he said their scans didn't show them as far off as we are showing in pics
Paul says they pulled from Columns
The ML1 is about 3-3/4" off, ML2 is about 2.5" Off
Zach maded the comment that walls would need to move, if we were to move our anchor, things would need resubmitted for approvals
Brock said as of now the only way these pipes move is by jackhammering
Dan Laub says no one responded back with an accepted Tolerance, they were trying to say 3-5" and he admits that was't acceptable, but 1/8" isnt attainable
Zach responded saying 1/4" and the tolerance was submitted in the CCIA, which Dan didn't know what that was
Zach continued with 1/4" tolerance
Alex Harpel brought up Adams email from 3/11, which was addressed to Dan as the last in the chain and Adam said 1/2" tolerance
Dan said he never got the email, Alex showed a screen shot showing his name in the TO Field
Keylan explained we have scan going back out next week to capture the CPs, we will have scans ready end of next week for meeting on 8/3, everyone agreed
Jake asked Brock to come up with solutions in the meantime
8/3/2026 - Paul says lets try to hit them, I said Wednesday after noon, said meeting Thursday at 6am PST will be good
Keep track of time
8/6/2026 - I said yeah we aligned, you can look in the federated model or any coordinated models, the new alignment has been published and new NWCS have been exported.
I brought up Alex Harpel saying control points may be an issue.
Anna Cummins(?) said we can setup our own control points. I said no, we need to have verified control points from the General Contractor that everyone is using on this. We are trying to align things down to less than 1/2", we need to make sure the control points are good. Setting up our own Control points can introduce issues we dont want.
I said we will get with field and fab to vet constructability and look at updating fab, verifying things will work with the anchors and if there are issues there, get engineering involved.
We will keep all updated on progress.
8/13/2026 - I was late to work, asked Adam if this meeting happened
He didn’t have it, so I don’t think it happened
630amEMT - Daily BIM Alignment
Abe Hernandez
Scott gave an overall for the MES/HAC foot clash
Melanie Working through EMT Models, links needed repathed
Go Through EMT1 and EMT2 and make sure MES, TW and MP content are good
IF good, push to Revizto
Also check MSA/FSHAC Piping
EMT Does have IFC's for Base Build, Scott showed them yesteday, I coulda swore we didn't have any sheets, prob thinking of HRV
7/16/2026 - Melanie says our MP model doesn’t line up with Eng Model, we are using Lightning Shared Coordinates, Eng is using ETM100
Abe - Attached Sign off schedule to summary email, have content populated and coordinated ahead of signoff dates highlighted in RED, these dates line up with Mortenson
I told her our content, mes content lines up in revizto, if you change anything, it will no longer line up
Download arch model, link our models in and see who lines up
She says archs did change the g datum model a while back, she had to repath it and that’s when things stopped lining up correctly
7/17/2026 - Cancelled
7/20/2026 - Cancelled
7/22/2026 - Ryan says Mortenson is on the verge of issue stop work order with Meta due to electrical incompetetance
7/23/2026 - Cancelled
7/30/2026 - Cancelled
8/6/2026 - Adam said he will cover EMT, I will do the LEB Meeting
8/13/2026 - Cancelled
630-710amLEB | BIM | Faith x Turner
Luke Jost - Joe Dorinsville
Edwin Perez from Turner hosted
5/14/26 - - Joe Brought up the access panels for Flush system, asked about rating, I would have to check submittals to verify. Me and Lance holmes informed joe the flush systems are temporary, once done, they get removed and the access panel stay
Anna said they were aware, but not the finalized locations, now they will be going through Valley for engineering, excel engineering to make sure everything is accounted for, engineered
Talked to Stefan, we are not providing the Access Panel, its GC2 wall, they are providing it
I need to check on RO system, ACCess panel and it looks like location may be borked
Scott asked about sign offs for lighting scope to base build duct connections, Joe said they havent covered it, sign off is around end of June. They will be circling back to loop area not that they have certain paperwork available
Joe said any issue can be brought up at anytime
5/21/265 - No John Rhee, Brent, Thomas Holler, NO PM TEAM
They went over stud wall model, Lance asking about raceways for security and bus ducts
5/28/2026 - They went over electrical stuff, skid placement, wall leave outs
Turner wants a meeting with Helm and Southland to go over Wall penetrations
Joe D discussed Span model naming, keeping them the same and consistant.
Will need to relink LEB Span models since they have new models with Nucor suffix
6/4/2026 - Eduardo Ibanez brought up Status of Facility Water Stubups asking if Verification of Stubups with Mortenson needed. Had Crider submitted? Lance was saying Ryan would have this info and asking if Ryan was in meeting
NO PM Team present
I sent PM Team a summary email
I explained, Ryan used HDR model for coordination, I worked with HDR to get everything line up, we provided dimensions, everyone agreed to them, now stub ups are off, Lance Resposnded to John Rhees email asking what is being done
I said we need to start having meeting to go over this issue since its so critical
Luke Jost told eduardo to add an action item for this and lance said he will head this off
6/11/2026 - I brought up the FW UG being off again, told the group Ben Kozel with crider said they were backfilling in layers and trying to get the stub ups on the POC/CIA points
Overhead Signoff is schedule for 6/30
Scott asked if it was entire building for NWB, Joe says yes
Joe Brought up IMP walls changing to Framed walls, Anna? Said it was still being worked on
Verify LEB10 POC For DCW
Verify DCW POCs line up with CIA
Lance said they are also providing a hose connection for discharge, I stated they are using the FLOOR Drains in center of gallery for discharge, Adam corrected me saying John has requested different discharge points. Wouldn've been nice to know.
Someone asked about the Flex piping from the 8" skid hitting the column, I told them it was flex pipe and temporary, that it will bend around the column
Vent in 6-19x6-D, adam told them to put in between MES Skid
Waldinger is doing the bypass on LEB6
Building 6 MES loops are showing misalignment with Waldinger Bypass
NO PM Team present
I said I would like it added to this meetings notes, Joe Dorinsville basically shut it down, saying it was a field issue
I said it was our issue also since we are constantly being asked to do overlays, which were happy to help any way we can, but this was more of a helm situation since they are the responsible party to connect to the UG and provide us with accurate points of contact according to the CIA
Joe reiterated it was a field issue
6/18/2026 - Edwin Perez is showing Verification on stub ups w mortneson needed. Pending Submittal. Eng. Drawings to be submitted - Crider and Crider. He said this is still on going
Edwins model view still shows MP Shifted to plan right, access panels were to the right of the wall they are supposed to be in
LEB6 Arch Coordination model is showing everyhting off, MES Skid not lining up, mp is to the right, access panels are to the right of the walls they are supposed to be in.
LEB10, checked with Joe D, things line up there.
6/25/2026 - Joe, Greg, Luke Long, Greg went over Electrical coordination
I sent email to PM Team, no one was present
Eduardo Ibanez brought up Status of Facility Water Stubups asking if Verification of Stubups with Mortenson needed. Had Crider submitted? He brought this up again. I explained again that we provided dimensions for LEB10 and LEB1 to Mortensen, Crider and HDR, they all agreed
I told group that I also emailed these dimensions to Waldinger for Region 2, but havent received any comments or response from anyone.
Scott asked about tracking for signoff on 6/30, eduardo said yes
Luke Jost asked about LEB10 Embeds to make sure they are getting tracked by turner
Edwin Perez asked about Waldinger Bypass and alignment to SI MES Loop Connection
I told Edwin Perez I provided poc dimensions and elevations, but havent received any response
Edwin said he will bring up in next BIM meeting
7/2/2026 - Get with john as far as who is providing what cam lock adapt for fip drops
Lance Holman also provided additional dishcharges (Drains) for Flush/ fill per john
They showed model, HDR DWC Drops are on face of column, I told group IFC shows they are on Web side, HDR Model doesn’t match HDR IFCs
John Rhee is communicating changes from model to FTI, Turner that they are not telling us, Discharge drains, DCW changes
The only reason I found out was because of the meeting flythrough, our pocs were on other side of corridor
John fucking totally ignored our information and didn't relay any information
I missed the HDR IFCs showing the drops on the plan south side of corridor
I explained LEB6 model misalignment was fixed, publishing issue, I will double check mondays model after the Saturday auto publish
I told group about the FW UG Dimension sheet that has been distributed multiple times and it details where the FW UG stubs are supposed to be ever since LEB1
I will double check LEB2 misalignment
They showed LEB6 and the 8" skids were into the columns again
I explained the deep dive I did last week, it shows everything aligned. There are issues with the FTI Container model that Turner is using for coordination
7/9/2026 - Setup LEB2 SI MP View off turner LEB2 Overall Building NWD, Crider is still off at Grid 2-50/ 2-D
Eduardo Ibanez hosted
LEB10
All Content on slab will be created in a file, progress is ongoing. Jay Asked what does this entail? Above Slab content?
LEB6
Our MP is still out of alignment in Turner LEB6 Overall Building.nwd, but Joe pulled in a recent nwd and it showed the FTI Container inside the Overall nwd is off
With joes pulled in NWD that shows us and waldinger aligned, Crider was still off around 8-10"
SI Duct and Waldinger do not align
Justin verified that Turner is using NWC files NOT the revit
Southland MP looks good
Southland MP model is still a little older, but non-critical
7/16/2026 - Joe D brought up some issue about control joints at LEB10, luke jost and jay kaiser will update as necessary
7/22/2026 - Joe D brought up control joint proximity to MP anchors, they scooted 1 at grid 29ish, no TW Skid.
Checking Coord Space at LEB I see Stratus models getting exported again on 7/17, that was last Friday
The only MP model available is from april, what the fuck is going on with this fucking shit
The LBE10 Publish settings were set to stratus, talked to heath, he showed adam was the last one to do it. Adam said he didn’t know had to change settings back
Lance suggested a meeting with FTI and Southland to get power to TW Skids, Lance Long said they have a meeting setup with FTI Tomorrow, looking at junction box on the wall
Jay K at FTI created an issue with Crider Facility Water Alignment and was trying to add crider watchers, he can only add FTI watchers.
Joe D told him to use Triston with Helm, Mitch with Waldinger
Mitch with Waldinger said it looks like its going to work out with aligning their Bypasses with Southland MP
Jay K brought up container models having outdated southland models
Joe D says its tough to say when the FTI container was reloaded. The last update they show was july 13th, 10 days ago
I rbought up the TW Skids on each end of the building also to check, they have anchors also
I stated I found a recommendaiton of 3" distance between an anchor and a sawcut or concrete joint
7/30/2026 - Jay brought up getting control points from Turner
Jay brought up missing MES/ TW skids from LEB1, LEB2 FTI Container, the MP content was aligned
8/6/2026 - I affirmed with Jay, I have not seen any blue beam sessions
I verified LEB 6 in Navis, using the View I created with all trades
James (Turner) is setting up meeting next week to go over CIA points with FTI and Baker
Jay asked about established control points, joe said bring it up in the session
8/13/2026 - Helm modeled their bypasses to the current asbuilt points received Last Friday, This Monday
I told Joe we would wait for the actual asbuilt 3d scans before we do any further model aligning. It’s a waste of time right now, to turn around and have to do it again after scans are received.
830amMCD + SOUTHLAND + TATE/FSHAC Coordination Check IN
Updates to MSA piping completed and pushed to ACC, cantilever supports, support changes
RFI 146, MOFE OFE
MES PIPING ALIGNMENT WITH MSA Alignment is different
04 MES skid, make sure MSA is aligning with MES 04 skid based on this RFI
MAKE sure MSA SKUS are updated
Make sure MES Skid 04 includes this RFI
Give Arthur and team updated info so they can verify steel is appropriate
Darrin says HRV1 and HRV2 Clashing models are complete
Running clashing through Navis, our VDC Team should be able to get access
I asked about Southland being able to view their clashes
Darrin said they were having disccussions about moving their clashing to ACC Model Coordination
I said we would touch base and peyton is spearing heading our clashing coordination to see what direction we will go
Scott Brought up HAC Alignment and things not centered
Arthur said they will check it out
We need to make sure the SOUTHLAND MES Model is bridged to MCDEAN so they can use that model
Follow up with Melanie, heath
I sent out a clarifying email that since the mes models are host on MCDean, they don’t need bridge. I told them the models we are using for coordination
7/29/2026 - Isabella said she talked to Tom Chirdon and Tom Maxwell, couldn’t determine where RFI 146 was, white its not in programmatic forma
Arthur wants to do same time tomorrow with USCE and Tom Chirdon so we can all get on the same page
It will be Wade from USCE
Isabella asked about clashing and updating steel model
Update tomorrow
Need hac model completed before we can finalize placement of Fan Coils
Peyton is talking to Darrin about seperating the models for clash coordination
What DCIS is it? 4374, is what this write up refers to
Arthur said he will get with meta and make sure it gets escalated to Meta so it gets handled on a programmatic level
7/30/2026 - FCM Placement update, early next week for that
Updating 2nd family content
Darren and Doowoo, may have an federated model "Soon" according to Isabella
Arthur role is FSHAC designer, They brought on SJS to manage Coordination, Darren is project engineer, hes the one for Model coordination
Adam will be putting together snips that shows where we are at compared to rfi 146.
Isabella says the rfi was answered for UGS and they are looking at moving pipes to realign
Had to leave early to talk to carsen scanning at txe
8/13/2026 - HRV TATE FSHAC Meeting
Export the MES to NWC for HRV DCB100
Tweak Header clmaps to line up with HAC Supports
Make things good for Monday meeting
Take a look at MCDean moving MES skids 1-2" into corridor
Create a step file of side isle piping for network suite
830amMCD + SOUTHLAND + TATE/FSHAC Coordination Check IN
Updates to MSA piping completed and pushed to ACC, cantilever supports, support changes
RFI 146, MOFE OFE
MES PIPING ALIGNMENT WITH MSA Alignment is different
04 MES skid, make sure MSA is aligning with MES 04 skid based on this RFI
MAKE sure MSA SKUS are updated
Make sure MES Skid 04 includes this RFI
Give Arthur and team updated info so they can verify steel is appropriate
Darrin says HRV1 and HRV2 Clashing models are complete
Running clashing through Navis, our VDC Team should be able to get access
I asked about Southland being able to view their clashes
Darrin said they were having disccussions about moving their clashing to ACC Model Coordination
I said we would touch base and peyton is spearing heading our clashing coordination to see what direction we will go
Scott Brought up HAC Alignment and things not centered
Arthur said they will check it out
We need to make sure the SOUTHLAND MES Model is bridged to MCDEAN so they can use that model
Follow up with Melanie, heath
I sent out a clarifying email that since the mes models are host on MCDean, they don’t need bridge. I told them the models we are using for coordination
7/29/2026 - Isabella said she talked to Tom Chirdon and Tom Maxwell, couldn’t determine where RFI 146 was, white its not in programmatic forma
Arthur wants to do same time tomorrow with USCE and Tom Chirdon so we can all get on the same page
It will be Wade from USCE
Isabella asked about clashing and updating steel model
Update tomorrow
Need hac model completed before we can finalize placement of Fan Coils
Peyton is talking to Darrin about seperating the models for clash coordination
What DCIS is it? 4374, is what this write up refers to
Arthur said he will get with meta and make sure it gets escalated to Meta so it gets handled on a programmatic level
8/12/2026 - Arthur stated the MES will not be moving, the MSA Frame will be adjusted to clear the clash between msa hac and mes anchor
He asked about the 8" TW Flex skid squeezing through column and mes, clashing, I let him know that was a temporary flush skid with flex pipe, we will get It through
Isabella stated that peyton will be putting together all information, and run through a list of clashing
Peyton showed the SI Duct clash with SI Mech pipe
Ryan got pissed that Darren wasn't available, saying this is such a broken proecess, arthur says hes out of his depth, Darren is double booked, Ryan said he needs to be there
Clash is showing flush access panels hitting bus duct on outside of wall
Isabella says since MCDean contracted with SJS to do clash and coordinating, they need to be present and hosting these meetings
Arthur asked Doowoo to assist in getting Darren participation and SJS participation
Ryan asked what kind of end was on the 8" flush skid, Arthur reminded it was hitting a timber column. I said it was a grooved end, we will get it through, even if we have to use a come a long, lol
900amTXE-FTI Weekly Sync Meeting
Luke Justice
Luke was asking about scanning at TXE10, He said coordinate with Greg Hueramo, he will be setting up an origination email
I told luke they need to have all areas ready for scanning since the team cant be sent out every other day, reset up, etc
I asked for Control point map, he said get with Greg Hueramo
I explained to him what the scanning was
I told him they will need to add paul hernandex, jeremy miller and adam brown to email
John Cowhey said he has a 1 pager for Site orientation which will be 8 hours
They will be enforcing badging within the next few weeks. No badge no access, Visitor badges will be available but not allowed to work
Luke will put together a schedule for orientation
11/17/26 - is new date for 0 prep according to John Cowhey
Forward FW off email to Luke, original email was sent out 4/17. I resent to Luke Justice
I told him Jeff Balthrop was involved a few weeks back
Send Luke Discrepancy on Anchor locations with BZI Wall panels, NWCs etc from Adam email, Adam email 5/5, TXE Adam email 5/6
Verify anchors at TXE and LEB, check they've been submitted to FTI
Send notice to John Cowhey, luke justice
They asked when Southland is looking at manning the site, jeremy informed them no PM team were available at this time to answer
new schedule coming out Friday
Got with michael kolnik, he sent out Shop Drawing submittal request to Eric Boehger
5/28/2026 - Loop Keylan and Michael into the Anchor clash info and meeting for Friday
Luke says bypass are fabbed, not installed will be installed next week, sent out email to everyone, paul, jeremy, michael
Need to coordinate orientation, drug testing
Day zero schedule? Luke said he was supposed to get last Friday, not seeing anything new
Luke showed the Faith TXE Anchor Shop Drawing submittals, they are only for the TXE10,1,2 Plates don’t know why it has TXE3 on the label
Not showing any Shop drawing embed submittal info
NO PM Management was present, Keylan Rollins was for engineering
6/4/2026 - Luke Cancelled at 741am, Got DAMN MAN!!!!
6/11/2026 - Luke Cancelled at 741am, Got DAMN MAN!!!!
6/18/2026 - Luke asked about Issues, I was explaining a summary of Greg Heuromos meeting, then Michael Kolnik was there! It was nice
6/25/2026 - Michael says greg told him the bypass will be complete on 6/7, michael has scanning scheduled for 6/6
Jason with FTI will use truck to help scanning move around job
Scanners will need badges, they can be escorted according to michael who talked to security
Michael says no one onsite yet, they are on first of kind, michael and jacob did get badged
FTI does have a superintendant and a couple of upper management onsite
Fully mobilized first week of July
Luis says they have been requesting a lot of BIM information, Asbuilts, trench information, etc
Luke says a laser just got done for the Trench
Alec Harpel says first half of txe10 was scanned, still waiting for coordinates
Need FW stub ups, grounding whips and trenches
Luis is asking for points for the finish floor to verify elevation/flatness
TXE1 slab just started pouring last week, according to Luke
Micahel said they wont have water into the building, they need to truck it in and provide the minimum GPM with 3" connection
TXE10 shows 3" main with 3" drops
TXE1 shows 4" main with 3" drops
7/2/2026 - Luke Justice cancelled
7/9/2026 - Luke Justice cancelled
7/16/2026 - Keylan gave run down of Scanning and photos, scanning completed
Jacob stated carsen is locating revit files and uploading info
Should get scans by afternoon
7/23/2026 - Luke asked about Control points, I told him we did get the PDF from Shay with coordinates and CP labels
I can use this to get the CPs into the model
I informed them that Justin Jenkins was looking for Dimensional data from CP to a known point. I said I would follow up with Justin
Sent email to Justin Jenkins with CP map and letting him know they didn’t understand the dimensional data from CP to Known point
7/30/2026 - Russell Faulkner, wall of destinys will be completed tomorrow
I told luke about missing elevations on CPs in building on the map, also identifiers were getting wiped out, couldn't tell which CP was which
Told Luke thye finished scanning yesterday, should be able to put everything together for the meeting with Jake Williams on Monday
8/6/2026 - Louis Saldana says meta is putting a third party survey onsite to verify control points
Keylan brought up getting the stub ups in the correct position in future buildings
Told luke walls are in the wrong spot, we cant set our anchors if walls are wrong
Luke says hes used to scanning before slab and after slab
He will find out
He said they were having issues verifying control points and aligning conduit at wall of
He says TXE2 is poured
Hes says TXE1 is not poured
Keylan said we would like to get this sutaiton taken care of before slabs get poured
8/13/2026 - Cancelled
930amLEB | BIM COORDINATION LEB2
Emma will no longer be on this project
Kaushal Bagdekar with Turner ran the meeting, saying who to contact for what, I asked if he could send an email with that info
They went over underground clashes
5/28/2026 - Tristen with helm verified he is using LEB1 dimensions for LEB 2 elevations and locaitons for FW
6/11/2026 - No PM Team
Went Over UG issues, concrete pads
6/18/2026 - Kaushal Bagdekar
Did a flythrough for LEB2 going over exterior sectionalizers
LEB-2_SPAN_SS.rvt, verifying during meeting that the model is good, Checked LEB2 SPAN_SS model, couldn’t load content, says cant link in NuCOR
NO Interior Walls and framing, Valley, Diogo or Ruth said they will get with valley
No Interior Meta Wall Panels
6/25/2026 - NO PM TEAM
They went over UG issues for LEB2
7/2/2026 - LEB2, Showed model where Helm, SI and Crider not aligned, #2070
LEB2 Building Overall actually has Crider model, showing misaligned
Grid 1-50, 1-D is the only spot where Crider is off looking at Turners LEB2_Building_Overall model only
Everything else is aligned, MP, Duct, Steel, Walls, no issues
Sent email showing misaligned concrete and crider stub ups at 2-50
LEB-SI-MP-LEB2-R25 model lined up identical to LEB2-Building-Overall
Didn't see new DCW POC valves, did I update LEB2
Did see FLUSH VENTS AND DRAINS, VENT ON 2-50 IS OFF
7/9/2026 - Sent Email to Joe, Jay, Edwin, Eduardo and Joe forwarded to Kaushal
Kaushal asked about flush skids in front of door ways, need to send them a time frame for flushing before equipment gets removed
Concrete elevations different at Gird 2-29 and 2-32
Crider stub ups off at 2-50/2-D
Added to chat
7/16/2026 - Sent email to Triston with Jay and Kaushal cc'd about Helm bypass flanges not aligning to SI MP Flanges throughout building
LEB2 looked like it aligned good
7/22/2026 - No southland issues covered
7/30/2026 - Just went over non-southland issues
I dropped for LEB Mortenson meeting at 1000am
8/13/2026 - NO PM/ FIELD TEAM
Ouch, Kaushal called out Triston for not being in the meeting 3 weeks now
Had Kaushal remove the waiting on southland to add content we are waiting for, under MP Pipe - Triston, he labeled it closed
Dropped out at 10am for Mcdean Hac Meeting
1000 amLEB - BIM Coordination Meeting (Thu) | Meeting-Join | Microsoft Teams
Ryan Zoldan - Richard Lopez
LEB 6 due finalized next week
I requested a schedule from Ryan, he has the sign off, region schedule, I brought up a pull plan, be he says that will be through Turner
Mortensen is the Base build GC, why aren't they leading a pull plan schedule
John Rhee nor Brent were in this meeting
6/4/2026 - I brought up the LEB10 FW UG Stub ups totally missing the Dims, Ben Kozel was there and he stated they are bringing them back in to dimensions by backfilling a little and moving them, backfilling and moving them
He acknowledge that lance did contact him
6/11/2026 - Ben Kozel, said there were no issues that need to be talked about.
Richard lopez asked around the room for any issues regarding LEB10 or any others
NO PM Team
6/18/2026 - Richard Lopez Hosted, just asked for any issues with LEB10,1,2,3 Underground issues
Rantwiler asked when IWM for TXE10 was going to be signed off, Ethan says he will talke to kyle since they are not really split out
6/25/2026 - Going over LEB7,8
Ryan brought up LEB6, HDR model is not lining up with the Dimensions provided by SI
Ryan henderson said he will follow up
Ryan said we have all agreed to follow these dimesions, I added that I have distrubuted that dimesion sheet ot Waldinger and explained everything, but havent received a response yet
Ryan brought up LEB6, HDR model is not lining up and my email I sent out
I updated, still waiting for HDR to align the stubups
Ryan said Crider is using civil 3d, but we can work it out to actually use their model for coordination and linking in so I don't have to use HDR
7/9/2026 - No issues to cover, they went over UG clashing for elect, sanitary
7/23/2026 - Richard asked Triston about any alingment issues, he was good
Ben said LEB6 stil had some very minor HDR alignment issues to on udergoung
7/30/2026 - Bend said LEB6 looked good
I said we republished LEB6, there was some extra content we had to remove
8/6/2026 - I brought up the LEB10 FW UG Stub ups totally missing the Dims, Matt Schaff said they are doing repairs this week and lookingat getting into within an inch
I mentioned, for helms benefit of using Eccentric reducers on bypass in order to rotate the stubup to align with MES better
I also mentioned after slab is poured, bypasses installed, we look at doing 3d scans
TXE1 looks good for the loop area sign off next week
Same with TXE2
6/4/2026 - Own B ran the meeting going over TXE1 and 2
6/11/2026 - Owen B, says TXE10 Loop for sign off
TXE2 Core scheduled for next week
TXE10 AB Datahall and Loop are signed off
TXE3 Alan lopez is running region 2 for signe off
TXE2 Loop and AB South sign off
issue 2602 - Cerris Vent in corner is clashing with Technical water, Rantwiler is saying they don’t have our model, I told them our model has been there for 6 months, the fact that HP is viewing it, means the model is available. If it’s a bridging issue we will help Cerris work it out
Trevor said he will get with rantwiler and get the model bridged, they will offset that vent around our TW Piping
They made comments about the TW skid being so close to the FW valves. Its been this way for over 6 months. Trevor also stated the vent will need an accessible cleanout
6/25/2026 - They just went over IWM and specific Electrical clashes
7/9/2026 - TXE 2 all docs are out, all sign offs are out
TXE1, 2 sign offs left
DHCD 2 weeks from now
7/22/2026 - No Issues
1130amLightning HRV - Global BIM Coordination Meeting
Isabella Vesce Rivera (SI)
Is there a coordination model we get access to? Revizto? Navis?
Get input on HDR Mockup I made for FW UG Stubup, Bypass and MES Loop connections
Colonial was trying to align to SI Desing model, that was all that was available for the bridging
Seth Blizzard says they arent obligated to meet our POC's, they follow the ARUP design. ARUP did let them know they are contracted to meet our POC's
Curtis Robbins said he just needs to click a button to enable the bridging to our actual Coordination Models
Seth started making comments about use being able to shift our pipes 3", I told them theres a lot more going on that what they were showing with our Engineered anchors, flush connections, MES and TWMU skids and TW Piping, there isnt much forgiveness
Still don’t have access to bridged Colonial files
230pmTXE-FTI Weekly Sync Meeting
Luke Justice
Luke was asking about scanning at TXE10, He said coordinate with Greg Hueramo, he will be setting up an origination email
I told luke they need to have all areas ready for scanning since the team cant be sent out every other day, reset up, etc
I asked for Control point map, he said get with Greg Hueramo
I explained to him what the scanning was
I told him they will need to add paul hernandex, jeremy miller and adam brown to email
John Cowhey said he has a 1 pager for Site orientation which will be 8 hours
They will be enforcing badging within the next few weeks. No badge no access, Visitor badges will be available but not allowed to work
Luke will put together a schedule for orientation
11/17/26 - is new date for 0 prep according to John Cowhey
Forward FW off email to Luke, original email was sent out 4/17. I resent to Luke Justice
I told him Jeff Balthrop was involved a few weeks back
Send Luke Discrepancy on Anchor locations with BZI Wall panels, NWCs etc from Adam email, Adam email 5/5, TXE Adam email 5/6
Verify anchors at TXE and LEB, check they've been submitted to FTI
Send notice to John Cowhey, luke justice
They asked when Southland is looking at manning the site, jeremy informed them no PM team were available at this time to answer
new schedule coming out Friday
Got with michael kolnik, he sent out Shop Drawing submittal request to Eric Boehger
5/28/2026 - Loop Keylan and Michael into the Anchor clash info and meeting for Friday
Luke says bypass are fabbed, not installed will be installed next week, sent out email to everyone, paul, jeremy, michael
Need to coordinate orientation, drug testing
Day zero schedule? Luke said he was supposed to get last Friday, not seeing anything new
Luke showed the Faith TXE Anchor Shop Drawing submittals, they are only for the TXE10,1,2 Plates don’t know why it has TXE3 on the label
Not showing any Shop drawing embed submittal info
NO PM Management was present, Keylan Rollins was for engineering
6/4/2026 - Luke Cancelled at 741am, Got DAMN MAN!!!!
6/11/2026 - Luke Cancelled at 741am, Got DAMN MAN!!!!
6/18/2026 - Luke asked about Issues, I was explaining a summary of Greg Heuromos meeting, then Michael Kolnik was there! It was nice
6/25/2026 - Michael says greg told him the bypass will be complete on 6/7, michael has scanning scheduled for 6/6
Jason with FTI will use truck to help scanning move around job
Scanners will need badges, they can be escorted according to michael who talked to security
Michael says no one onsite yet, they are on first of kind, michael and jacob did get badged
FTI does have a superintendant and a couple of upper management onsite
Fully mobilized first week of July
Luis says they have been requesting a lot of BIM information, Asbuilts, trench information, etc
Luke says a laser just got done for the Trench
Alec Harpel says first half of txe10 was scanned, still waiting for coordinates
Need FW stub ups, grounding whips and trenches
Luis is asking for points for the finish floor to verify elevation/flatness
TXE1 slab just started pouring last week, according to Luke
Micahel said they wont have water into the building, they need to truck it in and provide the minimum GPM with 3" connection
TXE10 shows 3" main with 3" drops
TXE1 shows 4" main with 3" drops
7/2/2026 - Luke Justice cancelled
7/9/2026 - Luke Justice cancelled
7/16/2026 - Keylan gave run down of Scanning and photos, scanning completed
Jacob stated carsen is locating revit files and uploading info
Should get scans by afternoon
7/23/2026 - Luke asked about Control points, I told him we did get the PDF from Shay with coordinates and CP labels
I can use this to get the CPs into the model
I informed them that Justin Jenkins was looking for Dimensional data from CP to a known point. I said I would follow up with Justin
Sent email to Justin Jenkins with CP map and letting him know they didn’t understand the dimensional data from CP to Known point
7/30/2026 - Russell Faulkner, wall of destinys will be completed tomorrow
I told luke about missing elevations on CPs in building on the map, also identifiers were getting wiped out, couldn't tell which CP was which
Told Luke thye finished scanning yesterday, should be able to put everything together for the meeting with Jake Williams on Monday
8/13/2026 - Cancelled
08/14/26 - FRI (+3 Meetings)
730amLEB - Weekly Detailing/ BIM Team Catch Up
Reece Fauble
Verify 107V and 07 Couplings on Pup pieces, region 1
Adam said we are still working through comments, still waiting on cantilever approval.
LEB10,1,2 will be good to push out to submit to tom
Need to update regions to datahall A,B,C,D
Day zero is 2/25/27
Need spools before 1/5/27, Adam said we wiill shoot for 6-8 weeks before then to allow for review, updates, etc
Scott says EORs get officially submitted to Tom, he approves, they get submitted to FTI. Not sure if EORs get submitted to Meta or not as part of record drawings
Scott says by Friday the 14th they will publish to stratus
Embed Layout Drawings
We gave drawings, we will have
Crider and Mortenson will provide scans once they are finished, so that helm can update their bypass.
Flush Skid BOM, Curtis used TXE Counts and ordered the material
Hose Carts are still being finalized
Get Reece copies of TXE Flush skid BOM information
Hose Carts will be finalized once FOK and SOK are done
No pour until november
Schedule model? Can we incorporate this?
LEB10 UG Stubup status
Crider, Mike Schaff said they were doing repairs this week
Make sure LEB PM Team knows we need to scan after slab, after bypasses installed, then we align, update spools
8/14/2026 - Cancelled
830amMCD + SOUTHLAND + TATE/FSHAC Coordination Check IN
Updates to MSA piping completed and pushed to ACC, cantilever supports, support changes
RFI 146, MOFE OFE
MES PIPING ALIGNMENT WITH MSA Alignment is different
04 MES skid, make sure MSA is aligning with MES 04 skid based on this RFI
MAKE sure MSA SKUS are updated
Make sure MES Skid 04 includes this RFI
Give Arthur and team updated info so they can verify steel is appropriate
Darrin says HRV1 and HRV2 Clashing models are complete
Running clashing through Navis, our VDC Team should be able to get access
I asked about Southland being able to view their clashes
Darrin said they were having disccussions about moving their clashing to ACC Model Coordination
I said we would touch base and peyton is spearing heading our clashing coordination to see what direction we will go
Scott Brought up HAC Alignment and things not centered
Arthur said they will check it out
We need to make sure the SOUTHLAND MES Model is bridged to MCDEAN so they can use that model
Follow up with Melanie, heath
I sent out a clarifying email that since the mes models are host on MCDean, they don’t need bridge. I told them the models we are using for coordination
7/29/2026 - Isabella said she talked to Tom Chirdon and Tom Maxwell, couldn’t determine where RFI 146 was, white its not in programmatic forma
Arthur wants to do same time tomorrow with USCE and Tom Chirdon so we can all get on the same page
It will be Wade from USCE
Isabella asked about clashing and updating steel model
Update tomorrow
Need hac model completed before we can finalize placement of Fan Coils
Peyton is talking to Darrin about seperating the models for clash coordination
What DCIS is it? 4374, is what this write up refers to
Arthur said he will get with meta and make sure it gets escalated to Meta so it gets handled on a programmatic level
7/30/2026 - FCM Placement update, early next week for that
Updating 2nd family content
Darren and Doowoo, may have an federated model "Soon" according to Isabella
Arthur role is FSHAC designer, They brought on SJS to manage Coordination, Darren is project engineer, hes the one for Model coordination
Adam will be putting together snips that shows where we are at compared to rfi 146.
Isabella says the rfi was answered for UGS and they are looking at moving pipes to realign
Had to leave early to talk to carsen scanning at txe
8/7/2026 - Cancelled
8/14/2026 - Cancelled, shows we had a meeting on 8/13/26
1100amMNT West Piping Detailing Meeting
Adam Brown
Went over MW Piping Presentation Guide Power Point
Will go over ACC Publish and Review next week
7/31/2026 - Cancelled
8/7/2026 - Missed due to LEB Meeting
8/14/2026 - Went over MW Piping Presentation Guide Power Point and Publishing sheets, Adam presented
8/3/26 - 8/9/26
08/03/26 - MON (+8 Meetings)
700amEMT Coordination
Abe Hernandez
Brought up CIA agreeement
This week EMT1 UG Signoff this week
Peyton showing MES MP Pipeing into duct and framing, mic didn't work so I couldn’t talk to verify MES Elevations
8/3/2026 - Abe said UCO3 UG Signoff is pushed to next week
Peyton going over clashes
#816 shows vesda FP content going through our bypass at hac, adam modeled the vesda
MH Duct at EMT1 was low, scott said he will take a look
800amTXE10 Facility Water Tolerance Issue
Jake Williams (Hensel Phelps)
Waited for Brock from Cerris, once he showed, he said their scans didn't show them as far off as we are showing in pics
Paul says they pulled from Columns
The ML1 is about 3-3/4" off, ML2 is about 2.5" Off
Zach maded the comment that walls would need to move, if we were to move our anchor, things would need resubmitted for approvals
Brock said as of now the only way these pipes move is by jackhammering
Dan Laub says no one responded back with an accepted Tolerance, they were trying to say 3-5" and he admits that was't acceptable, but 1/8" isnt attainable
Zach responded saying 1/4" and the tolerance was submitted in the CCIA, which Dan didn't know what that was
Zach continued with 1/4" tolerance
Alex Harpel brought up Adams email from 3/11, which was addressed to Dan as the last in the chain and Adam said 1/2" tolerance
Dan said he never got the email, Alex showed a screen shot showing his name in the TO Field
Keylan explained we have scan going back out next week to capture the CPs, we will have scans ready end of next week for meeting on 8/3, everyone agreed
Jake asked Brock to come up with solutions in the meantime
8/3/2026 - Paul says lets try to hit them, I said Wednesday after noon, said meeting Thursday at 6am PST will be good
Keep track of time
830amMCD + Southland + Tate / FSHAC Coordination
Arthur Foley (MC Dean)
First of a series of daily check in calls between Mcdean, Tate and Southland to make sure we get steel updates from Tate and clash detection
Matt Mcconnell is the PM from Tate
Should see new update tomorrow morning
Guin Yaprak verified this is the case, 10-11am tomorrow
HRV FOK will be in the NWS
MSA will be included
This will be a recurring meeting everyday
8/3/2026 - Isabella told darren about Seths response to my request for consistent elevations, which was no, she said this is unacceptable. Darren said they went to Meta about this whole situation
I informed Darren the current model they were viewing was outdated, the current model from last week shows updated alignment
Isabella said she doesn't understand why Meta got involved, that was unecessary
900amLightning TXE Staff Meeting | Meeting-Join | Microsoft Teams
Jacob Gelhousen
Will do scans after Cerris installs bypasses
6/1/2026 - Noel Nunez says Alehandro Chew will be safety manager
Michael said he sent TXE3 embeds along with PDF dimension in mid April
Doesn’t think TXE3 has been poured, think they are behind schedule
Says we havent been funded for Region 2, he is sending out embeds as needed
Michael asked what the question was about RO and TW, I said it was going over how to connect to the RO skid, from DCW and to TW MES
Michael asked if MES Loops were completed, adam said yes, he created new BOMs
Michael said his goal is to get everything ordered
Michale Paul said they thought the walls weren't going to be in until they could do anchor
They said that was what was agreed to
6/8/2026 - Michael said they had a PM Coins Mandatory meeting and couldn't host the meeting
6/15/2026 - Chris Moss came on board from TSMC, Pipe fitter, GF
Jose Alejandro Chew, new Safety Manager for TXE
6/22/2026 - Shop drawings (Engineer Drawings) looking at submittal on Frid, 6/26
6/29/2026 - Keylan Cancelled
7/6/2026 - Carson will scan on Thursday
7/13/2026 - Scans on TXE10 complete, should have done this week, EOW
Jacob will be pulling field measurements of FW Stub ups
Adam will overlay scans to see how they match up with our Stub Ups
SOK will be starting next week, 27th will have more setup covered
7/16/2026 - Zach wants scanning sent back out, scan off control points, need to get CPs from Greg, put in model, talk to carson to see what they need from us
Control points were requested on 6/12 meeting with Greg H, it was stated they would be sent to Michal and James Homrighausen
I also asked for control points from Luke Justice on 5/21, he said he would get with Greg H.
They made it out like it was detailing fault they scanned without using control points
Paul asked how soon I can get the points into model, I said immediately, but Im not sure scanning needs anything from us, they may input control points into the rcap software maually but we will have it the model if they need it
7/27/2026 - Scanning this week
FTI Will be doing Trimble next week
8/3/2026 - Adam brought up new pipe supportts that were sent to Tom due to more access to mes loop valves
Adam asked about tapped caps for mes connections, michael said it was a miss on them so they will cover it
Trimble is shooting wall points tomorrow and Wednesday
1130amMW Detailing Weekly Meeting
6/29/2026 - Marshall Cancelled
7/13/2026 - Missed, I thought it was cancelled
7/20/2026 - Armondo party on Friday
De Le Cruz tips and tricks, Title Blocks
7/27/2026 - Missed, went to Cameron Shop to meet Mid Atlantic Crew
1200pmEMT BIM Look Ahead Meeting
Nate Black (Mortensen)
UCO3 OH Signoff 7/24
Went over drone map, EMT1 and 2 have UG FW
Went over sign off schedule
Showed Marcos Revizto Clash Workflow
Showed UCO3 Loop OH
7/20/2026 - Went over drone view of jobsite
Joseie with delta went over heat safety
no PM Team
Got UCO3 sign off for OH on 7/24
7/27/2026 - Missed, went to Cameron Shop to meet Mid Atlantic Crew
1230pmAugust All Hands Meeting
300pmEdmond Office Happy Hour
08/04/26 - TUE (+10 Meetings)
600amHRV Schedule Review/ Discussion
Curtis Robbins (DPR)
Went over no permits, permit submittal, job pushed out 81 days
No PM Team in meeting
630amEMT - Lightning BIM Weekly Coordination
Abe Hernandez
Printed IFC Addendum 1
Scott showed Mortenson schedule 7/6
Peyton Coordination Model - Meeting with Heath, model is setup, need to get heath input
Using forma coordination module for clash detection
Cupertino says they are fine using the Forma module
Ryan - wants the model defined as to which one to use and clash with for Cupertino
Scott says he is on it
I let abe know that the MES and MP constructability models are now in the Revizto publish
He told Cupertino they can use that
Scott asked about elec panels hitting columns, I shared a fly by on Revizto and it didn't show any issues on UCO3
I showed the team Temp Power and Skyline clashing with MES Loops
I also emailed Nate Black last Friday
Ryan Warner says there is tees clashing on underground with Cupertino in elec gallery
7/21/2026
7/28/2026 - Cancelled
8/4/2026 - Abe Hernandez
Alex Hubbard
NWS Has above ground changes due to elec bus work
700amEMT Touch Base with Brandon
Adam Brown
Brandon Marse, Field Superintendant for EMT
2-3 Weeks needs UG Scanned for Facility Water, so they can see where they land and build bypasses of those scans and then scan again after bypasses installed
Said he would get us Control Point Information
Need to get Submittal #5 into Lightning Program Forma for EMT, Anchor Spool
Building bypass in Stainless, something about stopping any containmination of the HDPE
Adam showed where anchor layout was, the anchor embed template and is getting with tom to make sure Submittal #5 EMT specific Anchor approved submittal gets in the Lightning Forma
800amWeekly BIM Coordination Meeting - Region 2 (ZOOM)
Alan Lopez, Kyle Cummings (Hensel Phelps) / Ethen Berry
No one started the meeting, I sent an email, they said Alan was PTO and they started meeting late
They went over Region 2 underground, sign off later this week
5/26/26 - Allen Lopez Went over Region 2 again, said they were going to do a main signoff then a branch signoff. Covered a lot of UG clashes
6/2/2026
2 weeks sign off branch
6/9/2026
6/16/2026
Allen Lopez says he doesn't see Sure Steel model in TXE3, Kyle says also no Diversified, but Sure Steel model is there, needs added
Signoff schedule was not bridged, the one on FTI is outdated. Kyle and Justin said they would get the bridge up to date
Files - Data Management
6/23/2026
6/30/2026
7/7/2026
TXE3 Overhead Loop signoff next week
TXE3 Overhead Datahall signoff is July 27th
7/14/2026
7/21/2026
TXE3 Loop OH Signoff on Friday, DHA/B Following week
NO PM or Field Team present
8/4/2006
Didn’t see any hac piping, got with adam, we need to get hac piping copied in
830amLEB - BIM Coordination Meeting (Tue) | Meeting-Join | Microsoft Teams
Ryan Zoldan, Mortenson (GC1)
Missed for the 8am meeting
6/16/2026
6/23/2026
6/30/2026
7/7/2026
Ryan brought up their grids were off, crider and crider will be aligned today and HDR will be aligned. For LEB6
Ben Kozel says all waldinger was missing a flange on their bypass, everything else looked good, crider was good
Ben says HDR looks good for UG and Grids
7/21/2026
Talked about LEB6 HDR not matching Soutland provided dimensions, bullet point #1, supposed to be covered in meeting tomorrow
Talked about Underground stuff
830amMCD + SOUTHLAND + TATE/FSHAC Coordination Check IN
Updates to MSA piping completed and pushed to ACC, cantilever supports, support changes
RFI 146, MOFE OFE
MES PIPING ALIGNMENT WITH MSA Alignment is different
04 MES skid, make sure MSA is aligning with MES 04 skid based on this RFI
MAKE sure MSA SKUS are updated
Make sure MES Skid 04 includes this RFI
Give Arthur and team updated info so they can verify steel is appropriate
Darrin says HRV1 and HRV2 Clashing models are complete
Running clashing through Navis, our VDC Team should be able to get access
I asked about Southland being able to view their clashes
Darrin said they were having disccussions about moving their clashing to ACC Model Coordination
I said we would touch base and peyton is spearing heading our clashing coordination to see what direction we will go
Scott Brought up HAC Alignment and things not centered
Arthur said they will check it out
We need to make sure the SOUTHLAND MES Model is bridged to MCDEAN so they can use that model
Follow up with Melanie, heath
I sent out a clarifying email that since the mes models are host on MCDean, they don’t need bridge. I told them the models we are using for coordination
830amMCD / Southland Model Coordination
Darren B. MCDean
Caught the tail end of the meeting. Isabella says our piping has the required fittings to connect to mes that is referenced in RFI 146 based on Adams info. They are still comparing our low rez model to the hi rez model in the RFI image though
I told adam we need the hi rez model before we verify this, last week
Isabella asked Darren about the model, he said it was available
1000amLightning-Eng-Coord Huddle | Meeting-Join | Microsoft Teams
Tia/ Tom
Follow up on HAC Panel clashes with Patrick Brinnehal
Meeting to go over stratus and models with all PMs, Adam, Scott, Supers sometime next week, look at schedules
Chris Chase is the PM of EMT
5/26/2026 - Check if Adam got the 4" Welded Bypass to Shop, from 5/5/25 email in Inbox "Im shooting to have the LTG build out scope package done by end of week (For Review only not for construction). "
Verify what spools have been put on stratus for TIA/TOM Lightning huddle
Need meeting to discuss, txe10 anchor clashing with interior of walls, adam sent info out about conflicting models, but as of today, there is still clashes
RFI says they are changing wall to Gypsm board and expanding toward corridor 2.5"
6/2/2026 - We did get 2 more sites in Ohio
SI will be integrator
Heath introduced Peyton Steveons as VDC supervisor
Starting with HRV
Melanie introduced Vasi, VDC specialist helping out ron and melanie
Tia went over deliverable schedules
Per site, per building
She setup a break out meeting
Adam said they are moving the walls away from anchors so we are clear
Adam said we are 1/2" clear from plate, it will be a field issue installing the plate
Michael said he will talk to paul, he doesn't know what to do, he will call greg
only 2 walls changed from IMP, 2 others are still IMP
Michael said Greg told him they are putting walls up next week
Told Tia I sent snip of Dog Leg Metraflex in chat, didn’t get any smiles
Let her know we have LEB complete, TXE10,1,2 is complete
Adam said he will give link to CIAs, TXE3-12 and LEB3-12 not ready
Adam had meeting with HRV, told them to start using our coordination models for coordination
Quick hello, this is who we are meeting
with MC Dean
Mealnie says they will be updating projects to new architect model
Type F - 4 buildings
Type G - 2 buildings
6/9/2026 - Adam said they are going to move the MSA, HAC spools to the Lighting Program, for one source
Melanie and Keylan said it can be done
6/30/2026 - FTI wants scanners badged
TXE1 special Support approved
H Support hanger, supposed to get stamped this week
HRV supposed to get linked in models setup so we can coordinate ug
Need to verify LEB and TXE CIA points
SS Headers are in fab per EAN
John Rhee asked about Waldinger misaligned, we are now good, sending email showing HDR is off
Toms Eng review comments will be looking at doing updates next week
HRV Embed Dims, ryan says he has, I have Angle working on them now, wtf?!!!
PIQ, melanie is setting up, I asked her to keep an eye out for the BIM ex plan and contact list
Michael said they have drug test this week, orientation on Monday
7/7/2026 - Cancelled
7/14/2026 - Melanie is going through EMT with cupertino to verify alignment
Isabella asked about clashing HRV, Peyton will be running coordination model for HRV as well as EMT
HRV Embed sheets need to be sent to Basebuild, adam mentioned
Still waiting on word a
7/27/2026 - Adam said Zach gave him the low down on the CIA, it is not a contractual document, it was sebastian telling faith to do it
8/4/2026
1100amLEB - BIM/FAB Weekly Meeting
Reece Fauble
I missed meeting for Facility water with TXE
Listend to transcript
Meeting is to kick off discussions between bim and fab
Reece has packages setup for all buildings
has spools on packages for leb10 and leb1
he needs leed times
Storage will be an issue
No packages for sheet metal yet
Needs an idea from each package time frame and for storage
Ean says Ron can answer better next week
6 weeks before field install date, standard minimum
8/4/2026 - EMT Anchor, adam says dcb was approved, tom says we need to do submittal for network suite
Evidently the Expansion Tanks on TWMU skid are undersized so Tom/Brent/Steven/Brett want to add another one off skid
Ben Hensel says he submitted anchor for structural concrete approval
It looks like corbin is approving the DCB anchor for EMT, need to submit for NWS, Adam asked where the submittal for DCB for EMT lives
Asked Michael about Water Tank skid. We will need to get together and see what they need built
1200pmTXE-Region3 Coordination Meeting
Jade B Lowe (Hensel Phelps)
Jade is in charge of Region 3
Kyle cummins is in charge of site
Filll out contact excel sheet, put bim lead and project manager
Kyle - LOD 450 project, all installed elements are modeled, then asbuilts are fed back in to model
Indicate in the model some where that the asbuilt has been applied and model has been adjusted
6/16/2026 - Decided not to go to this one since its Region 3, TXE6,7 undergound
7/21/2026 - Missed meeting since they are covering base build
7/28/2026 - Missed meeting since they are covering base build
08/05/26 - WED (+9 Meetings)
630amEMT - Daily BIM Alignment
Abe Hernandez
Scott gave an overall for the MES/HAC foot clash
Melanie Working through EMT Models, links needed repathed
Go Through EMT1 and EMT2 and make sure MES, TW and MP content are good
IF good, push to Revizto
Also check MSA/FSHAC Piping
EMT Does have IFC's for Base Build, Scott showed them yesteday, I coulda swore we didn't have any sheets, prob thinking of HRV
7/22/2026 - Ryan says Mortenson is on the verge of issue stop work order with Meta due to electrical incompetetance
Neema says stub ups need to be slurried, underground pipes need to be verified for undergound thrust and that passive soil will be sufficient
Above ground thrust will be satisfied by slurry and surrounding footers
MC Dean Bridged files
Danton Wein with MC Dean
MDI has steel and skids, fabrication
ENG has electrical equipment
They both have all links turned on, these need turned off
mcd plan for trench moving, not relating to Southland
Southland
MP Model connections to FW UG Stub ups
Need CWC Bypass, will they be included in the CWC Model we already have or in a separate above ground model?
Ben verified the models are good
Ben then went to stub ups and neema took the convo to RFI something, I said we were going to take a first pass at matching CWC Stub ups
Neema was talking about some kind of trnech shit moving that didn’t apply
7/15/2026 - Adam CWC said no update on the bypass for CWC
7/22/2026 - Talked FWM and MCUP issues mainly
Eli from Colonial was present
Neema says they need to move FW Stup ups away from footer about 5"
I mentioned they need to hit the critical North south dimension of 6'-1 5/8" to match the mes skid line, but we can match whatever movement they do east and west
Ben and Neema both pointed out CWC can rotate bypass valve to the front, one of the bypasses was already rotated this direction, CWC started to fight back a little bit
This means CW Will need to move their stub ups to get out of way of footers
Danton affirmed that the 2 MDC ENG and MCD MDI Models are the current models for the FSHAC
Storefont issues
7/29/2026 - Ben gave dimesnions of shift in DCB2, around 4" toward wall, and will rotate valve
Ben said they are doing things in the field to make sure they hit the 6' - 1 5/8"
Once the shift is completed in DCB2, Ben will ping us
800amTXE/LEB Weekly Internal BIM Coordination | Meeting-Join | Microsoft Teams
Jay Keiser - FTI
LEB10 RO Hitting Column
LEB10 FLEX HOSE on 8" Flush skid hitting column, need to clear clashes
talked about email I sent about a list of which models to use for which trades as far as Walls, Wall Panels, Electrical, Arch, Structural etc
Kyle said he was still working on that
John Cowhey is asking about Lugs on the MES
I will chase this down, find who responded Johns email and start there
Robert Cheek responded on Monday saying he would get the answer same day, still waiting
I told Jay we are currently working through shop drawings and spools, while we are doing those we are paying attention to clashes and working through the clashes
I Brought up the FW underground being off and that we will be scanning and verifying CIA POC's, Should be doing this within a week
5/27/2026 - I BROUGHT UP LEB1 COORDINATING WITH CRIDER NO MODEL, USING HDR FOR UNDERGROUND COORDINATION
JAY BROUGHT UP TXE10 ANCHOR CLASH WITH WALL, ADAM SENT EMAIL ASKING ABOUT IT, SOMEONE SAID THEY WERE CHANGING WALL IN A EMAIL RESPONSE, ADAM REQUESTED MEETING, NO ONE RESPONDED
JAY ADDED THIS AS AN ACTION ITEM
EMMA SENT EMAIL REQUESTING CLARIFICATION, TRISTEN WAS CONFUSED
LUKE SAID HE WILL DISCUSS IN HIS MEETING WITH MORTENSON
JAY ADDED THIS AS AN ACTION ITEM
6/3/2026 - New LEB Mech and Plumbing meeting on Wed, John and Reece involved, going over FW stub up locations and F/F water gallery connections
Informed John of Convos with Greg to coordinate wall install with coring of anchor plate holes
Told Jay/John, Lance Holmes is coordinating with other trades on fix for LEB UG FW stubups not hitting POC points or dimensions
6/10/2026 - Verify Span models work on LEB10, 1, 2
6/17/2026 - Checked LEB1, Span_SS model is still only showing Labeled grids, no steel in revit linked model, 2models, same dates, different version, latest verison wont load, gives error
Bring up Walbringer as new MP contractor on LEB6, sent email out with dimension sheets for someone to get them the information
Coordination Sign off
Jay gave links to Turner and HP sign off locations
Clash Review
Jay said he will go through and filter out white noise, setup a meeting to over others. I told him whenever he wants and I will be there
Friday 6/19/22 9am
6/24/2026 - Check with Adam if he verified the lastest info from Crider lining up ug, LEB10
Check LEB1 model HDR Underground lining up with Model, We are lined up with HELM Bypass on LEB10
Luke will get with LEB and Turner for Verifying CIA Points
Louis will get with TXE and HP for Verifying CIA points
LEB6 - MP Model misalignment, I checked the Turner NWD, they are using a FTI Container that may have a misaligned MP NWC
I Put together and new NWD with current NWCs Available and everything lined up correctly
LEB, DCW Drops, Get with John to find out which way they want to go, then follow up with HDR and Helm and Waldinger
I sent John Rhee an email requesting update
7/1/2026 - Jay brought up LEB6 issue I emailed, I told them HDR still needs to update their pipe stup ups, they fixed the grid though
I brought up CIA from other GCs since they were talking about FTI Scanning HP elements, if HP didn't provide documented points what is FTI going to shoot?
Justin said yeah, it is a meta requirement but meta hasn’t really lined out what exactly is required
I told them FTI did such a great job on the document and spearheading it, I was wondering if the other GCs also maintained this document since we are connecting to systems from other trades
Jay follow up with Kyle on HP for going through HP clashing directly, can we access them, create issues, clear?
7/8/2026 - Brought up LEB10 turner models, stay with NWC, even though they have
Advised that I have moved our DCW POCs to match HELM and HDR
Advised of TXE10 Scanning schedule starting tomorrow
Waiting on Patrick B for response on HAC FCU orientation
7/15/2026 - Told Jay, I havent verified Turners FTI Container files are updated this week
TXE Told Jay, Adam noticed the Fan Coils may need rotated 180 degrees, sent email, waiting on Patrick B to look at it
Verify Bypass submittals to FTI for John Cowhey
Check LEB6 FTI Container updated
7/22/2026 - Patrick sent out email saying txe10 FCUs have been reorientated based on Adams email, he will be going to other buildings
John is still waiting for Submittal for EOL HAC Bypass, he is talking to Jacob onsite, need submittal approved and start releasing fab on those
Underground conduit was missed for TWMU Skids, they need to be run overhead, it’s a substantial amount of conduit
Sent John, Justin, Jay the Control Point Map
Told Jay I would do a fly through on Leb10, LEB2 and LEB6 checking for FTI Container alignment
Do we need to do an official submittal for the Dimensions for UG Stub ups and Bypass elevations?
Start using ACC Issues module for tthings like LEB10 Crider stub ups being off
7/29/2026 - John says, he still hasn’t received the Bypass Submittal
I told Jay I would send LEB Control point email from Richard Lopez
I said I would get with Jacob and Keylan to make sure he gets it
I gave low down of what we are scanning, including CP's, what happened with CSV from Kyle
I asked if FTI was doing Trimble next week, john said yes and they will check certain things
I explained how the columns were off, I thought HP should be verifying columns and grid lines, walls may be off
8/5/2026 - They need stub up information for Conduit for the TWMU skid
Alex Harpel says the control points may be off at TXE10, Jennifer will be going through and verifying points
I told Jay, Region 1 alignment looked good, Region 2 I will check at end of week
check leb6 slab elevations different
830amMCD + SOUTHLAND + TATE/FSHAC Coordination Check IN
Updates to MSA piping completed and pushed to ACC, cantilever supports, support changes
RFI 146, MOFE OFE
MES PIPING ALIGNMENT WITH MSA Alignment is different
04 MES skid, make sure MSA is aligning with MES 04 skid based on this RFI
MAKE sure MSA SKUS are updated
Make sure MES Skid 04 includes this RFI
Give Arthur and team updated info so they can verify steel is appropriate
Darrin says HRV1 and HRV2 Clashing models are complete
Running clashing through Navis, our VDC Team should be able to get access
I asked about Southland being able to view their clashes
Darrin said they were having disccussions about moving their clashing to ACC Model Coordination
I said we would touch base and peyton is spearing heading our clashing coordination to see what direction we will go
Scott Brought up HAC Alignment and things not centered
Arthur said they will check it out
We need to make sure the SOUTHLAND MES Model is bridged to MCDEAN so they can use that model
Follow up with Melanie, heath
I sent out a clarifying email that since the mes models are host on MCDean, they don’t need bridge. I told them the models we are using for coordination
7/29/2026 - Isabella said she talked to Tom Chirdon and Tom Maxwell, couldn’t determine where RFI 146 was, white its not in programmatic forma
Arthur wants to do same time tomorrow with USCE and Tom Chirdon so we can all get on the same page
It will be Wade from USCE
Isabella asked about clashing and updating steel model
Update tomorrow
Need hac model completed before we can finalize placement of Fan Coils
Peyton is talking to Darrin about seperating the models for clash coordination
What DCIS is it? 4374, is what this write up refers to
Arthur said he will get with meta and make sure it gets escalated to Meta so it gets handled on a programmatic level
900amLightning HRV - Internal Detailing Meeting
Isabella Vesce Rivera
Bridged files from Colonial
Isabella will bring up we need bridged file
I requested to sit on base build coordination meetings with DPR/ Colonial
Adam wants form to access DPR, he will give it to all
Tomas maxell and chirdon talking to structural engineer about eliminating the middle anchor on DCB100
Adam added couplings to MSA that will allevaite having to add welds for field install
Packages were created in stratus, should be able to get dates by EOW
MSA to HAC needs some couplings removed
Depending on if Ryan can put the couplings on GMP Field because Fab is hard bid
Adam will remove from on site scope, per Ryan
Adam Dial in how we want to name NWS MSA for spool sheets
Adam wants to name them so they are more in line with the stratus packing naming
Deliverables -
Sign off and install schedule
7/15/2026
Waiting on Corbon to yay or nay the middle small anchor
MC Dean is still making adj to hac steel, they did state it shouldn't affect any of our content, ian is supposed to be complete on 9/24
Adam is supposed to put couplings in MSA to stop field weld
Need this update in stratus per Ean
All packages are created in Stratus with Dates
Get with stone and scott about getting FCU in the HAC for HRV
Southland will be running our own Clash Coordination
MC Dean provides a NWC, but we are choosing to use DPRs NWD in our own Model Coordination due to being more current and includes more trades
Keith, Melanie and Peyton will be putting this together
Melanie says not to clash with their NWD, not good
Either we will use DPR Forma Model coordination, if not available, we will ask if we can bridge their models directly to our forma to run our own Model Coordination and clashes
DCB100 NWS1/4 signoff 9/22
DCB100 NWS2/3 signoff 9/29
7/22/2026
Gave run down to Thomas and Ryan of Colonial Stub ups
Trhomas says there will be a middle anchor
Peyton will be leading the Coordnation Model and space, will be issueing clashes
Will be running clashes today
Ryan did sent out an email to DPR and colonial web regarding the UG FW CWC Dim sheet showing critical dimensions
7/29/2026
Explained the moving of embed to get out of wall, will move all embed together but will cause actual anchor to shift on the embed placement
8/5/2026
Adam had to push publish, I lost stratus addin, cant find download, gave up
I updated HRV DCB100 and replaced 07 couplings with 107v
Gave isabella the work flow for Layout sheets for hot items, Sign off, Eng Review, Shop Drawings, Spools
1000amBIM Round Up | Meeting-Join | Microsoft Teams
Michael Kolnik
Jeremy says they are supposed to be scanning in a week or 2
Jeremy needs Floor drain locations from Cerris so they know exactly where they land, Need to get with Patrick Marshall at Cerris and see if we can get some shop drawings.
6/3/2026 - MICHAEL ASKED ABOUT CURTIS GIVING HIM AN ORDER REQUEST THAT HE THOUGHT WAS SUPPOSED TO BE FOR FLUSH SKIDS
IT HAD 16X14 TEES, 14" 90S, 8" STAINLESS CAPS
HE DIDN’T KNOW WHERE THESE TEES CAME FROM
I TOLD HIM THEY WERE FOR THE MES LOOPS, NOT THE SKIDS
THE 14" 90S WERE PROBABLY FOR THE FLUSH SPOOL TO CONNECT TO THE FLEX SKID
MICHAEL SAID HE CANT GET THEM IN TIME, SIAD HE IS LOOKING AT DOING A MATERIAL SUBSTITUTE REQUEST, I SAID IT ASAP AND PUT CURTIS IN THE LOOP ON IT
6/10/2026 - Michael said he is having a meeting Friday about FW scanning and fix for fw off dims, with HP, FTI, Scanners,
6/17/2026 - Adam brought up supports, new design doesn't leave room for any adjustments
Michael says scanning will be around 7/1, if UG is off, michael says we will have to fix and charge HP
Are we going to have 8 unique supports
Paul says we will have to do it in the field
Paul and Michael agreed a new stand with Trapeze hangers will work, adam wil resubmit
Michael has order all fittings and pipe for TXE10 and TXE2 for MES loops
Region 1 is staying with 1 flush skid
2 flushes, twice as long, michael said it doesn’t schedule, not enough time for 2 flushes
6/22/2026 - Adam is telling Michael they need to create packages in stratus for how they want hac jumpers, bypasses split up
Adam is proposing a fabrication kick off meeting with Ryan and Curtis to get everyone on board
Micheal needs 8 weeks, Curtis needs 3 weeks for example
Jacob says curtis wants packages created by cost codes, but we are talking about splitting them by areas
Paul says give tom a curtisy that we are rele
Need to update the 6" flush skid and put a bleed olet on the return vertical
Paul says hes not sure where the Bypasses are as far as UG Bypass
Pual not sure when production will start for Near site, installing bypasses on HAC on near site
He will then put the spools in the appropriate package
6/30/2026 - Paul says caps are needed on MES TW and FW Ports, they can put drains on if they want
No drains on jumpers
Curtis is shipping spools to SOK
Curtis said no drains on caps, just need caps
Michael, going over spools
No Drains on jumpers
Look at TXE1-01-FWR-JMP-001, showing Flex coupling, need quick vic
Michael Ordered 16x14 tees, make sure we stayed with those and didn't update to full 16" to flush skid
7/8/2026 - Michael and Paul requested 6" and 14" Flush spools to be stainless
Sent info to Tom and Stefan, Tom says no, the flushing chemicals will clean it
7/15/2026 - Jacob says curtis put dates a month earlier than whats listed
I Told them Curtis is the one who would determine if we need to change material, stick with what he says, move the dates to 6 before install date, and get that request out, if they can't meet that, curtis will decided the next direction, weld?
Looked over installed bypasses at TXE10, everthing is off.
The Anchor plate was 5/16" off and into wall space on ML1 area
7/22/2026 - No Meeting, no popup, no cancellation
1030amEMT - Mortenson BIM Coordination Meeting
Nate Black (Mortenson)
UCO3 Loop OH Coordiantion Sign off 7/24
Nate pointed to coordination models that will b
Scott asked about the container models and who is creating it
nate said if we can push our models to revizto directly, that would be great
Heath said he can do this
Need to notify heath when they
7/22/2026 - Went over Drone Fly through
FCW is being dropped in EMT2
Skyline safety share
Alex Eismore, mental health
7/22/2026 - Just covered based build items
1130amEMT - Mortenson BIM Component Call
Nate Black (Mortenson)
7/15/2026 - Cancelled
7/22/2026 - Meeting is still listed in Calendar, mainly Southland BIM team in invite
Go over UCO3 and EMT2 Wrong Locations on Base Build and Lightning Scope
ON Key plan the A sectors and B sectors need to be swapped
Heith said he missed it when he set it up, takes full responsibility
We havent' issues any sheets yet for EMT
08/06/26 - THU (+10 Meetings)
600amTXE10 Facility Water Tolerance Issue
Jake Williams (Hensel Phelps)
Waited for Brock from Cerris, once he showed, he said their scans didn't show them as far off as we are showing in pics
Paul says they pulled from Columns
The ML1 is about 3-3/4" off, ML2 is about 2.5" Off
Zach maded the comment that walls would need to move, if we were to move our anchor, things would need resubmitted for approvals
Brock said as of now the only way these pipes move is by jackhammering
Dan Laub says no one responded back with an accepted Tolerance, they were trying to say 3-5" and he admits that was't acceptable, but 1/8" isnt attainable
Zach responded saying 1/4" and the tolerance was submitted in the CCIA, which Dan didn't know what that was
Zach continued with 1/4" tolerance
Alex Harpel brought up Adams email from 3/11, which was addressed to Dan as the last in the chain and Adam said 1/2" tolerance
Dan said he never got the email, Alex showed a screen shot showing his name in the TO Field
Keylan explained we have scan going back out next week to capture the CPs, we will have scans ready end of next week for meeting on 8/3, everyone agreed
Jake asked Brock to come up with solutions in the meantime
8/3/2026 - Paul says lets try to hit them, I said Wednesday after noon, said meeting Thursday at 6am PST will be good
Keep track of time
8/6/2026 - I said yeah we aligned, you can look in the federated model or any coordinated models, the new alignment has been published and new NWCS have been exported.
I brought up Alex Harpel saying control points may be an issue.
Anna Cummins(?) said we can setup our own control points. I said no, we need to have verified control points from the General Contractor that everyone is using on this. We are trying to align things down to less than 1/2", we need to make sure the control points are good. Setting up our own Control points can introduce issues we dont want.
I said we will get with field and fab to vet constructability and look at updating fab, verifying things will work with the anchors and if there are issues there, get engineering involved.
We will keep all updated on progress.
630amEMT - Daily BIM Alignment
Abe Hernandez
Scott gave an overall for the MES/HAC foot clash
Melanie Working through EMT Models, links needed repathed
Go Through EMT1 and EMT2 and make sure MES, TW and MP content are good
IF good, push to Revizto
Also check MSA/FSHAC Piping
EMT Does have IFC's for Base Build, Scott showed them yesteday, I coulda swore we didn't have any sheets, prob thinking of HRV
7/16/2026 - Melanie says our MP model doesn’t line up with Eng Model, we are using Lightning Shared Coordinates, Eng is using ETM100
Abe - Attached Sign off schedule to summary email, have content populated and coordinated ahead of signoff dates highlighted in RED, these dates line up with Mortenson
I told her our content, mes content lines up in revizto, if you change anything, it will no longer line up
Download arch model, link our models in and see who lines up
She says archs did change the g datum model a while back, she had to repath it and that’s when things stopped lining up correctly
7/17/2026 - Cancelled
7/20/2026 - Cancelled
7/22/2026 - Ryan says Mortenson is on the verge of issue stop work order with Meta due to electrical incompetetance
7/23/2026 - Cancelled
7/30/2026 - Cancelled
8/6/2026 - Adam said he will cover EMT, I will do the LEB Meeting
630-710amLEB | BIM | Faith x Turner
Luke Jost - Joe Dorinsville
Edwin Perez from Turner hosted
5/14/26 - - Joe Brought up the access panels for Flush system, asked about rating, I would have to check submittals to verify. Me and Lance holmes informed joe the flush systems are temporary, once done, they get removed and the access panel stay
Anna said they were aware, but not the finalized locations, now they will be going through Valley for engineering, excel engineering to make sure everything is accounted for, engineered
Talked to Stefan, we are not providing the Access Panel, its GC2 wall, they are providing it
I need to check on RO system, ACCess panel and it looks like location may be borked
Scott asked about sign offs for lighting scope to base build duct connections, Joe said they havent covered it, sign off is around end of June. They will be circling back to loop area not that they have certain paperwork available
Joe said any issue can be brought up at anytime
5/21/265 - No John Rhee, Brent, Thomas Holler, NO PM TEAM
They went over stud wall model, Lance asking about raceways for security and bus ducts
5/28/2026 - They went over electrical stuff, skid placement, wall leave outs
Turner wants a meeting with Helm and Southland to go over Wall penetrations
Joe D discussed Span model naming, keeping them the same and consistant.
Will need to relink LEB Span models since they have new models with Nucor suffix
6/4/2026 - Eduardo Ibanez brought up Status of Facility Water Stubups asking if Verification of Stubups with Mortenson needed. Had Crider submitted? Lance was saying Ryan would have this info and asking if Ryan was in meeting
NO PM Team present
I sent PM Team a summary email
I explained, Ryan used HDR model for coordination, I worked with HDR to get everything line up, we provided dimensions, everyone agreed to them, now stub ups are off, Lance Resposnded to John Rhees email asking what is being done
I said we need to start having meeting to go over this issue since its so critical
Luke Jost told eduardo to add an action item for this and lance said he will head this off
6/11/2026 - I brought up the FW UG being off again, told the group Ben Kozel with crider said they were backfilling in layers and trying to get the stub ups on the POC/CIA points
Overhead Signoff is schedule for 6/30
Scott asked if it was entire building for NWB, Joe says yes
Joe Brought up IMP walls changing to Framed walls, Anna? Said it was still being worked on
Verify LEB10 POC For DCW
Verify DCW POCs line up with CIA
Lance said they are also providing a hose connection for discharge, I stated they are using the FLOOR Drains in center of gallery for discharge, Adam corrected me saying John has requested different discharge points. Wouldn've been nice to know.
Someone asked about the Flex piping from the 8" skid hitting the column, I told them it was flex pipe and temporary, that it will bend around the column
Vent in 6-19x6-D, adam told them to put in between MES Skid
Waldinger is doing the bypass on LEB6
Building 6 MES loops are showing misalignment with Waldinger Bypass
NO PM Team present
I said I would like it added to this meetings notes, Joe Dorinsville basically shut it down, saying it was a field issue
I said it was our issue also since we are constantly being asked to do overlays, which were happy to help any way we can, but this was more of a helm situation since they are the responsible party to connect to the UG and provide us with accurate points of contact according to the CIA
Joe reiterated it was a field issue
6/18/2026 - Edwin Perez is showing Verification on stub ups w mortneson needed. Pending Submittal. Eng. Drawings to be submitted - Crider and Crider. He said this is still on going
Edwins model view still shows MP Shifted to plan right, access panels were to the right of the wall they are supposed to be in
LEB6 Arch Coordination model is showing everyhting off, MES Skid not lining up, mp is to the right, access panels are to the right of the walls they are supposed to be in.
LEB10, checked with Joe D, things line up there.
6/25/2026 - Joe, Greg, Luke Long, Greg went over Electrical coordination
I sent email to PM Team, no one was present
Eduardo Ibanez brought up Status of Facility Water Stubups asking if Verification of Stubups with Mortenson needed. Had Crider submitted? He brought this up again. I explained again that we provided dimensions for LEB10 and LEB1 to Mortensen, Crider and HDR, they all agreed
I told group that I also emailed these dimensions to Waldinger for Region 2, but havent received any comments or response from anyone.
Scott asked about tracking for signoff on 6/30, eduardo said yes
Luke Jost asked about LEB10 Embeds to make sure they are getting tracked by turner
Edwin Perez asked about Waldinger Bypass and alignment to SI MES Loop Connection
I told Edwin Perez I provided poc dimensions and elevations, but havent received any response
Edwin said he will bring up in next BIM meeting
7/2/2026 - Get with john as far as who is providing what cam lock adapt for fip drops
Lance Holman also provided additional dishcharges (Drains) for Flush/ fill per john
They showed model, HDR DWC Drops are on face of column, I told group IFC shows they are on Web side, HDR Model doesn’t match HDR IFCs
John Rhee is communicating changes from model to FTI, Turner that they are not telling us, Discharge drains, DCW changes
The only reason I found out was because of the meeting flythrough, our pocs were on other side of corridor
John fucking totally ignored our information and didn't relay any information
I missed the HDR IFCs showing the drops on the plan south side of corridor
I explained LEB6 model misalignment was fixed, publishing issue, I will double check mondays model after the Saturday auto publish
I told group about the FW UG Dimension sheet that has been distributed multiple times and it details where the FW UG stubs are supposed to be ever since LEB1
I will double check LEB2 misalignment
They showed LEB6 and the 8" skids were into the columns again
I explained the deep dive I did last week, it shows everything aligned. There are issues with the FTI Container model that Turner is using for coordination
7/9/2026 - Setup LEB2 SI MP View off turner LEB2 Overall Building NWD, Crider is still off at Grid 2-50/ 2-D
Eduardo Ibanez hosted
LEB10
All Content on slab will be created in a file, progress is ongoing. Jay Asked what does this entail? Above Slab content?
LEB6
Our MP is still out of alignment in Turner LEB6 Overall Building.nwd, but Joe pulled in a recent nwd and it showed the FTI Container inside the Overall nwd is off
With joes pulled in NWD that shows us and waldinger aligned, Crider was still off around 8-10"
SI Duct and Waldinger do not align
Justin verified that Turner is using NWC files NOT the revit
Southland MP looks good
Southland MP model is still a little older, but non-critical
7/16/2026 - Joe D brought up some issue about control joints at LEB10, luke jost and jay kaiser will update as necessary
7/22/2026 - Joe D brought up control joint proximity to MP anchors, they scooted 1 at grid 29ish, no TW Skid.
Checking Coord Space at LEB I see Stratus models getting exported again on 7/17, that was last Friday
The only MP model available is from april, what the fuck is going on with this fucking shit
The LBE10 Publish settings were set to stratus, talked to heath, he showed adam was the last one to do it. Adam said he didn’t know had to change settings back
Lance suggested a meeting with FTI and Southland to get power to TW Skids, Lance Long said they have a meeting setup with FTI Tomorrow, looking at junction box on the wall
Jay K at FTI created an issue with Crider Facility Water Alignment and was trying to add crider watchers, he can only add FTI watchers.
Joe D told him to use Triston with Helm, Mitch with Waldinger
Mitch with Waldinger said it looks like its going to work out with aligning their Bypasses with Southland MP
Jay K brought up container models having outdated southland models
Joe D says its tough to say when the FTI container was reloaded. The last update they show was july 13th, 10 days ago
I rbought up the TW Skids on each end of the building also to check, they have anchors also
I stated I found a recommendaiton of 3" distance between an anchor and a sawcut or concrete joint
7/30/2026 - Jay brought up getting control points from Turner
Jay brought up missing MES/ TW skids from LEB1, LEB2 FTI Container, the MP content was aligned
8/6/2026 - I affirmed with Jay, I have not seen any blue beam sessions
I verified LEB 6 in Navis, using the View I created with all trades
James (Turner) is setting up meeting next week to go over CIA points with FTI and Baker
Jay asked about established control points, joe said bring it up in the session
830amMCD + SOUTHLAND + TATE/FSHAC Coordination Check IN
Updates to MSA piping completed and pushed to ACC, cantilever supports, support changes
RFI 146, MOFE OFE
MES PIPING ALIGNMENT WITH MSA Alignment is different
04 MES skid, make sure MSA is aligning with MES 04 skid based on this RFI
MAKE sure MSA SKUS are updated
Make sure MES Skid 04 includes this RFI
Give Arthur and team updated info so they can verify steel is appropriate
Darrin says HRV1 and HRV2 Clashing models are complete
Running clashing through Navis, our VDC Team should be able to get access
I asked about Southland being able to view their clashes
Darrin said they were having disccussions about moving their clashing to ACC Model Coordination
I said we would touch base and peyton is spearing heading our clashing coordination to see what direction we will go
Scott Brought up HAC Alignment and things not centered
Arthur said they will check it out
We need to make sure the SOUTHLAND MES Model is bridged to MCDEAN so they can use that model
Follow up with Melanie, heath
I sent out a clarifying email that since the mes models are host on MCDean, they don’t need bridge. I told them the models we are using for coordination
7/29/2026 - Isabella said she talked to Tom Chirdon and Tom Maxwell, couldn’t determine where RFI 146 was, white its not in programmatic forma
Arthur wants to do same time tomorrow with USCE and Tom Chirdon so we can all get on the same page
It will be Wade from USCE
Isabella asked about clashing and updating steel model
Update tomorrow
Need hac model completed before we can finalize placement of Fan Coils
Peyton is talking to Darrin about seperating the models for clash coordination
What DCIS is it? 4374, is what this write up refers to
Arthur said he will get with meta and make sure it gets escalated to Meta so it gets handled on a programmatic level
7/30/2026 - FCM Placement update, early next week for that
Updating 2nd family content
Darren and Doowoo, may have an federated model "Soon" according to Isabella
Arthur role is FSHAC designer, They brought on SJS to manage Coordination, Darren is project engineer, hes the one for Model coordination
Adam will be putting together snips that shows where we are at compared to rfi 146.
Isabella says the rfi was answered for UGS and they are looking at moving pipes to realign
Had to leave early to talk to carsen scanning at txe
900amTXE-FTI Weekly Sync Meeting
Luke Justice
Luke was asking about scanning at TXE10, He said coordinate with Greg Hueramo, he will be setting up an origination email
I told luke they need to have all areas ready for scanning since the team cant be sent out every other day, reset up, etc
I asked for Control point map, he said get with Greg Hueramo
I explained to him what the scanning was
I told him they will need to add paul hernandex, jeremy miller and adam brown to email
John Cowhey said he has a 1 pager for Site orientation which will be 8 hours
They will be enforcing badging within the next few weeks. No badge no access, Visitor badges will be available but not allowed to work
Luke will put together a schedule for orientation
11/17/26 - is new date for 0 prep according to John Cowhey
Forward FW off email to Luke, original email was sent out 4/17. I resent to Luke Justice
I told him Jeff Balthrop was involved a few weeks back
Send Luke Discrepancy on Anchor locations with BZI Wall panels, NWCs etc from Adam email, Adam email 5/5, TXE Adam email 5/6
Verify anchors at TXE and LEB, check they've been submitted to FTI
Send notice to John Cowhey, luke justice
They asked when Southland is looking at manning the site, jeremy informed them no PM team were available at this time to answer
new schedule coming out Friday
Got with michael kolnik, he sent out Shop Drawing submittal request to Eric Boehger
5/28/2026 - Loop Keylan and Michael into the Anchor clash info and meeting for Friday
Luke says bypass are fabbed, not installed will be installed next week, sent out email to everyone, paul, jeremy, michael
Need to coordinate orientation, drug testing
Day zero schedule? Luke said he was supposed to get last Friday, not seeing anything new
Luke showed the Faith TXE Anchor Shop Drawing submittals, they are only for the TXE10,1,2 Plates don’t know why it has TXE3 on the label
Not showing any Shop drawing embed submittal info
NO PM Management was present, Keylan Rollins was for engineering
6/4/2026 - Luke Cancelled at 741am, Got DAMN MAN!!!!
6/11/2026 - Luke Cancelled at 741am, Got DAMN MAN!!!!
6/18/2026 - Luke asked about Issues, I was explaining a summary of Greg Heuromos meeting, then Michael Kolnik was there! It was nice
6/25/2026 - Michael says greg told him the bypass will be complete on 6/7, michael has scanning scheduled for 6/6
Jason with FTI will use truck to help scanning move around job
Scanners will need badges, they can be escorted according to michael who talked to security
Michael says no one onsite yet, they are on first of kind, michael and jacob did get badged
FTI does have a superintendant and a couple of upper management onsite
Fully mobilized first week of July
Luis says they have been requesting a lot of BIM information, Asbuilts, trench information, etc
Luke says a laser just got done for the Trench
Alec Harpel says first half of txe10 was scanned, still waiting for coordinates
Need FW stub ups, grounding whips and trenches
Luis is asking for points for the finish floor to verify elevation/flatness
TXE1 slab just started pouring last week, according to Luke
Micahel said they wont have water into the building, they need to truck it in and provide the minimum GPM with 3" connection
TXE10 shows 3" main with 3" drops
TXE1 shows 4" main with 3" drops
7/2/2026 - Luke Justice cancelled
7/9/2026 - Luke Justice cancelled
7/16/2026 - Keylan gave run down of Scanning and photos, scanning completed
Jacob stated carsen is locating revit files and uploading info
Should get scans by afternoon
7/23/2026 - Luke asked about Control points, I told him we did get the PDF from Shay with coordinates and CP labels
I can use this to get the CPs into the model
I informed them that Justin Jenkins was looking for Dimensional data from CP to a known point. I said I would follow up with Justin
Sent email to Justin Jenkins with CP map and letting him know they didn’t understand the dimensional data from CP to Known point
7/30/2026 - Russell Faulkner, wall of destinys will be completed tomorrow
I told luke about missing elevations on CPs in building on the map, also identifiers were getting wiped out, couldn't tell which CP was which
Told Luke thye finished scanning yesterday, should be able to put everything together for the meeting with Jake Williams on Monday
8/6/2026 - Louis Saldana says meta is putting a third party survey onsite to verify control points
Keylan brought up getting the stub ups in the correct position in future buildings
Told luke walls are in the wrong spot, we cant set our anchors if walls are wrong
Luke says hes used to scanning before slab and after slab
He will find out
He said they were having issues verifying control points and aligning conduit at wall of
He says TXE2 is poured
Hes says TXE1 is not poured
Keylan said we would like to get this sutaiton taken care of before slabs get poured
930amLEB | BIM COORDINATION LEB2
Emma will no longer be on this project
Kaushal Bagdekar with Turner ran the meeting, saying who to contact for what, I asked if he could send an email with that info
They went over underground clashes
5/28/2026 - Tristen with helm verified he is using LEB1 dimensions for LEB 2 elevations and locaitons for FW
6/11/2026 - No PM Team
Went Over UG issues, concrete pads
6/18/2026 - Kaushal Bagdekar
Did a flythrough for LEB2 going over exterior sectionalizers
LEB-2_SPAN_SS.rvt, verifying during meeting that the model is good, Checked LEB2 SPAN_SS model, couldn’t load content, says cant link in NuCOR
NO Interior Walls and framing, Valley, Diogo or Ruth said they will get with valley
No Interior Meta Wall Panels
6/25/2026 - NO PM TEAM
They went over UG issues for LEB2
7/2/2026 - LEB2, Showed model where Helm, SI and Crider not aligned, #2070
LEB2 Building Overall actually has Crider model, showing misaligned
Grid 1-50, 1-D is the only spot where Crider is off looking at Turners LEB2_Building_Overall model only
Everything else is aligned, MP, Duct, Steel, Walls, no issues
Sent email showing misaligned concrete and crider stub ups at 2-50
LEB-SI-MP-LEB2-R25 model lined up identical to LEB2-Building-Overall
Didn't see new DCW POC valves, did I update LEB2
Did see FLUSH VENTS AND DRAINS, VENT ON 2-50 IS OFF
7/9/2026 - Sent Email to Joe, Jay, Edwin, Eduardo and Joe forwarded to Kaushal
Kaushal asked about flush skids in front of door ways, need to send them a time frame for flushing before equipment gets removed
Concrete elevations different at Gird 2-29 and 2-32
Crider stub ups off at 2-50/2-D
Added to chat
7/16/2026 - Sent email to Triston with Jay and Kaushal cc'd about Helm bypass flanges not aligning to SI MP Flanges throughout building
LEB2 looked like it aligned good
7/22/2026 - No southland issues covered
7/30/2026 - Just went over non-southland issues
I dropped for LEB Mortenson meeting at 1000am
1000 amLEB - BIM Coordination Meeting (Thu) | Meeting-Join | Microsoft Teams
Ryan Zoldan - Richard Lopez
LEB 6 due finalized next week
I requested a schedule from Ryan, he has the sign off, region schedule, I brought up a pull plan, be he says that will be through Turner
Mortensen is the Base build GC, why aren't they leading a pull plan schedule
John Rhee nor Brent were in this meeting
6/4/2026 - I brought up the LEB10 FW UG Stub ups totally missing the Dims, Ben Kozel was there and he stated they are bringing them back in to dimensions by backfilling a little and moving them, backfilling and moving them
He acknowledge that lance did contact him
6/11/2026 - Ben Kozel, said there were no issues that need to be talked about.
Richard lopez asked around the room for any issues regarding LEB10 or any others
NO PM Team
6/18/2026 - Richard Lopez Hosted, just asked for any issues with LEB10,1,2,3 Underground issues
Rantwiler asked when IWM for TXE10 was going to be signed off, Ethan says he will talke to kyle since they are not really split out
6/25/2026 - Going over LEB7,8
Ryan brought up LEB6, HDR model is not lining up with the Dimensions provided by SI
Ryan henderson said he will follow up
Ryan said we have all agreed to follow these dimesions, I added that I have distrubuted that dimesion sheet ot Waldinger and explained everything, but havent received a response yet
Ryan brought up LEB6, HDR model is not lining up and my email I sent out
I updated, still waiting for HDR to align the stubups
Ryan said Crider is using civil 3d, but we can work it out to actually use their model for coordination and linking in so I don't have to use HDR
7/9/2026 - No issues to cover, they went over UG clashing for elect, sanitary
7/23/2026 - Richard asked Triston about any alingment issues, he was good
Ben said LEB6 stil had some very minor HDR alignment issues to on udergoung
7/30/2026 - Bend said LEB6 looked good
I said we republished LEB6, there was some extra content we had to remove
8/6/2026 - I brought up the LEB10 FW UG Stub ups totally missing the Dims, Matt Schaff said they are doing repairs this week and lookingat getting into within an inch
I mentioned, for helms benefit of using Eccentric reducers on bypass in order to rotate the stubup to align with MES better
I also mentioned after slab is poured, bypasses installed, we look at doing 3d scans
TXE1 looks good for the loop area sign off next week
Same with TXE2
6/4/2026 - Own B ran the meeting going over TXE1 and 2
6/11/2026 - Owen B, says TXE10 Loop for sign off
TXE2 Core scheduled for next week
TXE10 AB Datahall and Loop are signed off
TXE3 Alan lopez is running region 2 for signe off
TXE2 Loop and AB South sign off
issue 2602 - Cerris Vent in corner is clashing with Technical water, Rantwiler is saying they don’t have our model, I told them our model has been there for 6 months, the fact that HP is viewing it, means the model is available. If it’s a bridging issue we will help Cerris work it out
Trevor said he will get with rantwiler and get the model bridged, they will offset that vent around our TW Piping
They made comments about the TW skid being so close to the FW valves. Its been this way for over 6 months. Trevor also stated the vent will need an accessible cleanout
6/25/2026 - They just went over IWM and specific Electrical clashes
7/9/2026 - TXE 2 all docs are out, all sign offs are out
TXE1, 2 sign offs left
DHCD 2 weeks from now
7/22/2026 - No Issues
1130amLightning HRV - Global BIM Coordination Meeting
Isabella Vesce Rivera (SI)
Is there a coordination model we get access to? Revizto? Navis?
Get input on HDR Mockup I made for FW UG Stubup, Bypass and MES Loop connections
Colonial was trying to align to SI Desing model, that was all that was available for the bridging
Seth Blizzard says they arent obligated to meet our POC's, they follow the ARUP design. ARUP did let them know they are contracted to meet our POC's
Curtis Robbins said he just needs to click a button to enable the bridging to our actual Coordination Models
Seth started making comments about use being able to shift our pipes 3", I told them theres a lot more going on that what they were showing with our Engineered anchors, flush connections, MES and TWMU skids and TW Piping, there isnt much forgiveness
Still don’t have access to bridged Colonial files
230pmTXE-FTI Weekly Sync Meeting
Luke Justice
Luke was asking about scanning at TXE10, He said coordinate with Greg Hueramo, he will be setting up an origination email
I told luke they need to have all areas ready for scanning since the team cant be sent out every other day, reset up, etc
I asked for Control point map, he said get with Greg Hueramo
I explained to him what the scanning was
I told him they will need to add paul hernandex, jeremy miller and adam brown to email
John Cowhey said he has a 1 pager for Site orientation which will be 8 hours
They will be enforcing badging within the next few weeks. No badge no access, Visitor badges will be available but not allowed to work
Luke will put together a schedule for orientation
11/17/26 - is new date for 0 prep according to John Cowhey
Forward FW off email to Luke, original email was sent out 4/17. I resent to Luke Justice
I told him Jeff Balthrop was involved a few weeks back
Send Luke Discrepancy on Anchor locations with BZI Wall panels, NWCs etc from Adam email, Adam email 5/5, TXE Adam email 5/6
Verify anchors at TXE and LEB, check they've been submitted to FTI
Send notice to John Cowhey, luke justice
They asked when Southland is looking at manning the site, jeremy informed them no PM team were available at this time to answer
new schedule coming out Friday
Got with michael kolnik, he sent out Shop Drawing submittal request to Eric Boehger
5/28/2026 - Loop Keylan and Michael into the Anchor clash info and meeting for Friday
Luke says bypass are fabbed, not installed will be installed next week, sent out email to everyone, paul, jeremy, michael
Need to coordinate orientation, drug testing
Day zero schedule? Luke said he was supposed to get last Friday, not seeing anything new
Luke showed the Faith TXE Anchor Shop Drawing submittals, they are only for the TXE10,1,2 Plates don’t know why it has TXE3 on the label
Not showing any Shop drawing embed submittal info
NO PM Management was present, Keylan Rollins was for engineering
6/4/2026 - Luke Cancelled at 741am, Got DAMN MAN!!!!
6/11/2026 - Luke Cancelled at 741am, Got DAMN MAN!!!!
6/18/2026 - Luke asked about Issues, I was explaining a summary of Greg Heuromos meeting, then Michael Kolnik was there! It was nice
6/25/2026 - Michael says greg told him the bypass will be complete on 6/7, michael has scanning scheduled for 6/6
Jason with FTI will use truck to help scanning move around job
Scanners will need badges, they can be escorted according to michael who talked to security
Michael says no one onsite yet, they are on first of kind, michael and jacob did get badged
FTI does have a superintendant and a couple of upper management onsite
Fully mobilized first week of July
Luis says they have been requesting a lot of BIM information, Asbuilts, trench information, etc
Luke says a laser just got done for the Trench
Alec Harpel says first half of txe10 was scanned, still waiting for coordinates
Need FW stub ups, grounding whips and trenches
Luis is asking for points for the finish floor to verify elevation/flatness
TXE1 slab just started pouring last week, according to Luke
Micahel said they wont have water into the building, they need to truck it in and provide the minimum GPM with 3" connection
TXE10 shows 3" main with 3" drops
TXE1 shows 4" main with 3" drops
7/2/2026 - Luke Justice cancelled
7/9/2026 - Luke Justice cancelled
7/16/2026 - Keylan gave run down of Scanning and photos, scanning completed
Jacob stated carsen is locating revit files and uploading info
Should get scans by afternoon
7/23/2026 - Luke asked about Control points, I told him we did get the PDF from Shay with coordinates and CP labels
I can use this to get the CPs into the model
I informed them that Justin Jenkins was looking for Dimensional data from CP to a known point. I said I would follow up with Justin
Sent email to Justin Jenkins with CP map and letting him know they didn’t understand the dimensional data from CP to Known point
7/30/2026 - Russell Faulkner, wall of destinys will be completed tomorrow
I told luke about missing elevations on CPs in building on the map, also identifiers were getting wiped out, couldn't tell which CP was which
Told Luke thye finished scanning yesterday, should be able to put everything together for the meeting with Jake Williams on Monday
08/07/26 - FRI (+4 Meetings)
730amLEB - Weekly Detailing/ BIM Team Catch Up
Reece Fauble
Verify 107V and 07 Couplings on Pup pieces, region 1
Adam said we are still working through comments, still waiting on cantilever approval.
LEB10,1,2 will be good to push out to submit to tom
Need to update regions to datahall A,B,C,D
Day zero is 2/25/27
Need spools before 1/5/27, Adam said we wiill shoot for 6-8 weeks before then to allow for review, updates, etc
Scott says EORs get officially submitted to Tom, he approves, they get submitted to FTI. Not sure if EORs get submitted to Meta or not as part of record drawings
Scott says by Friday the 14th they will publish to stratus
Embed Layout Drawings
We gave drawings, we will have
Crider and Mortenson will provide scans once they are finished, so that helm can update their bypass.
Flush Skid BOM, Curtis used TXE Counts and ordered the material
Hose Carts are still being finalized
Get Reece copies of TXE Flush skid BOM information
Hose Carts will be finalized once FOK and SOK are done
No pour until november
Schedule model? Can we incorporate this?
LEB10 UG Stubup status
Crider, Mike Schaff said they were doing repairs this week
Make sure LEB PM Team knows we need to scan after slab, after bypasses installed, then we align, update spools
830amMCD + SOUTHLAND + TATE/FSHAC Coordination Check IN
Updates to MSA piping completed and pushed to ACC, cantilever supports, support changes
RFI 146, MOFE OFE
MES PIPING ALIGNMENT WITH MSA Alignment is different
04 MES skid, make sure MSA is aligning with MES 04 skid based on this RFI
MAKE sure MSA SKUS are updated
Make sure MES Skid 04 includes this RFI
Give Arthur and team updated info so they can verify steel is appropriate
Darrin says HRV1 and HRV2 Clashing models are complete
Running clashing through Navis, our VDC Team should be able to get access
I asked about Southland being able to view their clashes
Darrin said they were having disccussions about moving their clashing to ACC Model Coordination
I said we would touch base and peyton is spearing heading our clashing coordination to see what direction we will go
Scott Brought up HAC Alignment and things not centered
Arthur said they will check it out
We need to make sure the SOUTHLAND MES Model is bridged to MCDEAN so they can use that model
Follow up with Melanie, heath
I sent out a clarifying email that since the mes models are host on MCDean, they don’t need bridge. I told them the models we are using for coordination
7/29/2026 - Isabella said she talked to Tom Chirdon and Tom Maxwell, couldn’t determine where RFI 146 was, white its not in programmatic forma
Arthur wants to do same time tomorrow with USCE and Tom Chirdon so we can all get on the same page
It will be Wade from USCE
Isabella asked about clashing and updating steel model
Update tomorrow
Need hac model completed before we can finalize placement of Fan Coils
Peyton is talking to Darrin about seperating the models for clash coordination
What DCIS is it? 4374, is what this write up refers to
Arthur said he will get with meta and make sure it gets escalated to Meta so it gets handled on a programmatic level
7/30/2026 - FCM Placement update, early next week for that
Updating 2nd family content
Darren and Doowoo, may have an federated model "Soon" according to Isabella
Arthur role is FSHAC designer, They brought on SJS to manage Coordination, Darren is project engineer, hes the one for Model coordination
Adam will be putting together snips that shows where we are at compared to rfi 146.
Isabella says the rfi was answered for UGS and they are looking at moving pipes to realign
Had to leave early to talk to carsen scanning at txe
8/7/2026 - Cancelled
1100amMNT West Piping Detailing Meeting
Adam Brown
Went over MW Piping Presentation Guide Power Point
Will go over ACC Publish and Review next week
7/31/2026 - Cancelled
8/7/2026 - Missed due to LEB Meeting
1105amLEB - Facility Water Piping Support Brackets and Concrete Coordination
8/7/26 - Nick Garver
They explained to Concrete Trade the shop drawings and the anchor submittal and that they would be installing them
Nick said this came from Lance
Reece gave an over view
Concrete dude said they will check the scope, but don’t see any isses
Reece told them top of plate = finished concrete
7/27/26 - 8/2/26
07/27/26 - MON (+6 Meetings)
630amEMT - Daily BIM Alignment
Abe Hernandez
Scott gave an overall for the MES/HAC foot clash
Melanie Working through EMT Models, links needed repathed
Go Through EMT1 and EMT2 and make sure MES, TW and MP content are good
IF good, push to Revizto
Also check MSA/FSHAC Piping
EMT Does have IFC's for Base Build, Scott showed them yesteday, I coulda swore we didn't have any sheets, prob thinking of HRV
7/16/2026 - Melanie says our MP model doesn’t line up with Eng Model, we are using Lightning Shared Coordinates, Eng is using ETM100
Abe - Attached Sign off schedule to summary email, have content populated and coordinated ahead of signoff dates highlighted in RED, these dates line up with Mortenson
I told her our content, mes content lines up in revizto, if you change anything, it will no longer line up
Download arch model, link our models in and see who lines up
She says archs did change the g datum model a while back, she had to repath it and that’s when things stopped lining up correctly
7/17/2026 - Cancelled
7/20/2026 - Cancelled
7/27/2026 - Cancelled
700amEMT Coordination
Abe Hernandez
Brought up CIA agreeement
This week EMT1 UG Signoff this week
Peyton showing MES MP Pipeing into duct and framing, mic didn't work so I couldn’t talk to verify MES Elevations
830amMCD + Southland + Tate / FSHAC Coordination
Arthur Foley (MC Dean)
First of a series of daily check in calls between Mcdean, Tate and Southland to make sure we get steel updates from Tate and clash detection
Matt Mcconnell is the PM from Tate
Should see new update tomorrow morning
Guin Yaprak verified this is the case, 10-11am tomorrow
HRV FOK will be in the NWS
MSA will be included
This will be a recurring meeting everyday
900amLightning TXE Staff Meeting | Meeting-Join | Microsoft Teams
Jacob Gelhousen
Will do scans after Cerris installs bypasses
6/1/2026 - Noel Nunez says Alehandro Chew will be safety manager
Michael said he sent TXE3 embeds along with PDF dimension in mid April
Doesn’t think TXE3 has been poured, think they are behind schedule
Says we havent been funded for Region 2, he is sending out embeds as needed
Michael asked what the question was about RO and TW, I said it was going over how to connect to the RO skid, from DCW and to TW MES
Michael asked if MES Loops were completed, adam said yes, he created new BOMs
Michael said his goal is to get everything ordered
Michale Paul said they thought the walls weren't going to be in until they could do anchor
They said that was what was agreed to
6/8/2026 - Michael said they had a PM Coins Mandatory meeting and couldn't host the meeting
6/15/2026 - Chris Moss came on board from TSMC, Pipe fitter, GF
Jose Alejandro Chew, new Safety Manager for TXE
6/22/2026 - Shop drawings (Engineer Drawings) looking at submittal on Frid, 6/26
6/29/2026 - Keylan Cancelled
7/6/2026 - Carson will scan on Thursday
7/13/2026 - Scans on TXE10 complete, should have done this week, EOW
Jacob will be pulling field measurements of FW Stub ups
Adam will overlay scans to see how they match up with our Stub Ups
SOK will be starting next week, 27th will have more setup covered
7/16/2026 - Zach wants scanning sent back out, scan off control points, need to get CPs from Greg, put in model, talk to carson to see what they need from us
Control points were requested on 6/12 meeting with Greg H, it was stated they would be sent to Michal and James Homrighausen
I also asked for control points from Luke Justice on 5/21, he said he would get with Greg H.
They made it out like it was detailing fault they scanned without using control points
Paul asked how soon I can get the points into model, I said immediately, but Im not sure scanning needs anything from us, they may input control points into the rcap software maually but we will have it the model if they need it
7/27/2026 - Scanning this week
FTI Will be doing Trimble next week
1130amMW Detailing Weekly Meeting
6/29/2026 - Marshall Cancelled
7/13/2026 - Missed, I thought it was cancelled
7/20/2026 - Armondo party on Friday
De Le Cruz tips and tricks, Title Blocks
7/27/2026 - Missed, went to Cameron Shop to meet Mid Atlantic Crew
1200pmEMT BIM Look Ahead Meeting
Nate Black (Mortensen)
UCO3 OH Signoff 7/24
Went over drone map, EMT1 and 2 have UG FW
Went over sign off schedule
Showed Marcos Revizto Clash Workflow
Showed UCO3 Loop OH
7/20/2026 - Went over drone view of jobsite
Joseie with delta went over heat safety
no PM Team
Got UCO3 sign off for OH on 7/24
7/27/2026 - Missed, went to Cameron Shop to meet Mid Atlantic Crew
07/28/26 - TUE (+7 Meetings)
630amEMT - Lightning BIM Weekly Coordination
Abe Hernandez
Printed IFC Addendum 1
Scott showed Mortenson schedule 7/6
Peyton Coordination Model - Meeting with Heath, model is setup, need to get heath input
Using forma coordination module for clash detection
Cupertino says they are fine using the Forma module
Ryan - wants the model defined as to which one to use and clash with for Cupertino
Scott says he is on it
I let abe know that the MES and MP constructability models are now in the Revizto publish
He told Cupertino they can use that
Scott asked about elec panels hitting columns, I shared a fly by on Revizto and it didn't show any issues on UCO3
I showed the team Temp Power and Skyline clashing with MES Loops
I also emailed Nate Black last Friday
Ryan Warner says there is tees clashing on underground with Cupertino in elec gallery
7/21/2026
7/28/2026 - Cancelled
800amWeekly BIM Coordination Meeting - Region 2 (ZOOM)
Alan Lopez, Kyle Cummings (Hensel Phelps) / Ethen Berry
No one started the meeting, I sent an email, they said Alan was PTO and they started meeting late
They went over Region 2 underground, sign off later this week
5/26/26 - Allen Lopez Went over Region 2 again, said they were going to do a main signoff then a branch signoff. Covered a lot of UG clashes
6/2/2026
2 weeks sign off branch
6/9/2026
6/16/2026
Allen Lopez says he doesn't see Sure Steel model in TXE3, Kyle says also no Diversified, but Sure Steel model is there, needs added
Signoff schedule was not bridged, the one on FTI is outdated. Kyle and Justin said they would get the bridge up to date
Files - Data Management
6/23/2026
6/30/2026
7/7/2026
TXE3 Overhead Loop signoff next week
TXE3 Overhead Datahall signoff is July 27th
7/14/2026
7/21/2026
TXE3 Loop OH Signoff on Friday, DHA/B Following week
NO PM or Field Team present
830amLEB - BIM Coordination Meeting (Tue) | Meeting-Join | Microsoft Teams
Ryan Zoldan, Mortenson (GC1)
Missed for the 8am meeting
6/16/2026
6/23/2026
6/30/2026
7/7/2026
Ryan brought up their grids were off, crider and crider will be aligned today and HDR will be aligned. For LEB6
Ben Kozel says all waldinger was missing a flange on their bypass, everything else looked good, crider was good
Ben says HDR looks good for UG and Grids
7/21/2026
Talked about LEB6 HDR not matching Soutland provided dimensions, bullet point #1, supposed to be covered in meeting tomorrow
Talked about Underground stuff
830amMCD + SOUTHLAND + TATE/FSHAC Coordination Check IN
Updates to MSA piping completed and pushed to ACC, cantilever supports, support changes
RFI 146, MOFE OFE
MES PIPING ALIGNMENT WITH MSA Alignment is different
04 MES skid, make sure MSA is aligning with MES 04 skid based on this RFI
MAKE sure MSA SKUS are updated
Make sure MES Skid 04 includes this RFI
Give Arthur and team updated info so they can verify steel is appropriate
Darrin says HRV1 and HRV2 Clashing models are complete
Running clashing through Navis, our VDC Team should be able to get access
I asked about Southland being able to view their clashes
Darrin said they were having disccussions about moving their clashing to ACC Model Coordination
I said we would touch base and peyton is spearing heading our clashing coordination to see what direction we will go
Scott Brought up HAC Alignment and things not centered
Arthur said they will check it out
We need to make sure the SOUTHLAND MES Model is bridged to MCDEAN so they can use that model
Follow up with Melanie, heath
I sent out a clarifying email that since the mes models are host on MCDean, they don’t need bridge. I told them the models we are using for coordination
1000amLightning-Eng-Coord Huddle | Meeting-Join | Microsoft Teams
Tia/ Tom
Follow up on HAC Panel clashes with Patrick Brinnehal
Meeting to go over stratus and models with all PMs, Adam, Scott, Supers sometime next week, look at schedules
Chris Chase is the PM of EMT
5/26/2026 - Check if Adam got the 4" Welded Bypass to Shop, from 5/5/25 email in Inbox "Im shooting to have the LTG build out scope package done by end of week (For Review only not for construction). "
Verify what spools have been put on stratus for TIA/TOM Lightning huddle
Need meeting to discuss, txe10 anchor clashing with interior of walls, adam sent info out about conflicting models, but as of today, there is still clashes
RFI says they are changing wall to Gypsm board and expanding toward corridor 2.5"
6/2/2026 - We did get 2 more sites in Ohio
SI will be integrator
Heath introduced Peyton Steveons as VDC supervisor
Starting with HRV
Melanie introduced Vasi, VDC specialist helping out ron and melanie
Tia went over deliverable schedules
Per site, per building
She setup a break out meeting
Adam said they are moving the walls away from anchors so we are clear
Adam said we are 1/2" clear from plate, it will be a field issue installing the plate
Michael said he will talk to paul, he doesn't know what to do, he will call greg
only 2 walls changed from IMP, 2 others are still IMP
Michael said Greg told him they are putting walls up next week
Told Tia I sent snip of Dog Leg Metraflex in chat, didn’t get any smiles
Let her know we have LEB complete, TXE10,1,2 is complete
Adam said he will give link to CIAs, TXE3-12 and LEB3-12 not ready
Adam had meeting with HRV, told them to start using our coordination models for coordination
Quick hello, this is who we are meeting
with MC Dean
Mealnie says they will be updating projects to new architect model
Type F - 4 buildings
Type G - 2 buildings
6/9/2026 - Adam said they are going to move the MSA, HAC spools to the Lighting Program, for one source
Melanie and Keylan said it can be done
6/30/2026 - FTI wants scanners badged
TXE1 special Support approved
H Support hanger, supposed to get stamped this week
HRV supposed to get linked in models setup so we can coordinate ug
Need to verify LEB and TXE CIA points
SS Headers are in fab per EAN
John Rhee asked about Waldinger misaligned, we are now good, sending email showing HDR is off
Toms Eng review comments will be looking at doing updates next week
HRV Embed Dims, ryan says he has, I have Angle working on them now, wtf?!!!
PIQ, melanie is setting up, I asked her to keep an eye out for the BIM ex plan and contact list
Michael said they have drug test this week, orientation on Monday
7/7/2026 - Cancelled
7/14/2026 - Melanie is going through EMT with cupertino to verify alignment
Isabella asked about clashing HRV, Peyton will be running coordination model for HRV as well as EMT
HRV Embed sheets need to be sent to Basebuild, adam mentioned
Still waiting on word a
7/27/2026 - Adam said Zach gave him the low down on the CIA, it is not a contractual document, it was sebastian telling faith to do it
1100amLEB - BIM/FAB Weekly Meeting
Reece Fauble
I missed meeting for Facility water with TXE
Listend to transcript
Meeting is to kick off discussions between bim and fab
Reece has packages setup for all buildings
has spools on packages for leb10 and leb1
he needs leed times
Storage will be an issue
No packages for sheet metal yet
Needs an idea from each package time frame and for storage
Ean says Ron can answer better next week
6 weeks before field install date, standard minimum
7/27/2026 - Cancelled
1200pmTXE-Region3 Coordination Meeting
Jade B Lowe (Hensel Phelps)
Jade is in charge of Region 3
Kyle cummins is in charge of site
Filll out contact excel sheet, put bim lead and project manager
Kyle - LOD 450 project, all installed elements are modeled, then asbuilts are fed back in to model
Indicate in the model some where that the asbuilt has been applied and model has been adjusted
6/16/2026 - Decided not to go to this one since its Region 3, TXE6,7 undergound
7/21/2026 - Missed meeting since they are covering base build
7/28/2026 - Missed meeting since they are covering base build
07/29/26 - WED (+9 Meetings)
630amEMT - Daily BIM Alignment
Abe Hernandez
Scott gave an overall for the MES/HAC foot clash
Melanie Working through EMT Models, links needed repathed
Go Through EMT1 and EMT2 and make sure MES, TW and MP content are good
IF good, push to Revizto
Also check MSA/FSHAC Piping
EMT Does have IFC's for Base Build, Scott showed them yesteday, I coulda swore we didn't have any sheets, prob thinking of HRV
7/22/2026 - Ryan says Mortenson is on the verge of issue stop work order with Meta due to electrical incompetetance
Neema says stub ups need to be slurried, underground pipes need to be verified for undergound thrust and that passive soil will be sufficient
Above ground thrust will be satisfied by slurry and surrounding footers
MC Dean Bridged files
Danton Wein with MC Dean
MDI has steel and skids, fabrication
ENG has electrical equipment
They both have all links turned on, these need turned off
mcd plan for trench moving, not relating to Southland
Southland
MP Model connections to FW UG Stub ups
Need CWC Bypass, will they be included in the CWC Model we already have or in a separate above ground model?
Ben verified the models are good
Ben then went to stub ups and neema took the convo to RFI something, I said we were going to take a first pass at matching CWC Stub ups
Neema was talking about some kind of trnech shit moving that didn’t apply
7/15/2026 - Adam CWC said no update on the bypass for CWC
7/22/2026 - Talked FWM and MCUP issues mainly
Eli from Colonial was present
Neema says they need to move FW Stup ups away from footer about 5"
I mentioned they need to hit the critical North south dimension of 6'-1 5/8" to match the mes skid line, but we can match whatever movement they do east and west
Ben and Neema both pointed out CWC can rotate bypass valve to the front, one of the bypasses was already rotated this direction, CWC started to fight back a little bit
This means CW Will need to move their stub ups to get out of way of footers
Danton affirmed that the 2 MDC ENG and MCD MDI Models are the current models for the FSHAC
Storefont issues
7/29/2026 - Ben gave dimesnions of shift in DCB2, around 4" toward wall, and will rotate valve
Ben said they are doing things in the field to make sure they hit the 6' - 1 5/8"
Once the shift is completed in DCB2, Ben will ping us
800amTXE/LEB Weekly Internal BIM Coordination | Meeting-Join | Microsoft Teams
Jay Keiser - FTI
LEB10 RO Hitting Column
LEB10 FLEX HOSE on 8" Flush skid hitting column, need to clear clashes
talked about email I sent about a list of which models to use for which trades as far as Walls, Wall Panels, Electrical, Arch, Structural etc
Kyle said he was still working on that
John Cowhey is asking about Lugs on the MES
I will chase this down, find who responded Johns email and start there
Robert Cheek responded on Monday saying he would get the answer same day, still waiting
I told Jay we are currently working through shop drawings and spools, while we are doing those we are paying attention to clashes and working through the clashes
I Brought up the FW underground being off and that we will be scanning and verifying CIA POC's, Should be doing this within a week
5/27/2026 - I BROUGHT UP LEB1 COORDINATING WITH CRIDER NO MODEL, USING HDR FOR UNDERGROUND COORDINATION
JAY BROUGHT UP TXE10 ANCHOR CLASH WITH WALL, ADAM SENT EMAIL ASKING ABOUT IT, SOMEONE SAID THEY WERE CHANGING WALL IN A EMAIL RESPONSE, ADAM REQUESTED MEETING, NO ONE RESPONDED
JAY ADDED THIS AS AN ACTION ITEM
EMMA SENT EMAIL REQUESTING CLARIFICATION, TRISTEN WAS CONFUSED
LUKE SAID HE WILL DISCUSS IN HIS MEETING WITH MORTENSON
JAY ADDED THIS AS AN ACTION ITEM
6/3/2026 - New LEB Mech and Plumbing meeting on Wed, John and Reece involved, going over FW stub up locations and F/F water gallery connections
Informed John of Convos with Greg to coordinate wall install with coring of anchor plate holes
Told Jay/John, Lance Holmes is coordinating with other trades on fix for LEB UG FW stubups not hitting POC points or dimensions
6/10/2026 - Verify Span models work on LEB10, 1, 2
6/17/2026 - Checked LEB1, Span_SS model is still only showing Labeled grids, no steel in revit linked model, 2models, same dates, different version, latest verison wont load, gives error
Bring up Walbringer as new MP contractor on LEB6, sent email out with dimension sheets for someone to get them the information
Coordination Sign off
Jay gave links to Turner and HP sign off locations
Clash Review
Jay said he will go through and filter out white noise, setup a meeting to over others. I told him whenever he wants and I will be there
Friday 6/19/22 9am
6/24/2026 - Check with Adam if he verified the lastest info from Crider lining up ug, LEB10
Check LEB1 model HDR Underground lining up with Model, We are lined up with HELM Bypass on LEB10
Luke will get with LEB and Turner for Verifying CIA Points
Louis will get with TXE and HP for Verifying CIA points
LEB6 - MP Model misalignment, I checked the Turner NWD, they are using a FTI Container that may have a misaligned MP NWC
I Put together and new NWD with current NWCs Available and everything lined up correctly
LEB, DCW Drops, Get with John to find out which way they want to go, then follow up with HDR and Helm and Waldinger
I sent John Rhee an email requesting update
7/1/2026 - Jay brought up LEB6 issue I emailed, I told them HDR still needs to update their pipe stup ups, they fixed the grid though
I brought up CIA from other GCs since they were talking about FTI Scanning HP elements, if HP didn't provide documented points what is FTI going to shoot?
Justin said yeah, it is a meta requirement but meta hasn’t really lined out what exactly is required
I told them FTI did such a great job on the document and spearheading it, I was wondering if the other GCs also maintained this document since we are connecting to systems from other trades
Jay follow up with Kyle on HP for going through HP clashing directly, can we access them, create issues, clear?
7/8/2026 - Brought up LEB10 turner models, stay with NWC, even though they have
Advised that I have moved our DCW POCs to match HELM and HDR
Advised of TXE10 Scanning schedule starting tomorrow
Waiting on Patrick B for response on HAC FCU orientation
7/15/2026 - Told Jay, I havent verified Turners FTI Container files are updated this week
TXE Told Jay, Adam noticed the Fan Coils may need rotated 180 degrees, sent email, waiting on Patrick B to look at it
Verify Bypass submittals to FTI for John Cowhey
Check LEB6 FTI Container updated
7/22/2026 - Patrick sent out email saying txe10 FCUs have been reorientated based on Adams email, he will be going to other buildings
John is still waiting for Submittal for EOL HAC Bypass, he is talking to Jacob onsite, need submittal approved and start releasing fab on those
Underground conduit was missed for TWMU Skids, they need to be run overhead, it’s a substantial amount of conduit
Sent John, Justin, Jay the Control Point Map
Told Jay I would do a fly through on Leb10, LEB2 and LEB6 checking for FTI Container alignment
Do we need to do an official submittal for the Dimensions for UG Stub ups and Bypass elevations?
Start using ACC Issues module for tthings like LEB10 Crider stub ups being off
7/29/2026 - John says, he still hasn’t received the Bypass Submittal
I told Jay I would send LEB Control point email from Richard Lopez
I said I would get with Jacob and Keylan to make sure he gets it
I gave low down of what we are scanning, including CP's, what happened with CSV from Kyle
I asked if FTI was doing Trimble next week, john said yes and they will check certain things
I explained how the columns were off, I thought HP should be verifying columns and grid lines, walls may be off
830amMCD + SOUTHLAND + TATE/FSHAC Coordination Check IN
Updates to MSA piping completed and pushed to ACC, cantilever supports, support changes
RFI 146, MOFE OFE
MES PIPING ALIGNMENT WITH MSA Alignment is different
04 MES skid, make sure MSA is aligning with MES 04 skid based on this RFI
MAKE sure MSA SKUS are updated
Make sure MES Skid 04 includes this RFI
Give Arthur and team updated info so they can verify steel is appropriate
Darrin says HRV1 and HRV2 Clashing models are complete
Running clashing through Navis, our VDC Team should be able to get access
I asked about Southland being able to view their clashes
Darrin said they were having disccussions about moving their clashing to ACC Model Coordination
I said we would touch base and peyton is spearing heading our clashing coordination to see what direction we will go
Scott Brought up HAC Alignment and things not centered
Arthur said they will check it out
We need to make sure the SOUTHLAND MES Model is bridged to MCDEAN so they can use that model
Follow up with Melanie, heath
I sent out a clarifying email that since the mes models are host on MCDean, they don’t need bridge. I told them the models we are using for coordination
7/29/2026 - Isabella said she talked to Tom Chirdon and Tom Maxwell, couldn’t determine where RFI 146 was, white its not in programmatic forma
Arthur wants to do same time tomorrow with USCE and Tom Chirdon so we can all get on the same page
It will be Wade from USCE
Isabella asked about clashing and updating steel model
Update tomorrow
Need hac model completed before we can finalize placement of Fan Coils
Peyton is talking to Darrin about seperating the models for clash coordination
What DCIS is it? 4374, is what this write up refers to
Arthur said he will get with meta and make sure it gets escalated to Meta so it gets handled on a programmatic level
900amLightning HRV - Internal Detailing Meeting
Isabella Vesce Rivera
Bridged files from Colonial
Isabella will bring up we need bridged file
I requested to sit on base build coordination meetings with DPR/ Colonial
Adam wants form to access DPR, he will give it to all
Tomas maxell and chirdon talking to structural engineer about eliminating the middle anchor on DCB100
Adam added couplings to MSA that will allevaite having to add welds for field install
Packages were created in stratus, should be able to get dates by EOW
MSA to HAC needs some couplings removed
Depending on if Ryan can put the couplings on GMP Field because Fab is hard bid
Adam will remove from on site scope, per Ryan
Adam Dial in how we want to name NWS MSA for spool sheets
Adam wants to name them so they are more in line with the stratus packing naming
Deliverables -
Sign off and install schedule
7/15/2026
Waiting on Corbon to yay or nay the middle small anchor
MC Dean is still making adj to hac steel, they did state it shouldn't affect any of our content, ian is supposed to be complete on 9/24
Adam is supposed to put couplings in MSA to stop field weld
Need this update in stratus per Ean
All packages are created in Stratus with Dates
Get with stone and scott about getting FCU in the HAC for HRV
Southland will be running our own Clash Coordination
MC Dean provides a NWC, but we are choosing to use DPRs NWD in our own Model Coordination due to being more current and includes more trades
Keith, Melanie and Peyton will be putting this together
Melanie says not to clash with their NWD, not good
Either we will use DPR Forma Model coordination, if not available, we will ask if we can bridge their models directly to our forma to run our own Model Coordination and clashes
DCB100 NWS1/4 signoff 9/22
DCB100 NWS2/3 signoff 9/29
7/22/2026
Gave run down to Thomas and Ryan of Colonial Stub ups
Trhomas says there will be a middle anchor
Peyton will be leading the Coordnation Model and space, will be issueing clashes
Will be running clashes today
Ryan did sent out an email to DPR and colonial web regarding the UG FW CWC Dim sheet showing critical dimensions
7/29/2026
Explained the moving of embed to get out of wall, will move all embed together but will cause actual anchor to shift on the embed placement
1000amBIM Round Up | Meeting-Join | Microsoft Teams
Michael Kolnik
Jeremy says they are supposed to be scanning in a week or 2
Jeremy needs Floor drain locations from Cerris so they know exactly where they land, Need to get with Patrick Marshall at Cerris and see if we can get some shop drawings.
6/3/2026 - MICHAEL ASKED ABOUT CURTIS GIVING HIM AN ORDER REQUEST THAT HE THOUGHT WAS SUPPOSED TO BE FOR FLUSH SKIDS
IT HAD 16X14 TEES, 14" 90S, 8" STAINLESS CAPS
HE DIDN’T KNOW WHERE THESE TEES CAME FROM
I TOLD HIM THEY WERE FOR THE MES LOOPS, NOT THE SKIDS
THE 14" 90S WERE PROBABLY FOR THE FLUSH SPOOL TO CONNECT TO THE FLEX SKID
MICHAEL SAID HE CANT GET THEM IN TIME, SIAD HE IS LOOKING AT DOING A MATERIAL SUBSTITUTE REQUEST, I SAID IT ASAP AND PUT CURTIS IN THE LOOP ON IT
6/10/2026 - Michael said he is having a meeting Friday about FW scanning and fix for fw off dims, with HP, FTI, Scanners,
6/17/2026 - Adam brought up supports, new design doesn't leave room for any adjustments
Michael says scanning will be around 7/1, if UG is off, michael says we will have to fix and charge HP
Are we going to have 8 unique supports
Paul says we will have to do it in the field
Paul and Michael agreed a new stand with Trapeze hangers will work, adam wil resubmit
Michael has order all fittings and pipe for TXE10 and TXE2 for MES loops
Region 1 is staying with 1 flush skid
2 flushes, twice as long, michael said it doesn’t schedule, not enough time for 2 flushes
6/22/2026 - Adam is telling Michael they need to create packages in stratus for how they want hac jumpers, bypasses split up
Adam is proposing a fabrication kick off meeting with Ryan and Curtis to get everyone on board
Micheal needs 8 weeks, Curtis needs 3 weeks for example
Jacob says curtis wants packages created by cost codes, but we are talking about splitting them by areas
Paul says give tom a curtisy that we are rele
Need to update the 6" flush skid and put a bleed olet on the return vertical
Paul says hes not sure where the Bypasses are as far as UG Bypass
Pual not sure when production will start for Near site, installing bypasses on HAC on near site
He will then put the spools in the appropriate package
6/30/2026 - Paul says caps are needed on MES TW and FW Ports, they can put drains on if they want
No drains on jumpers
Curtis is shipping spools to SOK
Curtis said no drains on caps, just need caps
Michael, going over spools
No Drains on jumpers
Look at TXE1-01-FWR-JMP-001, showing Flex coupling, need quick vic
Michael Ordered 16x14 tees, make sure we stayed with those and didn't update to full 16" to flush skid
7/8/2026 - Michael and Paul requested 6" and 14" Flush spools to be stainless
Sent info to Tom and Stefan, Tom says no, the flushing chemicals will clean it
7/15/2026 - Jacob says curtis put dates a month earlier than whats listed
I Told them Curtis is the one who would determine if we need to change material, stick with what he says, move the dates to 6 before install date, and get that request out, if they can't meet that, curtis will decided the next direction, weld?
Looked over installed bypasses at TXE10, everthing is off.
The Anchor plate was 5/16" off and into wall space on ML1 area
7/22/2026 - No Meeting, no popup, no cancellation
1030amEMT - Mortenson BIM Coordination Meeting
Nate Black (Mortenson)
UCO3 Loop OH Coordiantion Sign off 7/24
Nate pointed to coordination models that will b
Scott asked about the container models and who is creating it
nate said if we can push our models to revizto directly, that would be great
Heath said he can do this
Need to notify heath when they
7/22/2026 - Went over Drone Fly through
FCW is being dropped in EMT2
Skyline safety share
Alex Eismore, mental health
7/22/2026 - Just covered based build items
1130amEMT - Mortenson BIM Component Call
Nate Black (Mortenson)
7/15/2026 - Cancelled
7/22/2026 - Meeting is still listed in Calendar, mainly Southland BIM team in invite
Go over UCO3 and EMT2 Wrong Locations on Base Build and Lightning Scope
ON Key plan the A sectors and B sectors need to be swapped
Heith said he missed it when he set it up, takes full responsibility
We havent' issues any sheets yet for EMT
07/30/26 - THU (+8 Meetings)
630amEMT - Daily BIM Alignment
Abe Hernandez
Scott gave an overall for the MES/HAC foot clash
Melanie Working through EMT Models, links needed repathed
Go Through EMT1 and EMT2 and make sure MES, TW and MP content are good
IF good, push to Revizto
Also check MSA/FSHAC Piping
EMT Does have IFC's for Base Build, Scott showed them yesteday, I coulda swore we didn't have any sheets, prob thinking of HRV
7/16/2026 - Melanie says our MP model doesn’t line up with Eng Model, we are using Lightning Shared Coordinates, Eng is using ETM100
Abe - Attached Sign off schedule to summary email, have content populated and coordinated ahead of signoff dates highlighted in RED, these dates line up with Mortenson
I told her our content, mes content lines up in revizto, if you change anything, it will no longer line up
Download arch model, link our models in and see who lines up
She says archs did change the g datum model a while back, she had to repath it and that’s when things stopped lining up correctly
7/17/2026 - Cancelled
7/20/2026 - Cancelled
7/22/2026 - Ryan says Mortenson is on the verge of issue stop work order with Meta due to electrical incompetetance
7/23/2026 - Cancelled
7/30/2026 - Cancelled
630-710amLEB | BIM | Faith x Turner
Luke Jost - Joe Dorinsville
Edwin Perez from Turner hosted
5/14/26 - - Joe Brought up the access panels for Flush system, asked about rating, I would have to check submittals to verify. Me and Lance holmes informed joe the flush systems are temporary, once done, they get removed and the access panel stay
Anna said they were aware, but not the finalized locations, now they will be going through Valley for engineering, excel engineering to make sure everything is accounted for, engineered
Talked to Stefan, we are not providing the Access Panel, its GC2 wall, they are providing it
I need to check on RO system, ACCess panel and it looks like location may be borked
Scott asked about sign offs for lighting scope to base build duct connections, Joe said they havent covered it, sign off is around end of June. They will be circling back to loop area not that they have certain paperwork available
Joe said any issue can be brought up at anytime
5/21/265 - No John Rhee, Brent, Thomas Holler, NO PM TEAM
They went over stud wall model, Lance asking about raceways for security and bus ducts
5/28/2026 - They went over electrical stuff, skid placement, wall leave outs
Turner wants a meeting with Helm and Southland to go over Wall penetrations
Joe D discussed Span model naming, keeping them the same and consistant.
Will need to relink LEB Span models since they have new models with Nucor suffix
6/4/2026 - Eduardo Ibanez brought up Status of Facility Water Stubups asking if Verification of Stubups with Mortenson needed. Had Crider submitted? Lance was saying Ryan would have this info and asking if Ryan was in meeting
NO PM Team present
I sent PM Team a summary email
I explained, Ryan used HDR model for coordination, I worked with HDR to get everything line up, we provided dimensions, everyone agreed to them, now stub ups are off, Lance Resposnded to John Rhees email asking what is being done
I said we need to start having meeting to go over this issue since its so critical
Luke Jost told eduardo to add an action item for this and lance said he will head this off
6/11/2026 - I brought up the FW UG being off again, told the group Ben Kozel with crider said they were backfilling in layers and trying to get the stub ups on the POC/CIA points
Overhead Signoff is schedule for 6/30
Scott asked if it was entire building for NWB, Joe says yes
Joe Brought up IMP walls changing to Framed walls, Anna? Said it was still being worked on
Verify LEB10 POC For DCW
Verify DCW POCs line up with CIA
Lance said they are also providing a hose connection for discharge, I stated they are using the FLOOR Drains in center of gallery for discharge, Adam corrected me saying John has requested different discharge points. Wouldn've been nice to know.
Someone asked about the Flex piping from the 8" skid hitting the column, I told them it was flex pipe and temporary, that it will bend around the column
Vent in 6-19x6-D, adam told them to put in between MES Skid
Waldinger is doing the bypass on LEB6
Building 6 MES loops are showing misalignment with Waldinger Bypass
NO PM Team present
I said I would like it added to this meetings notes, Joe Dorinsville basically shut it down, saying it was a field issue
I said it was our issue also since we are constantly being asked to do overlays, which were happy to help any way we can, but this was more of a helm situation since they are the responsible party to connect to the UG and provide us with accurate points of contact according to the CIA
Joe reiterated it was a field issue
6/18/2026 - Edwin Perez is showing Verification on stub ups w mortneson needed. Pending Submittal. Eng. Drawings to be submitted - Crider and Crider. He said this is still on going
Edwins model view still shows MP Shifted to plan right, access panels were to the right of the wall they are supposed to be in
LEB6 Arch Coordination model is showing everyhting off, MES Skid not lining up, mp is to the right, access panels are to the right of the walls they are supposed to be in.
LEB10, checked with Joe D, things line up there.
6/25/2026 - Joe, Greg, Luke Long, Greg went over Electrical coordination
I sent email to PM Team, no one was present
Eduardo Ibanez brought up Status of Facility Water Stubups asking if Verification of Stubups with Mortenson needed. Had Crider submitted? He brought this up again. I explained again that we provided dimensions for LEB10 and LEB1 to Mortensen, Crider and HDR, they all agreed
I told group that I also emailed these dimensions to Waldinger for Region 2, but havent received any comments or response from anyone.
Scott asked about tracking for signoff on 6/30, eduardo said yes
Luke Jost asked about LEB10 Embeds to make sure they are getting tracked by turner
Edwin Perez asked about Waldinger Bypass and alignment to SI MES Loop Connection
I told Edwin Perez I provided poc dimensions and elevations, but havent received any response
Edwin said he will bring up in next BIM meeting
7/2/2026 - Get with john as far as who is providing what cam lock adapt for fip drops
Lance Holman also provided additional dishcharges (Drains) for Flush/ fill per john
They showed model, HDR DWC Drops are on face of column, I told group IFC shows they are on Web side, HDR Model doesn’t match HDR IFCs
John Rhee is communicating changes from model to FTI, Turner that they are not telling us, Discharge drains, DCW changes
The only reason I found out was because of the meeting flythrough, our pocs were on other side of corridor
John fucking totally ignored our information and didn't relay any information
I missed the HDR IFCs showing the drops on the plan south side of corridor
I explained LEB6 model misalignment was fixed, publishing issue, I will double check mondays model after the Saturday auto publish
I told group about the FW UG Dimension sheet that has been distributed multiple times and it details where the FW UG stubs are supposed to be ever since LEB1
I will double check LEB2 misalignment
They showed LEB6 and the 8" skids were into the columns again
I explained the deep dive I did last week, it shows everything aligned. There are issues with the FTI Container model that Turner is using for coordination
7/9/2026 - Setup LEB2 SI MP View off turner LEB2 Overall Building NWD, Crider is still off at Grid 2-50/ 2-D
Eduardo Ibanez hosted
LEB10
All Content on slab will be created in a file, progress is ongoing. Jay Asked what does this entail? Above Slab content?
LEB6
Our MP is still out of alignment in Turner LEB6 Overall Building.nwd, but Joe pulled in a recent nwd and it showed the FTI Container inside the Overall nwd is off
With joes pulled in NWD that shows us and waldinger aligned, Crider was still off around 8-10"
SI Duct and Waldinger do not align
Justin verified that Turner is using NWC files NOT the revit
Southland MP looks good
Southland MP model is still a little older, but non-critical
7/16/2026 - Joe D brought up some issue about control joints at LEB10, luke jost and jay kaiser will update as necessary
7/22/2026 - Joe D brought up control joint proximity to MP anchors, they scooted 1 at grid 29ish, no TW Skid.
Checking Coord Space at LEB I see Stratus models getting exported again on 7/17, that was last Friday
The only MP model available is from april, what the fuck is going on with this fucking shit
The LBE10 Publish settings were set to stratus, talked to heath, he showed adam was the last one to do it. Adam said he didn’t know had to change settings back
Lance suggested a meeting with FTI and Southland to get power to TW Skids, Lance Long said they have a meeting setup with FTI Tomorrow, looking at junction box on the wall
Jay K at FTI created an issue with Crider Facility Water Alignment and was trying to add crider watchers, he can only add FTI watchers.
Joe D told him to use Triston with Helm, Mitch with Waldinger
Mitch with Waldinger said it looks like its going to work out with aligning their Bypasses with Southland MP
Jay K brought up container models having outdated southland models
Joe D says its tough to say when the FTI container was reloaded. The last update they show was july 13th, 10 days ago
I rbought up the TW Skids on each end of the building also to check, they have anchors also
I stated I found a recommendaiton of 3" distance between an anchor and a sawcut or concrete joint
7/30/2026 - Jay brought up getting control points from Turner
Jay brought up missing MES/ TW skids from LEB1, LEB2 FTI Container, the MP content was aligned
830amMCD + SOUTHLAND + TATE/FSHAC Coordination Check IN
Updates to MSA piping completed and pushed to ACC, cantilever supports, support changes
RFI 146, MOFE OFE
MES PIPING ALIGNMENT WITH MSA Alignment is different
04 MES skid, make sure MSA is aligning with MES 04 skid based on this RFI
MAKE sure MSA SKUS are updated
Make sure MES Skid 04 includes this RFI
Give Arthur and team updated info so they can verify steel is appropriate
Darrin says HRV1 and HRV2 Clashing models are complete
Running clashing through Navis, our VDC Team should be able to get access
I asked about Southland being able to view their clashes
Darrin said they were having disccussions about moving their clashing to ACC Model Coordination
I said we would touch base and peyton is spearing heading our clashing coordination to see what direction we will go
Scott Brought up HAC Alignment and things not centered
Arthur said they will check it out
We need to make sure the SOUTHLAND MES Model is bridged to MCDEAN so they can use that model
Follow up with Melanie, heath
I sent out a clarifying email that since the mes models are host on MCDean, they don’t need bridge. I told them the models we are using for coordination
7/29/2026 - Isabella said she talked to Tom Chirdon and Tom Maxwell, couldn’t determine where RFI 146 was, white its not in programmatic forma
Arthur wants to do same time tomorrow with USCE and Tom Chirdon so we can all get on the same page
It will be Wade from USCE
Isabella asked about clashing and updating steel model
Update tomorrow
Need hac model completed before we can finalize placement of Fan Coils
Peyton is talking to Darrin about seperating the models for clash coordination
What DCIS is it? 4374, is what this write up refers to
Arthur said he will get with meta and make sure it gets escalated to Meta so it gets handled on a programmatic level
7/30/2026 - FCM Placement update, early next week for that
Updating 2nd family content
Darren and Doowoo, may have an federated model "Soon" according to Isabella
Arthur role is FSHAC designer, They brought on SJS to manage Coordination, Darren is project engineer, hes the one for Model coordination
Adam will be putting together snips that shows where we are at compared to rfi 146.
Isabella says the rfi was answered for UGS and they are looking at moving pipes to realign
Had to leave early to talk to carsen scanning at txe
930amLEB | BIM COORDINATION LEB2
Emma will no longer be on this project
Kaushal Bagdekar with Turner ran the meeting, saying who to contact for what, I asked if he could send an email with that info
They went over underground clashes
5/28/2026 - Tristen with helm verified he is using LEB1 dimensions for LEB 2 elevations and locaitons for FW
6/11/2026 - No PM Team
Went Over UG issues, concrete pads
6/18/2026 - Kaushal Bagdekar
Did a flythrough for LEB2 going over exterior sectionalizers
LEB-2_SPAN_SS.rvt, verifying during meeting that the model is good, Checked LEB2 SPAN_SS model, couldn’t load content, says cant link in NuCOR
NO Interior Walls and framing, Valley, Diogo or Ruth said they will get with valley
No Interior Meta Wall Panels
6/25/2026 - NO PM TEAM
They went over UG issues for LEB2
7/2/2026 - LEB2, Showed model where Helm, SI and Crider not aligned, #2070
LEB2 Building Overall actually has Crider model, showing misaligned
Grid 1-50, 1-D is the only spot where Crider is off looking at Turners LEB2_Building_Overall model only
Everything else is aligned, MP, Duct, Steel, Walls, no issues
Sent email showing misaligned concrete and crider stub ups at 2-50
LEB-SI-MP-LEB2-R25 model lined up identical to LEB2-Building-Overall
Didn't see new DCW POC valves, did I update LEB2
Did see FLUSH VENTS AND DRAINS, VENT ON 2-50 IS OFF
7/9/2026 - Sent Email to Joe, Jay, Edwin, Eduardo and Joe forwarded to Kaushal
Kaushal asked about flush skids in front of door ways, need to send them a time frame for flushing before equipment gets removed
Concrete elevations different at Gird 2-29 and 2-32
Crider stub ups off at 2-50/2-D
Added to chat
7/16/2026 - Sent email to Triston with Jay and Kaushal cc'd about Helm bypass flanges not aligning to SI MP Flanges throughout building
LEB2 looked like it aligned good
7/22/2026 - No southland issues covered
7/30/2026 - Just went over non-southland issues
I dropped for LEB Mortenson meeting at 1000am
1000 amLEB - BIM Coordination Meeting (Thu) | Meeting-Join | Microsoft Teams
Ryan Zoldan
LEB 6 due finalized next week
I requested a schedule from Ryan, he has the sign off, region schedule, I brought up a pull plan, be he says that will be through Turner
Mortensen is the Base build GC, why aren't they leading a pull plan schedule
John Rhee nor Brent were in this meeting
6/4/2026 - I brought up the LEB10 FW UG Stub ups totally missing the Dims, Ben Kozel was there and he stated they are bringing them back in to dimensions by backfilling a little and moving them, backfilling and moving them
He acknowledge that lance did contact him
6/11/2026 - Ben Kozel, said there were no issues that need to be talked about.
Richard lopez asked around the room for any issues regarding LEB10 or any others
NO PM Team
6/18/2026 - Richard Lopez Hosted, just asked for any issues with LEB10,1,2,3 Underground issues
Rantwiler asked when IWM for TXE10 was going to be signed off, Ethan says he will talke to kyle since they are not really split out
6/25/2026 - Going over LEB7,8
Ryan brought up LEB6, HDR model is not lining up with the Dimensions provided by SI
Ryan henderson said he will follow up
Ryan said we have all agreed to follow these dimesions, I added that I have distrubuted that dimesion sheet ot Waldinger and explained everything, but havent received a response yet
Ryan brought up LEB6, HDR model is not lining up and my email I sent out
I updated, still waiting for HDR to align the stubups
Ryan said Crider is using civil 3d, but we can work it out to actually use their model for coordination and linking in so I don't have to use HDR
7/9/2026 - No issues to cover, they went over UG clashing for elect, sanitary
7/23/2026 - Richard asked Triston about any alingment issues, he was good
Ben said LEB6 stil had some very minor HDR alignment issues to on udergoung
7/30/2026 - Bend said LEB6 looked good
I said we republished LEB6, there was some extra content we had to remove
TXE1 looks good for the loop area sign off next week
Same with TXE2
6/4/2026 - Own B ran the meeting going over TXE1 and 2
6/11/2026 - Owen B, says TXE10 Loop for sign off
TXE2 Core scheduled for next week
TXE10 AB Datahall and Loop are signed off
TXE3 Alan lopez is running region 2 for signe off
TXE2 Loop and AB South sign off
issue 2602 - Cerris Vent in corner is clashing with Technical water, Rantwiler is saying they don’t have our model, I told them our model has been there for 6 months, the fact that HP is viewing it, means the model is available. If it’s a bridging issue we will help Cerris work it out
Trevor said he will get with rantwiler and get the model bridged, they will offset that vent around our TW Piping
They made comments about the TW skid being so close to the FW valves. Its been this way for over 6 months. Trevor also stated the vent will need an accessible cleanout
6/25/2026 - They just went over IWM and specific Electrical clashes
7/9/2026 - TXE 2 all docs are out, all sign offs are out
TXE1, 2 sign offs left
DHCD 2 weeks from now
7/22/2026 - No Issues
1130amLightning HRV - Global BIM Coordination Meeting
Isabella Vesce Rivera (SI)
Is there a coordination model we get access to? Revizto? Navis?
Get input on HDR Mockup I made for FW UG Stubup, Bypass and MES Loop connections
Colonial was trying to align to SI Desing model, that was all that was available for the bridging
Seth Blizzard says they arent obligated to meet our POC's, they follow the ARUP design. ARUP did let them know they are contracted to meet our POC's
Curtis Robbins said he just needs to click a button to enable the bridging to our actual Coordination Models
Seth started making comments about use being able to shift our pipes 3", I told them theres a lot more going on that what they were showing with our Engineered anchors, flush connections, MES and TWMU skids and TW Piping, there isnt much forgiveness
Still don’t have access to bridged Colonial files
230pmTXE-FTI Weekly Sync Meeting
Luke Justice
Luke was asking about scanning at TXE10, He said coordinate with Greg Hueramo, he will be setting up an origination email
I told luke they need to have all areas ready for scanning since the team cant be sent out every other day, reset up, etc
I asked for Control point map, he said get with Greg Hueramo
I explained to him what the scanning was
I told him they will need to add paul hernandex, jeremy miller and adam brown to email
John Cowhey said he has a 1 pager for Site orientation which will be 8 hours
They will be enforcing badging within the next few weeks. No badge no access, Visitor badges will be available but not allowed to work
Luke will put together a schedule for orientation
11/17/26 - is new date for 0 prep according to John Cowhey
Forward FW off email to Luke, original email was sent out 4/17. I resent to Luke Justice
I told him Jeff Balthrop was involved a few weeks back
Send Luke Discrepancy on Anchor locations with BZI Wall panels, NWCs etc from Adam email, Adam email 5/5, TXE Adam email 5/6
Verify anchors at TXE and LEB, check they've been submitted to FTI
Send notice to John Cowhey, luke justice
They asked when Southland is looking at manning the site, jeremy informed them no PM team were available at this time to answer
new schedule coming out Friday
Got with michael kolnik, he sent out Shop Drawing submittal request to Eric Boehger
5/28/2026 - Loop Keylan and Michael into the Anchor clash info and meeting for Friday
Luke says bypass are fabbed, not installed will be installed next week, sent out email to everyone, paul, jeremy, michael
Need to coordinate orientation, drug testing
Day zero schedule? Luke said he was supposed to get last Friday, not seeing anything new
Luke showed the Faith TXE Anchor Shop Drawing submittals, they are only for the TXE10,1,2 Plates don’t know why it has TXE3 on the label
Not showing any Shop drawing embed submittal info
NO PM Management was present, Keylan Rollins was for engineering
6/4/2026 - Luke Cancelled at 741am, Got DAMN MAN!!!!
6/11/2026 - Luke Cancelled at 741am, Got DAMN MAN!!!!
6/18/2026 - Luke asked about Issues, I was explaining a summary of Greg Heuromos meeting, then Michael Kolnik was there! It was nice
6/25/2026 - Michael says greg told him the bypass will be complete on 6/7, michael has scanning scheduled for 6/6
Jason with FTI will use truck to help scanning move around job
Scanners will need badges, they can be escorted according to michael who talked to security
Michael says no one onsite yet, they are on first of kind, michael and jacob did get badged
FTI does have a superintendant and a couple of upper management onsite
Fully mobilized first week of July
Luis says they have been requesting a lot of BIM information, Asbuilts, trench information, etc
Luke says a laser just got done for the Trench
Alec Harpel says first half of txe10 was scanned, still waiting for coordinates
Need FW stub ups, grounding whips and trenches
Luis is asking for points for the finish floor to verify elevation/flatness
TXE1 slab just started pouring last week, according to Luke
Micahel said they wont have water into the building, they need to truck it in and provide the minimum GPM with 3" connection
TXE10 shows 3" main with 3" drops
TXE1 shows 4" main with 3" drops
7/2/2026 - Luke Justice cancelled
7/9/2026 - Luke Justice cancelled
7/16/2026 - Keylan gave run down of Scanning and photos, scanning completed
Jacob stated carsen is locating revit files and uploading info
Should get scans by afternoon
7/23/2026 - Luke asked about Control points, I told him we did get the PDF from Shay with coordinates and CP labels
I can use this to get the CPs into the model
I informed them that Justin Jenkins was looking for Dimensional data from CP to a known point. I said I would follow up with Justin
Sent email to Justin Jenkins with CP map and letting him know they didn’t understand the dimensional data from CP to Known point
7/30/2026 - Russell Faulkner, wall of destinys will be completed tomorrow
I told luke about missing elevations on CPs in building on the map, also identifiers were getting wiped out, couldn't tell which CP was which
Told Luke thye finished scanning yesterday, should be able to put everything together for the meeting with Jake Williams on Monday
07/31/26 - FRI (+4 Meetings)
630amEMT - Daily BIM Alignment
Abe Hernandez
Scott gave an overall for the MES/HAC foot clash
Melanie Working through EMT Models, links needed repathed
Go Through EMT1 and EMT2 and make sure MES, TW and MP content are good
IF good, push to Revizto
Also check MSA/FSHAC Piping
EMT Does have IFC's for Base Build, Scott showed them yesteday, I coulda swore we didn't have any sheets, prob thinking of HRV
7/16/2026 - Melanie says our MP model doesn’t line up with Eng Model, we are using Lightning Shared Coordinates, Eng is using ETM100
Abe - Attached Sign off schedule to summary email, have content populated and coordinated ahead of signoff dates highlighted in RED, these dates line up with Mortenson
I told her our content, mes content lines up in revizto, if you change anything, it will no longer line up
Download arch model, link our models in and see who lines up
She says archs did change the g datum model a while back, she had to repath it and that’s when things stopped lining up correctly
7/17/2026 - Cancelled
7/22/2026 - Abe
Monday meeting will be clash review
Need to send base build mortenson meetings, nevermind scott interuppted telling abe to go straight to GC1 for invite
Told Abe all mechanical piping for MES is populated in all buildings, EMT1 and EMT2 need to be aligned, sent Nate black email informing him Design models for Mechanical pipe no longer needed
FSHAC Piping is included in FSHAC Model
I informed abe the Mechanical hac and msa piping is part of the FSHAC model, not the MP model
Melanie brought up mutliple instances of pipe, looks like there are 2 uco3 basebuild MP models of southland, 1 from nicole, 1 from heath
700amNWS Fill Flush Plan
Adam Brown
Stefan says minimum requiirement is 3ft per sec, 5-8 FPS is the sweet spot, 14" skid - 4600 GPH
Phil says the deliverables is in 855
Stefan Says 3, 14" Skids, (11) TW and (11) FW Skids
Need to design new connectors for TW and FW skids to NWS MES
Adam msg Tom atbout getting Hi Rez model, tom said waiitng on Structural approvals, 4-6 weeks
Stefan says Paul wants an RO Tank with pump, RO Skid fills tank, Tank and Pump fill TW
Try to use 1 RO Skid for NWS and Datahall
1000am7/31/26 - TXE10 Trimble Follow UP - Adam Brown
1100amMNT West Piping Detailing Meeting
Adam Brown
Went over MW Piping Presentation Guide Power Point
Will go over ACC Publish and Review next week
7/31/2026 - Cancelled
7/20/26 - 7/26/26
07/20/26 - MON (+4 Meetings)
630amEMT - Daily BIM Alignment
Abe Hernandez
Scott gave an overall for the MES/HAC foot clash
Melanie Working through EMT Models, links needed repathed
Go Through EMT1 and EMT2 and make sure MES, TW and MP content are good
IF good, push to Revizto
Also check MSA/FSHAC Piping
EMT Does have IFC's for Base Build, Scott showed them yesteday, I coulda swore we didn't have any sheets, prob thinking of HRV
7/16/2026 - Melanie says our MP model doesn’t line up with Eng Model, we are using Lightning Shared Coordinates, Eng is using ETM100
Abe - Attached Sign off schedule to summary email, have content populated and coordinated ahead of signoff dates highlighted in RED, these dates line up with Mortenson
I told her our content, mes content lines up in revizto, if you change anything, it will no longer line up
Download arch model, link our models in and see who lines up
She says archs did change the g datum model a while back, she had to repath it and that’s when things stopped lining up correctly
7/17/2026 - Cancelled
7/20/2026 - Cancelled
900amLightning TXE Staff Meeting | Meeting-Join | Microsoft Teams
Jacob Gelhousen
Will do scans after Cerris installs bypasses
6/1/2026 - Noel Nunez says Alehandro Chew will be safety manager
Michael said he sent TXE3 embeds along with PDF dimension in mid April
Doesn’t think TXE3 has been poured, think they are behind schedule
Says we havent been funded for Region 2, he is sending out embeds as needed
Michael asked what the question was about RO and TW, I said it was going over how to connect to the RO skid, from DCW and to TW MES
Michael asked if MES Loops were completed, adam said yes, he created new BOMs
Michael said his goal is to get everything ordered
Michale Paul said they thought the walls weren't going to be in until they could do anchor
They said that was what was agreed to
6/8/2026 - Michael said they had a PM Coins Mandatory meeting and couldn't host the meeting
6/15/2026 - Chris Moss came on board from TSMC, Pipe fitter, GF
Jose Alejandro Chew, new Safety Manager for TXE
6/22/2026 - Shop drawings (Engineer Drawings) looking at submittal on Frid, 6/26
6/29/2026 - Keylan Cancelled
7/6/2026 - Carson will scan on Thursday
7/13/2026 - Scans on TXE10 complete, should have done this week, EOW
Jacob will be pulling field measurements of FW Stub ups
Adam will overlay scans to see how they match up with our Stub Ups
SOK will be starting next week, 27th will have more setup covered
7/16/2026 - Zach wants scanning sent back out, scan off control points, need to get CPs from Greg, put in model, talk to carson to see what they need from us
Control points were requested on 6/12 meeting with Greg H, it was stated they would be sent to Michal and James Homrighausen
I also asked for control points from Luke Justice on 5/21, he said he would get with Greg H.
They made it out like it was detailing fault they scanned without using control points
Paul asked how soon I can get the points into model, I said immediately, but Im not sure scanning needs anything from us, they may input control points into the rcap software maually but we will have it the model if they need it
1130amMW Detailing Weekly Meeting
6/29/2026 - Marshall Cancelled
7/13/2026 - Missed, I thought it was cancelled
7/20/2026 - Armondo party on Friday
De Le Cruz tips and tricks, Title Blocks
1200pmEMT BIM Look Ahead Meeting
Nate Black (Mortensen)
UCO3 OH Signoff 7/24
Went over drone map, EMT1 and 2 have UG FW
Went over sign off schedule
Showed Marcos Revizto Clash Workflow
Showed UCO3 Loop OH
7/20/2026 - Went over drone view of jobsite
Joseie with delta went over heat safety
no PM Team
Got UCO3 sign off for OH on 7/24
07/21/26 - TUE (+7 Meetings)
630amEMT - Lightning BIM Weekly Coordination
Abe Hernandez
Printed IFC Addendum 1
Scott showed Mortenson schedule 7/6
Peyton Coordination Model - Meeting with Heath, model is setup, need to get heath input
Using forma coordination module for clash detection
Cupertino says they are fine using the Forma module
Ryan - wants the model defined as to which one to use and clash with for Cupertino
Scott says he is on it
I let abe know that the MES and MP constructability models are now in the Revizto publish
He told Cupertino they can use that
Scott asked about elec panels hitting columns, I shared a fly by on Revizto and it didn't show any issues on UCO3
I showed the team Temp Power and Skyline clashing with MES Loops
I also emailed Nate Black last Friday
Ryan Warner says there is tees clashing on underground with Cupertino in elec gallery
7/21/2026
800amWeekly BIM Coordination Meeting - Region 2 (ZOOM)
Alan Lopez, Kyle Cummings (Hensel Phelps) / Ethen Berry
No one started the meeting, I sent an email, they said Alan was PTO and they started meeting late
They went over Region 2 underground, sign off later this week
5/26/26 - Allen Lopez Went over Region 2 again, said they were going to do a main signoff then a branch signoff. Covered a lot of UG clashes
6/2/2026
2 weeks sign off branch
6/9/2026
6/16/2026
Allen Lopez says he doesn't see Sure Steel model in TXE3, Kyle says also no Diversified, but Sure Steel model is there, needs added
Signoff schedule was not bridged, the one on FTI is outdated. Kyle and Justin said they would get the bridge up to date
Files - Data Management
6/23/2026
6/30/2026
7/7/2026
TXE3 Overhead Loop signoff next week
TXE3 Overhead Datahall signoff is July 27th
7/14/2026
7/21/2026
TXE3 Loop OH Signoff on Friday, DHA/B Following week
NO PM or Field Team present
830amLEB - BIM Coordination Meeting (Tue) | Meeting-Join | Microsoft Teams
Ryan Zoldan, Mortenson (GC1)
Missed for the 8am meeting
6/16/2026
6/23/2026
6/30/2026
7/7/2026
Ryan brought up their grids were off, crider and crider will be aligned today and HDR will be aligned. For LEB6
Ben Kozel says all waldinger was missing a flange on their bypass, everything else looked good, crider was good
Ben says HDR looks good for UG and Grids
7/21/2026
Talked about LEB6 HDR not matching Soutland provided dimensions, bullet point #1, supposed to be covered in meeting tomorrow
Talked about Underground stuff
1000amLightning-Eng-Coord Huddle | Meeting-Join | Microsoft Teams
Tia/ Tom
Follow up on HAC Panel clashes with Patrick Brinnehal
Meeting to go over stratus and models with all PMs, Adam, Scott, Supers sometime next week, look at schedules
Chris Chase is the PM of EMT
5/26/2026 - Check if Adam got the 4" Welded Bypass to Shop, from 5/5/25 email in Inbox "Im shooting to have the LTG build out scope package done by end of week (For Review only not for construction). "
Verify what spools have been put on stratus for TIA/TOM Lightning huddle
Need meeting to discuss, txe10 anchor clashing with interior of walls, adam sent info out about conflicting models, but as of today, there is still clashes
RFI says they are changing wall to Gypsm board and expanding toward corridor 2.5"
6/2/2026 - We did get 2 more sites in Ohio
SI will be integrator
Heath introduced Peyton Steveons as VDC supervisor
Starting with HRV
Melanie introduced Vasi, VDC specialist helping out ron and melanie
Tia went over deliverable schedules
Per site, per building
She setup a break out meeting
Adam said they are moving the walls away from anchors so we are clear
Adam said we are 1/2" clear from plate, it will be a field issue installing the plate
Michael said he will talk to paul, he doesn't know what to do, he will call greg
only 2 walls changed from IMP, 2 others are still IMP
Michael said Greg told him they are putting walls up next week
Told Tia I sent snip of Dog Leg Metraflex in chat, didn’t get any smiles
Let her know we have LEB complete, TXE10,1,2 is complete
Adam said he will give link to CIAs, TXE3-12 and LEB3-12 not ready
Adam had meeting with HRV, told them to start using our coordination models for coordination
Quick hello, this is who we are meeting
with MC Dean
Mealnie says they will be updating projects to new architect model
Type F - 4 buildings
Type G - 2 buildings
6/9/2026 - Adam said they are going to move the MSA, HAC spools to the Lighting Program, for one source
Melanie and Keylan said it can be done
6/30/2026 - FTI wants scanners badged
TXE1 special Support approved
H Support hanger, supposed to get stamped this week
HRV supposed to get linked in models setup so we can coordinate ug
Need to verify LEB and TXE CIA points
SS Headers are in fab per EAN
John Rhee asked about Waldinger misaligned, we are now good, sending email showing HDR is off
Toms Eng review comments will be looking at doing updates next week
HRV Embed Dims, ryan says he has, I have Angle working on them now, wtf?!!!
PIQ, melanie is setting up, I asked her to keep an eye out for the BIM ex plan and contact list
Michael said they have drug test this week, orientation on Monday
7/7/2026 - Cancelled
7/14/2026 - Melanie is going through EMT with cupertino to verify alignment
Isabella asked about clashing HRV, Peyton will be running coordination model for HRV as well as EMT
HRV Embed sheets need to be sent to Basebuild, adam mentioned
Still waiting on word a
1100amTXE10 Facility Water Tolerance Issue
Jake Williams (Hensel Phelps)
Waited for Brock from Cerris, once he showed, he said their scans didn't show them as far off as we are showing in pics
Paul says they pulled from Columns
The ML1 is about 3-3/4" off, ML2 is about 2.5" Off
Zach maded the comment that walls would need to move, if we were to move our anchor, things would need resubmitted for approvals
Brock said as of now the only way these pipes move is by jackhammering
Dan Laub says no one responded back with an accepted Tolerance, they were trying to say 3-5" and he admits that was't acceptable, but 1/8" isnt attainable
Zach responded saying 1/4" and the tolerance was submitted in the CCIA, which Dan didn't know what that was
Zach continued with 1/4" tolerance
Alex Harpel brought up Adams email from 3/11, which was addressed to Dan as the last in the chain and Adam said 1/2" tolerance
Dan said he never got the email, Alex showed a screen shot showing his name in the TO Field
Keylan explained we have scan going back out next week to capture the CPs, we will have scans ready end of next week for meeting on 8/3, everyone agreed
Jake asked Brock to come up with solutions in the meantime
1100amLEB - BIM/FAB Weekly Meeting
Reece Fauble
I missed meeting for Facility water with TXE
Listend to transcript
Meeting is to kick off discussions between bim and fab
Reece has packages setup for all buildings
has spools on packages for leb10 and leb1
he needs leed times
Storage will be an issue
No packages for sheet metal yet
Needs an idea from each package time frame and for storage
Ean says Ron can answer better next week
6 weeks before field install date, standard minimum
1200pmTXE-Region3 Coordination Meeting
Jade B Lowe (Hensel Phelps)
Jade is in charge of Region 3
Kyle cummins is in charge of site
Filll out contact excel sheet, put bim lead and project manager
Kyle - LOD 450 project, all installed elements are modeled, then asbuilts are fed back in to model
Indicate in the model some where that the asbuilt has been applied and model has been adjusted
6/16/2026 - Decided not to go to this one since its Region 3, TXE6,7 undergound
7/21/2026 - Missed meeting since they are covering base build
07/22/26 - WED (+8 Meetings)
630amEMT - Daily BIM Alignment
Abe Hernandez
Scott gave an overall for the MES/HAC foot clash
Melanie Working through EMT Models, links needed repathed
Go Through EMT1 and EMT2 and make sure MES, TW and MP content are good
IF good, push to Revizto
Also check MSA/FSHAC Piping
EMT Does have IFC's for Base Build, Scott showed them yesteday, I coulda swore we didn't have any sheets, prob thinking of HRV
7/22/2026 - Ryan says Mortenson is on the verge of issue stop work order with Meta due to electrical incompetetance
700amHRV - EoR Coordination Call
Ben Speese
CWC Neema Faryar(ARUP)
Gave thrust block info
Carl and Seth are present from CWC
Neema says stub ups need to be slurried, underground pipes need to be verified for undergound thrust and that passive soil will be sufficient
Above ground thrust will be satisfied by slurry and surrounding footers
MC Dean Bridged files
Danton Wein with MC Dean
MDI has steel and skids, fabrication
ENG has electrical equipment
They both have all links turned on, these need turned off
mcd plan for trench moving, not relating to Southland
Southland
MP Model connections to FW UG Stub ups
Need CWC Bypass, will they be included in the CWC Model we already have or in a separate above ground model?
Ben verified the models are good
Ben then went to stub ups and neema took the convo to RFI something, I said we were going to take a first pass at matching CWC Stub ups
Neema was talking about some kind of trnech shit moving that didn’t apply
7/15/2026 - Adam CWC said no update on the bypass for CWC
7/22/2026 - Talked FWM and MCUP issues mainly
Eli from Colonial was present
Neema says they need to move FW Stup ups away from footer about 5"
I mentioned they need to hit the critical North south dimension of 6'-1 5/8" to match the mes skid line, but we can match whatever movement they do east and west
Ben and Neema both pointed out CWC can rotate bypass valve to the front, one of the bypasses was already rotated this direction, CWC started to fight back a little bit
This means CW Will need to move their stub ups to get out of way of footers
Danton affirmed that the 2 MDC ENG and MCD MDI Models are the current models for the FSHAC
Storefont issues
800amTXE/LEB Weekly Internal BIM Coordination | Meeting-Join | Microsoft Teams
Jay Keiser - FTI
LEB10 RO Hitting Column
LEB10 FLEX HOSE on 8" Flush skid hitting column, need to clear clashes
talked about email I sent about a list of which models to use for which trades as far as Walls, Wall Panels, Electrical, Arch, Structural etc
Kyle said he was still working on that
John Cowhey is asking about Lugs on the MES
I will chase this down, find who responded Johns email and start there
Robert Cheek responded on Monday saying he would get the answer same day, still waiting
I told Jay we are currently working through shop drawings and spools, while we are doing those we are paying attention to clashes and working through the clashes
I Brought up the FW underground being off and that we will be scanning and verifying CIA POC's, Should be doing this within a week
5/27/2026 - I BROUGHT UP LEB1 COORDINATING WITH CRIDER NO MODEL, USING HDR FOR UNDERGROUND COORDINATION
JAY BROUGHT UP TXE10 ANCHOR CLASH WITH WALL, ADAM SENT EMAIL ASKING ABOUT IT, SOMEONE SAID THEY WERE CHANGING WALL IN A EMAIL RESPONSE, ADAM REQUESTED MEETING, NO ONE RESPONDED
JAY ADDED THIS AS AN ACTION ITEM
EMMA SENT EMAIL REQUESTING CLARIFICATION, TRISTEN WAS CONFUSED
LUKE SAID HE WILL DISCUSS IN HIS MEETING WITH MORTENSON
JAY ADDED THIS AS AN ACTION ITEM
6/3/2026 - New LEB Mech and Plumbing meeting on Wed, John and Reece involved, going over FW stub up locations and F/F water gallery connections
Informed John of Convos with Greg to coordinate wall install with coring of anchor plate holes
Told Jay/John, Lance Holmes is coordinating with other trades on fix for LEB UG FW stubups not hitting POC points or dimensions
6/10/2026 - Verify Span models work on LEB10, 1, 2
6/17/2026 - Checked LEB1, Span_SS model is still only showing Labeled grids, no steel in revit linked model, 2models, same dates, different version, latest verison wont load, gives error
Bring up Walbringer as new MP contractor on LEB6, sent email out with dimension sheets for someone to get them the information
Coordination Sign off
Jay gave links to Turner and HP sign off locations
Clash Review
Jay said he will go through and filter out white noise, setup a meeting to over others. I told him whenever he wants and I will be there
Friday 6/19/22 9am
6/24/2026 - Check with Adam if he verified the lastest info from Crider lining up ug, LEB10
Check LEB1 model HDR Underground lining up with Model, We are lined up with HELM Bypass on LEB10
Luke will get with LEB and Turner for Verifying CIA Points
Louis will get with TXE and HP for Verifying CIA points
LEB6 - MP Model misalignment, I checked the Turner NWD, they are using a FTI Container that may have a misaligned MP NWC
I Put together and new NWD with current NWCs Available and everything lined up correctly
LEB, DCW Drops, Get with John to find out which way they want to go, then follow up with HDR and Helm and Waldinger
I sent John Rhee an email requesting update
7/1/2026 - Jay brought up LEB6 issue I emailed, I told them HDR still needs to update their pipe stup ups, they fixed the grid though
I brought up CIA from other GCs since they were talking about FTI Scanning HP elements, if HP didn't provide documented points what is FTI going to shoot?
Justin said yeah, it is a meta requirement but meta hasn’t really lined out what exactly is required
I told them FTI did such a great job on the document and spearheading it, I was wondering if the other GCs also maintained this document since we are connecting to systems from other trades
Jay follow up with Kyle on HP for going through HP clashing directly, can we access them, create issues, clear?
7/8/2026 - Brought up LEB10 turner models, stay with NWC, even though they have
Advised that I have moved our DCW POCs to match HELM and HDR
Advised of TXE10 Scanning schedule starting tomorrow
Waiting on Patrick B for response on HAC FCU orientation
7/15/2026 - Told Jay, I havent verified Turners FTI Container files are updated this week
TXE Told Jay, Adam noticed the Fan Coils may need rotated 180 degrees, sent email, waiting on Patrick B to look at it
Verify Bypass submittals to FTI for John Cowhey
Check LEB6 FTI Container updated
7/22/2026 - Patrick sent out email saying txe10 FCUs have been reorientated based on Adams email, he will be going to other buildings
John is still waiting for Submittal for EOL HAC Bypass, he is talking to Jacob onsite, need submittal approved and start releasing fab on those
Underground conduit was missed for TWMU Skids, they need to be run overhead, it’s a substantial amount of conduit
Sent John, Justin, Jay the Control Point Map
Told Jay I would do a fly through on Leb10, LEB2 and LEB6 checking for FTI Container alignment
Do we need to do an official submittal for the Dimensions for UG Stub ups and Bypass elevations?
Start using ACC Issues module for tthings like LEB10 Crider stub ups being off
900amLightning HRV - Internal Detailing Meeting
Isabella Vesce Rivera
Bridged files from Colonial
Isabella will bring up we need bridged file
I requested to sit on base build coordination meetings with DPR/ Colonial
Adam wants form to access DPR, he will give it to all
Tomas maxell and chirdon talking to structural engineer about eliminating the middle anchor on DCB100
Adam added couplings to MSA that will allevaite having to add welds for field install
Packages were created in stratus, should be able to get dates by EOW
MSA to HAC needs some couplings removed
Depending on if Ryan can put the couplings on GMP Field because Fab is hard bid
Adam will remove from on site scope, per Ryan
Adam Dial in how we want to name NWS MSA for spool sheets
Adam wants to name them so they are more in line with the stratus packing naming
Deliverables -
Sign off and install schedule
7/15/2026
Waiting on Corbon to yay or nay the middle small anchor
MC Dean is still making adj to hac steel, they did state it shouldn't affect any of our content, ian is supposed to be complete on 9/24
Adam is supposed to put couplings in MSA to stop field weld
Need this update in stratus per Ean
All packages are created in Stratus with Dates
Get with stone and scott about getting FCU in the HAC for HRV
Southland will be running our own Clash Coordination
MC Dean provides a NWC, but we are choosing to use DPRs NWD in our own Model Coordination due to being more current and includes more trades
Keith, Melanie and Peyton will be putting this together
Melanie says not to clash with their NWD, not good
Either we will use DPR Forma Model coordination, if not available, we will ask if we can bridge their models directly to our forma to run our own Model Coordination and clashes
DCB100 NWS1/4 signoff 9/22
DCB100 NWS2/3 signoff 9/29
7/22/2026
Gave run down to Thomas and Ryan of Colonial Stub ups
Trhomas says there will be a middle anchor
Peyton will be leading the Coordnation Model and space, will be issueing clashes
Will be running clashes today
Ryan did sent out an email to DPR and colonial web regarding the UG FW CWC Dim sheet showing critical dimensions
1000amBIM Round Up | Meeting-Join | Microsoft Teams
Michael Kolnik
Jeremy says they are supposed to be scanning in a week or 2
Jeremy needs Floor drain locations from Cerris so they know exactly where they land, Need to get with Patrick Marshall at Cerris and see if we can get some shop drawings.
6/3/2026 - MICHAEL ASKED ABOUT CURTIS GIVING HIM AN ORDER REQUEST THAT HE THOUGHT WAS SUPPOSED TO BE FOR FLUSH SKIDS
IT HAD 16X14 TEES, 14" 90S, 8" STAINLESS CAPS
HE DIDN’T KNOW WHERE THESE TEES CAME FROM
I TOLD HIM THEY WERE FOR THE MES LOOPS, NOT THE SKIDS
THE 14" 90S WERE PROBABLY FOR THE FLUSH SPOOL TO CONNECT TO THE FLEX SKID
MICHAEL SAID HE CANT GET THEM IN TIME, SIAD HE IS LOOKING AT DOING A MATERIAL SUBSTITUTE REQUEST, I SAID IT ASAP AND PUT CURTIS IN THE LOOP ON IT
6/10/2026 - Michael said he is having a meeting Friday about FW scanning and fix for fw off dims, with HP, FTI, Scanners,
6/17/2026 - Adam brought up supports, new design doesn't leave room for any adjustments
Michael says scanning will be around 7/1, if UG is off, michael says we will have to fix and charge HP
Are we going to have 8 unique supports
Paul says we will have to do it in the field
Paul and Michael agreed a new stand with Trapeze hangers will work, adam wil resubmit
Michael has order all fittings and pipe for TXE10 and TXE2 for MES loops
Region 1 is staying with 1 flush skid
2 flushes, twice as long, michael said it doesn’t schedule, not enough time for 2 flushes
6/22/2026 - Adam is telling Michael they need to create packages in stratus for how they want hac jumpers, bypasses split up
Adam is proposing a fabrication kick off meeting with Ryan and Curtis to get everyone on board
Micheal needs 8 weeks, Curtis needs 3 weeks for example
Jacob says curtis wants packages created by cost codes, but we are talking about splitting them by areas
Paul says give tom a curtisy that we are rele
Need to update the 6" flush skid and put a bleed olet on the return vertical
Paul says hes not sure where the Bypasses are as far as UG Bypass
Pual not sure when production will start for Near site, installing bypasses on HAC on near site
He will then put the spools in the appropriate package
6/30/2026 - Paul says caps are needed on MES TW and FW Ports, they can put drains on if they want
No drains on jumpers
Curtis is shipping spools to SOK
Curtis said no drains on caps, just need caps
Michael, going over spools
No Drains on jumpers
Look at TXE1-01-FWR-JMP-001, showing Flex coupling, need quick vic
Michael Ordered 16x14 tees, make sure we stayed with those and didn't update to full 16" to flush skid
7/8/2026 - Michael and Paul requested 6" and 14" Flush spools to be stainless
Sent info to Tom and Stefan, Tom says no, the flushing chemicals will clean it
7/15/2026 - Jacob says curtis put dates a month earlier than whats listed
I Told them Curtis is the one who would determine if we need to change material, stick with what he says, move the dates to 6 before install date, and get that request out, if they can't meet that, curtis will decided the next direction, weld?
Looked over installed bypasses at TXE10, everthing is off.
The Anchor plate was 5/16" off and into wall space on ML1 area
7/22/2026 - No Meeting, no popup, no cancellation
1030amEMT - Mortenson BIM Coordination Meeting
Nate Black (Mortenson)
UCO3 Loop OH Coordiantion Sign off 7/24
Nate pointed to coordination models that will b
Scott asked about the container models and who is creating it
nate said if we can push our models to revizto directly, that would be great
Heath said he can do this
Need to notify heath when they
7/22/2026 - Went over Drone Fly through
FCW is being dropped in EMT2
Skyline safety share
Alex Eismore, mental health
7/22/2026 - Just covered based build items
1130amEMT - Mortenson BIM Component Call
Nate Black (Mortenson)
7/15/2026 - Cancelled
7/22/2026 - Meeting is still listed in Calendar, mainly Southland BIM team in invite
Go over UCO3 and EMT2 Wrong Locations on Base Build and Lightning Scope
ON Key plan the A sectors and B sectors need to be swapped
Heith said he missed it when he set it up, takes full responsibility
We havent' issues any sheets yet for EMT
07/23/26 - THU (+7 Meetings)
630amEMT - Daily BIM Alignment
Abe Hernandez
Scott gave an overall for the MES/HAC foot clash
Melanie Working through EMT Models, links needed repathed
Go Through EMT1 and EMT2 and make sure MES, TW and MP content are good
IF good, push to Revizto
Also check MSA/FSHAC Piping
EMT Does have IFC's for Base Build, Scott showed them yesteday, I coulda swore we didn't have any sheets, prob thinking of HRV
7/16/2026 - Melanie says our MP model doesn’t line up with Eng Model, we are using Lightning Shared Coordinates, Eng is using ETM100
Abe - Attached Sign off schedule to summary email, have content populated and coordinated ahead of signoff dates highlighted in RED, these dates line up with Mortenson
I told her our content, mes content lines up in revizto, if you change anything, it will no longer line up
Download arch model, link our models in and see who lines up
She says archs did change the g datum model a while back, she had to repath it and that’s when things stopped lining up correctly
7/17/2026 - Cancelled
7/20/2026 - Cancelled
7/22/2026 - Ryan says Mortenson is on the verge of issue stop work order with Meta due to electrical incompetetance
7/23/2026 - Cancelled
630-710amLEB | BIM | Faith x Turner
Luke Jost - Joe Dorinsville
Edwin Perez from Turner hosted
5/14/26 - - Joe Brought up the access panels for Flush system, asked about rating, I would have to check submittals to verify. Me and Lance holmes informed joe the flush systems are temporary, once done, they get removed and the access panel stay
Anna said they were aware, but not the finalized locations, now they will be going through Valley for engineering, excel engineering to make sure everything is accounted for, engineered
Talked to Stefan, we are not providing the Access Panel, its GC2 wall, they are providing it
I need to check on RO system, ACCess panel and it looks like location may be borked
Scott asked about sign offs for lighting scope to base build duct connections, Joe said they havent covered it, sign off is around end of June. They will be circling back to loop area not that they have certain paperwork available
Joe said any issue can be brought up at anytime
5/21/265 - No John Rhee, Brent, Thomas Holler, NO PM TEAM
They went over stud wall model, Lance asking about raceways for security and bus ducts
5/28/2026 - They went over electrical stuff, skid placement, wall leave outs
Turner wants a meeting with Helm and Southland to go over Wall penetrations
Joe D discussed Span model naming, keeping them the same and consistant.
Will need to relink LEB Span models since they have new models with Nucor suffix
6/4/2026 - Eduardo Ibanez brought up Status of Facility Water Stubups asking if Verification of Stubups with Mortenson needed. Had Crider submitted? Lance was saying Ryan would have this info and asking if Ryan was in meeting
NO PM Team present
I sent PM Team a summary email
I explained, Ryan used HDR model for coordination, I worked with HDR to get everything line up, we provided dimensions, everyone agreed to them, now stub ups are off, Lance Resposnded to John Rhees email asking what is being done
I said we need to start having meeting to go over this issue since its so critical
Luke Jost told eduardo to add an action item for this and lance said he will head this off
6/11/2026 - I brought up the FW UG being off again, told the group Ben Kozel with crider said they were backfilling in layers and trying to get the stub ups on the POC/CIA points
Overhead Signoff is schedule for 6/30
Scott asked if it was entire building for NWB, Joe says yes
Joe Brought up IMP walls changing to Framed walls, Anna? Said it was still being worked on
Verify LEB10 POC For DCW
Verify DCW POCs line up with CIA
Lance said they are also providing a hose connection for discharge, I stated they are using the FLOOR Drains in center of gallery for discharge, Adam corrected me saying John has requested different discharge points. Wouldn've been nice to know.
Someone asked about the Flex piping from the 8" skid hitting the column, I told them it was flex pipe and temporary, that it will bend around the column
Vent in 6-19x6-D, adam told them to put in between MES Skid
Waldinger is doing the bypass on LEB6
Building 6 MES loops are showing misalignment with Waldinger Bypass
NO PM Team present
I said I would like it added to this meetings notes, Joe Dorinsville basically shut it down, saying it was a field issue
I said it was our issue also since we are constantly being asked to do overlays, which were happy to help any way we can, but this was more of a helm situation since they are the responsible party to connect to the UG and provide us with accurate points of contact according to the CIA
Joe reiterated it was a field issue
6/18/2026 - Edwin Perez is showing Verification on stub ups w mortneson needed. Pending Submittal. Eng. Drawings to be submitted - Crider and Crider. He said this is still on going
Edwins model view still shows MP Shifted to plan right, access panels were to the right of the wall they are supposed to be in
LEB6 Arch Coordination model is showing everyhting off, MES Skid not lining up, mp is to the right, access panels are to the right of the walls they are supposed to be in.
LEB10, checked with Joe D, things line up there.
6/25/2026 - Joe, Greg, Luke Long, Greg went over Electrical coordination
I sent email to PM Team, no one was present
Eduardo Ibanez brought up Status of Facility Water Stubups asking if Verification of Stubups with Mortenson needed. Had Crider submitted? He brought this up again. I explained again that we provided dimensions for LEB10 and LEB1 to Mortensen, Crider and HDR, they all agreed
I told group that I also emailed these dimensions to Waldinger for Region 2, but havent received any comments or response from anyone.
Scott asked about tracking for signoff on 6/30, eduardo said yes
Luke Jost asked about LEB10 Embeds to make sure they are getting tracked by turner
Edwin Perez asked about Waldinger Bypass and alignment to SI MES Loop Connection
I told Edwin Perez I provided poc dimensions and elevations, but havent received any response
Edwin said he will bring up in next BIM meeting
7/2/2026 - Get with john as far as who is providing what cam lock adapt for fip drops
Lance Holman also provided additional dishcharges (Drains) for Flush/ fill per john
They showed model, HDR DWC Drops are on face of column, I told group IFC shows they are on Web side, HDR Model doesn’t match HDR IFCs
John Rhee is communicating changes from model to FTI, Turner that they are not telling us, Discharge drains, DCW changes
The only reason I found out was because of the meeting flythrough, our pocs were on other side of corridor
John fucking totally ignored our information and didn't relay any information
I missed the HDR IFCs showing the drops on the plan south side of corridor
I explained LEB6 model misalignment was fixed, publishing issue, I will double check mondays model after the Saturday auto publish
I told group about the FW UG Dimension sheet that has been distributed multiple times and it details where the FW UG stubs are supposed to be ever since LEB1
I will double check LEB2 misalignment
They showed LEB6 and the 8" skids were into the columns again
I explained the deep dive I did last week, it shows everything aligned. There are issues with the FTI Container model that Turner is using for coordination
7/9/2026 - Setup LEB2 SI MP View off turner LEB2 Overall Building NWD, Crider is still off at Grid 2-50/ 2-D
Eduardo Ibanez hosted
LEB10
All Content on slab will be created in a file, progress is ongoing. Jay Asked what does this entail? Above Slab content?
LEB6
Our MP is still out of alignment in Turner LEB6 Overall Building.nwd, but Joe pulled in a recent nwd and it showed the FTI Container inside the Overall nwd is off
With joes pulled in NWD that shows us and waldinger aligned, Crider was still off around 8-10"
SI Duct and Waldinger do not align
Justin verified that Turner is using NWC files NOT the revit
Southland MP looks good
Southland MP model is still a little older, but non-critical
7/16/2026 - Joe D brought up some issue about control joints at LEB10, luke jost and jay kaiser will update as necessary
7/22/2026 - Joe D brought up control joint proximity to MP anchors, they scooted 1 at grid 29ish, no TW Skid.
Checking Coord Space at LEB I see Stratus models getting exported again on 7/17, that was last Friday
The only MP model available is from april, what the fuck is going on with this fucking shit
The LBE10 Publish settings were set to stratus, talked to heath, he showed adam was the last one to do it. Adam said he didn’t know had to change settings back
Lance suggested a meeting with FTI and Southland to get power to TW Skids, Lance Long said they have a meeting setup with FTI Tomorrow, looking at junction box on the wall
Jay K at FTI created an issue with Crider Facility Water Alignment and was trying to add crider watchers, he can only add FTI watchers.
Joe D told him to use Triston with Helm, Mitch with Waldinger
Mitch with Waldinger said it looks like its going to work out with aligning their Bypasses with Southland MP
Jay K brought up container models having outdated southland models
Joe D says its tough to say when the FTI container was reloaded. The last update they show was july 13th, 10 days ago
I rbought up the TW Skids on each end of the building also to check, they have anchors also
I stated I found a recommendaiton of 3" distance between an anchor and a sawcut or concrete joint
800amTXE-FTI Weekly Sync Meeting
Luke Justice
Luke was asking about scanning at TXE10, He said coordinate with Greg Hueramo, he will be setting up an origination email
I told luke they need to have all areas ready for scanning since the team cant be sent out every other day, reset up, etc
I asked for Control point map, he said get with Greg Hueramo
I explained to him what the scanning was
I told him they will need to add paul hernandex, jeremy miller and adam brown to email
John Cowhey said he has a 1 pager for Site orientation which will be 8 hours
They will be enforcing badging within the next few weeks. No badge no access, Visitor badges will be available but not allowed to work
Luke will put together a schedule for orientation
11/17/26 - is new date for 0 prep according to John Cowhey
Forward FW off email to Luke, original email was sent out 4/17. I resent to Luke Justice
I told him Jeff Balthrop was involved a few weeks back
Send Luke Discrepancy on Anchor locations with BZI Wall panels, NWCs etc from Adam email, Adam email 5/5, TXE Adam email 5/6
Verify anchors at TXE and LEB, check they've been submitted to FTI
Send notice to John Cowhey, luke justice
They asked when Southland is looking at manning the site, jeremy informed them no PM team were available at this time to answer
new schedule coming out Friday
Got with michael kolnik, he sent out Shop Drawing submittal request to Eric Boehger
5/28/2026 - Loop Keylan and Michael into the Anchor clash info and meeting for Friday
Luke says bypass are fabbed, not installed will be installed next week, sent out email to everyone, paul, jeremy, michael
Need to coordinate orientation, drug testing
Day zero schedule? Luke said he was supposed to get last Friday, not seeing anything new
Luke showed the Faith TXE Anchor Shop Drawing submittals, they are only for the TXE10,1,2 Plates don’t know why it has TXE3 on the label
Not showing any Shop drawing embed submittal info
NO PM Management was present, Keylan Rollins was for engineering
6/4/2026 - Luke Cancelled at 741am, Got DAMN MAN!!!!
6/11/2026 - Luke Cancelled at 741am, Got DAMN MAN!!!!
6/18/2026 - Luke asked about Issues, I was explaining a summary of Greg Heuromos meeting, then Michael Kolnik was there! It was nice
6/25/2026 - Michael says greg told him the bypass will be complete on 6/7, michael has scanning scheduled for 6/6
Jason with FTI will use truck to help scanning move around job
Scanners will need badges, they can be escorted according to michael who talked to security
Michael says no one onsite yet, they are on first of kind, michael and jacob did get badged
FTI does have a superintendant and a couple of upper management onsite
Fully mobilized first week of July
Luis says they have been requesting a lot of BIM information, Asbuilts, trench information, etc
Luke says a laser just got done for the Trench
Alec Harpel says first half of txe10 was scanned, still waiting for coordinates
Need FW stub ups, grounding whips and trenches
Luis is asking for points for the finish floor to verify elevation/flatness
TXE1 slab just started pouring last week, according to Luke
Micahel said they wont have water into the building, they need to truck it in and provide the minimum GPM with 3" connection
TXE10 shows 3" main with 3" drops
TXE1 shows 4" main with 3" drops
7/2/2026 - Luke Justice cancelled
7/9/2026 - Luke Justice cancelled
7/16/2026 - Keylan gave run down of Scanning and photos, scanning completed
Jacob stated carsen is locating revit files and uploading info
Should get scans by afternoon
7/23/2026 - Luke asked about Control points, I told him we did get the PDF from Shay with coordinates and CP labels
I can use this to get the CPs into the model
I informed them that Justin Jenkins was looking for Dimensional data from CP to a known point. I said I would follow up with Justin
Sent email to Justin Jenkins with CP map and letting him know they didn’t understand the dimensional data from CP to Known point
930amLEB | BIM COORDINATION LEB2
Emma will no longer be on this project
Kaushal Bagdekar with Turner ran the meeting, saying who to contact for what, I asked if he could send an email with that info
They went over underground clashes
5/28/2026 - Tristen with helm verified he is using LEB1 dimensions for LEB 2 elevations and locaitons for FW
6/11/2026 - No PM Team
Went Over UG issues, concrete pads
6/18/2026 - Kaushal Bagdekar
Did a flythrough for LEB2 going over exterior sectionalizers
LEB-2_SPAN_SS.rvt, verifying during meeting that the model is good, Checked LEB2 SPAN_SS model, couldn’t load content, says cant link in NuCOR
NO Interior Walls and framing, Valley, Diogo or Ruth said they will get with valley
No Interior Meta Wall Panels
6/25/2026 - NO PM TEAM
They went over UG issues for LEB2
7/2/2026 - LEB2, Showed model where Helm, SI and Crider not aligned, #2070
LEB2 Building Overall actually has Crider model, showing misaligned
Grid 1-50, 1-D is the only spot where Crider is off looking at Turners LEB2_Building_Overall model only
Everything else is aligned, MP, Duct, Steel, Walls, no issues
Sent email showing misaligned concrete and crider stub ups at 2-50
LEB-SI-MP-LEB2-R25 model lined up identical to LEB2-Building-Overall
Didn't see new DCW POC valves, did I update LEB2
Did see FLUSH VENTS AND DRAINS, VENT ON 2-50 IS OFF
7/9/2026 - Sent Email to Joe, Jay, Edwin, Eduardo and Joe forwarded to Kaushal
Kaushal asked about flush skids in front of door ways, need to send them a time frame for flushing before equipment gets removed
Concrete elevations different at Gird 2-29 and 2-32
Crider stub ups off at 2-50/2-D
Added to chat
7/16/2026 - Sent email to Triston with Jay and Kaushal cc'd about Helm bypass flanges not aligning to SI MP Flanges throughout building
LEB2 looked like it aligned good
7/22/2026 - No southland issues covered
1000 amLEB - BIM Coordination Meeting (Thu) | Meeting-Join | Microsoft Teams
Ryan Zoldan
LEB 6 due finalized next week
I requested a schedule from Ryan, he has the sign off, region schedule, I brought up a pull plan, be he says that will be through Turner
Mortensen is the Base build GC, why aren't they leading a pull plan schedule
John Rhee nor Brent were in this meeting
6/4/2026 - I brought up the LEB10 FW UG Stub ups totally missing the Dims, Ben Kozel was there and he stated they are bringing them back in to dimensions by backfilling a little and moving them, backfilling and moving them
He acknowledge that lance did contact him
6/11/2026 - Ben Kozel, said there were no issues that need to be talked about.
Richard lopez asked around the room for any issues regarding LEB10 or any others
NO PM Team
6/18/2026 - Richard Lopez Hosted, just asked for any issues with LEB10,1,2,3 Underground issues
Rantwiler asked when IWM for TXE10 was going to be signed off, Ethan says he will talke to kyle since they are not really split out
6/25/2026 - Going over LEB7,8
Ryan brought up LEB6, HDR model is not lining up with the Dimensions provided by SI
Ryan henderson said he will follow up
Ryan said we have all agreed to follow these dimesions, I added that I have distrubuted that dimesion sheet ot Waldinger and explained everything, but havent received a response yet
Ryan brought up LEB6, HDR model is not lining up and my email I sent out
I updated, still waiting for HDR to align the stubups
Ryan said Crider is using civil 3d, but we can work it out to actually use their model for coordination and linking in so I don't have to use HDR
7/9/2026 - No issues to cover, they went over UG clashing for elect, sanitary
7/23/2026 - Richard asked Triston about any alingment issues, he was good
Ben said LEB6 stil had some very minor HDR alignment issues to on udergoung
TXE1 looks good for the loop area sign off next week
Same with TXE2
6/4/2026 - Own B ran the meeting going over TXE1 and 2
6/11/2026 - Owen B, says TXE10 Loop for sign off
TXE2 Core scheduled for next week
TXE10 AB Datahall and Loop are signed off
TXE3 Alan lopez is running region 2 for signe off
TXE2 Loop and AB South sign off
issue 2602 - Cerris Vent in corner is clashing with Technical water, Rantwiler is saying they don’t have our model, I told them our model has been there for 6 months, the fact that HP is viewing it, means the model is available. If it’s a bridging issue we will help Cerris work it out
Trevor said he will get with rantwiler and get the model bridged, they will offset that vent around our TW Piping
They made comments about the TW skid being so close to the FW valves. Its been this way for over 6 months. Trevor also stated the vent will need an accessible cleanout
6/25/2026 - They just went over IWM and specific Electrical clashes
7/9/2026 - TXE 2 all docs are out, all sign offs are out
TXE1, 2 sign offs left
DHCD 2 weeks from now
7/22/2026 - No Issues
1130amLightning HRV - Global BIM Coordination Meeting
Isabella Vesce Rivera (SI)
Is there a coordination model we get access to? Revizto? Navis?
Get input on HDR Mockup I made for FW UG Stubup, Bypass and MES Loop connections
Colonial was trying to align to SI Desing model, that was all that was available for the bridging
Seth Blizzard says they arent obligated to meet our POC's, they follow the ARUP design. ARUP did let them know they are contracted to meet our POC's
Curtis Robbins said he just needs to click a button to enable the bridging to our actual Coordination Models
Seth started making comments about use being able to shift our pipes 3", I told them theres a lot more going on that what they were showing with our Engineered anchors, flush connections, MES and TWMU skids and TW Piping, there isnt much forgiveness
Still don’t have access to bridged Colonial files
07/24/26 - FRI (+3 Meetings)
630amEMT - Daily BIM Alignment
Abe Hernandez
Scott gave an overall for the MES/HAC foot clash
Melanie Working through EMT Models, links needed repathed
Go Through EMT1 and EMT2 and make sure MES, TW and MP content are good
IF good, push to Revizto
Also check MSA/FSHAC Piping
EMT Does have IFC's for Base Build, Scott showed them yesteday, I coulda swore we didn't have any sheets, prob thinking of HRV
7/16/2026 - Melanie says our MP model doesn’t line up with Eng Model, we are using Lightning Shared Coordinates, Eng is using ETM100
Abe - Attached Sign off schedule to summary email, have content populated and coordinated ahead of signoff dates highlighted in RED, these dates line up with Mortenson
I told her our content, mes content lines up in revizto, if you change anything, it will no longer line up
Download arch model, link our models in and see who lines up
She says archs did change the g datum model a while back, she had to repath it and that’s when things stopped lining up correctly
7/17/2026 - Cancelled
7/22/2026 - Abe
Monday meeting will be clash review
Need to send base build mortenson meetings, nevermind scott interuppted telling abe to go straight to GC1 for invite
Told Abe all mechanical piping for MES is populated in all buildings, EMT1 and EMT2 need to be aligned, sent Nate black email informing him Design models for Mechanical pipe no longer needed
FSHAC Piping is included in FSHAC Model
I informed abe the Mechanical hac and msa piping is part of the FSHAC model, not the MP model
Melanie brought up mutliple instances of pipe, looks like there are 2 uco3 basebuild MP models of southland, 1 from nicole, 1 from heath
1000amHRV DCB90 View/Sheet Layout
Heith Williams
DCB90 True North is set to 202 degrees by Archs Datum, Heath don’t know why but when your modeling with Project north, it flips the building upside down with Grid 1 on right and 60+ on left
He had to rotate all section scope boxes 180 degrees to get the views corrected.
We have to make sure the sheets, names, views match when we are doing sheets
1100amMNT West Piping Detailing Meeting
Adam Brown
Went over MW Piping Presentation Guide Power Point
Will go over ACC Publish and Review next week
7/13/26 - 7/19/26
07/13/26 - MON (+5 Meetings)
630amLightning Ketchup
Adam Brown
TW Pipe hitting new H TW Supports, need raised or ???
HRV Updates
No Bypass from colonial, using ARUP Eng bypass
Working on adding all updates at ML2
EMT UCO3 updated, Revizto updated
LEBNWB
700amEMT - Lightning BIM Weekly Coordination
Abe Hernandez
Printed IFC Addendum 1
Scott showed Mortenson schedule 7/6
Peyton Coordination Model - Meeting with Heath, model is setup, need to get heath input
Using forma coordination module for clash detection
Cupertino says they are fine using the Forma module
Ryan - wants the model defined as to which one to use and clash with for Cupertino
Scott says he is on it
I let abe know that the MES and MP constructability models are now in the Revizto publish
He told Cupertino they can use that
Scott asked about elec panels hitting columns, I shared a fly by on Revizto and it didn't show any issues on UCO3
I showed the team Temp Power and Skyline clashing with MES Loops
I also emailed Nate Black last Friday
Ryan Warner says there is tees clashing on underground with Cupertino in elec gallery
900amLightning TXE Staff Meeting | Meeting-Join | Microsoft Teams
Jacob Gelhousen
Will do scans after Cerris installs bypasses
6/1/2026 - Noel Nunez says Alehandro Chew will be safety manager
Michael said he sent TXE3 embeds along with PDF dimension in mid April
Doesn’t think TXE3 has been poured, think they are behind schedule
Says we havent been funded for Region 2, he is sending out embeds as needed
Michael asked what the question was about RO and TW, I said it was going over how to connect to the RO skid, from DCW and to TW MES
Michael asked if MES Loops were completed, adam said yes, he created new BOMs
Michael said his goal is to get everything ordered
Michale Paul said they thought the walls weren't going to be in until they could do anchor
They said that was what was agreed to
6/8/2026 - Michael said they had a PM Coins Mandatory meeting and couldn't host the meeting
6/15/2026 - Chris Moss came on board from TSMC, Pipe fitter, GF
Jose Alejandro Chew, new Safety Manager for TXE
6/22/2026 - Shop drawings (Engineer Drawings) looking at submittal on Frid, 6/26
6/29/2026 - Keylan Cancelled
7/6/2026 - Carson will scan on Thursday
7/13/2026 - Scans on TXE10 complete, should have done this week, EOW
Jacob will be pulling field measurements of FW Stub ups
Adam will overlay scans to see how they match up with our Stub Ups
SOK will be starting next week, 27th will have more setup covered
1130amMW Detailing Weekly Meeting
6/29/2026 - Marshall Cancelled
7/13/2026 - Missed, I thought it was cancelled
1200pmEMT BIM Look Ahead Meeting
Nate Black (Mortensen)
UCO3 OH Signoff 7/24
Went over drone map, EMT1 and 2 have UG FW
Went over sign off schedule
Showed Marcos Revizto Clash Workflow
Showed UCO3 Loop OH
07/14/26 - TUE (+7 Meetings)
630amEMT - Daily BIM Alignment
Abe Hernandez
NEW H Pipe Supports for EMT, Approvals?
Scott showed where the live SI LTG FSHAC lives, he should be able to get it live today and push to VDC so it can be distributed
Mortenson Sign off schedule? UCO3 OH 7/24 from yesterday meeting
Abe says he has a schedule
Ryan Warner says we need to get coordinated with UG Elec stubups according to Mortenson sign off schedule
He says we are 4-5 weeks behind UCO3 sign off dates
This started taking over the whole meeting, I dropped for the 7am HRV Arthur Foley MC Dean meeting
700amHRV Southdland + MC Dean BIM Coordination
Arthur Foley (MC Dean)
Adam says when they load in the new updated hac models, shoot us an email so we can verify pipe supports in the hac
I told arthur I was focusing on UG FW, we still need Colonial Bypass, Arthur said he would contact them for an update
I reiterated later that I was working West to east checking our content with Colonial locations, still need their bypass,
Scxott says he will put Fan Coil Models by Monday of next week so MC Dean can produce IFCs
Arthur says they will get the federated model through 3rd party, Darren is point of contact, Arthur says they should have the federated model will be available next week
Isabella reitereated the importance of this
Arthur has updated steel model and will upload to HRV by end of week
Scott says he will clash with new model and fan coil
HACs have an elevation update to complete, says they are 99% complete
Says current steel is complete for FAN Coil placement
Schedules
Install schedules, Sign off Schedules, Doowooo said he will get these from DPR
Coordnition meeting
Thomas Maxwell says they are not having coodination meeting
Isabellas Thursday meeting will look at doing coordination with DPR, MC Dean, trades
Arthur says they do show a NWC with content for a coordiantion model
Prefers Southland runs their own clash checking and report, Adam says we can handle it
800amWeekly BIM Coordination Meeting - Region 2 (ZOOM)
Alan Lopez, Kyle Cummings (Hensel Phelps) / Ethen Berry
No one started the meeting, I sent an email, they said Alan was PTO and they started meeting late
They went over Region 2 underground, sign off later this week
5/26/26 - Allen Lopez Went over Region 2 again, said they were going to do a main signoff then a branch signoff. Covered a lot of UG clashes
6/2/2026
2 weeks sign off branch
6/9/2026
6/16/2026
Allen Lopez says he doesn't see Sure Steel model in TXE3, Kyle says also no Diversified, but Sure Steel model is there, needs added
Signoff schedule was not bridged, the one on FTI is outdated. Kyle and Justin said they would get the bridge up to date
Files - Data Management
6/23/2026
6/30/2026
7/7/2026
TXE3 Overhead Loop signoff next week
TXE3 Overhead Datahall signoff is July 27th
7/14/2026
830amLEB - BIM Coordination Meeting (Tue) | Meeting-Join | Microsoft Teams
Ryan Zoldan, Mortenson (GC1)
Missed for the 8am meeting
6/16/2026
6/23/2026
6/30/2026
7/7/2026
Ryan brought up their grids were off, crider and crider will be aligned today and HDR will be aligned. For LEB6
Ben Kozel says all waldinger was missing a flange on their bypass, everything else looked good, crider was good
Ben says HDR looks good for UG and Grids
1000amLightning-Eng-Coord Huddle | Meeting-Join | Microsoft Teams
Tia/ Tom
Follow up on HAC Panel clashes with Patrick Brinnehal
Meeting to go over stratus and models with all PMs, Adam, Scott, Supers sometime next week, look at schedules
Chris Chase is the PM of EMT
5/26/2026 - Check if Adam got the 4" Welded Bypass to Shop, from 5/5/25 email in Inbox "Im shooting to have the LTG build out scope package done by end of week (For Review only not for construction). "
Verify what spools have been put on stratus for TIA/TOM Lightning huddle
Need meeting to discuss, txe10 anchor clashing with interior of walls, adam sent info out about conflicting models, but as of today, there is still clashes
RFI says they are changing wall to Gypsm board and expanding toward corridor 2.5"
6/2/2026 - We did get 2 more sites in Ohio
SI will be integrator
Heath introduced Peyton Steveons as VDC supervisor
Starting with HRV
Melanie introduced Vasi, VDC specialist helping out ron and melanie
Tia went over deliverable schedules
Per site, per building
She setup a break out meeting
Adam said they are moving the walls away from anchors so we are clear
Adam said we are 1/2" clear from plate, it will be a field issue installing the plate
Michael said he will talk to paul, he doesn't know what to do, he will call greg
only 2 walls changed from IMP, 2 others are still IMP
Michael said Greg told him they are putting walls up next week
Told Tia I sent snip of Dog Leg Metraflex in chat, didn’t get any smiles
Let her know we have LEB complete, TXE10,1,2 is complete
Adam said he will give link to CIAs, TXE3-12 and LEB3-12 not ready
Adam had meeting with HRV, told them to start using our coordination models for coordination
Quick hello, this is who we are meeting
with MC Dean
Mealnie says they will be updating projects to new architect model
Type F - 4 buildings
Type G - 2 buildings
6/9/2026 - Adam said they are going to move the MSA, HAC spools to the Lighting Program, for one source
Melanie and Keylan said it can be done
6/30/2026 - FTI wants scanners badged
TXE1 special Support approved
H Support hanger, supposed to get stamped this week
HRV supposed to get linked in models setup so we can coordinate ug
Need to verify LEB and TXE CIA points
SS Headers are in fab per EAN
John Rhee asked about Waldinger misaligned, we are now good, sending email showing HDR is off
Toms Eng review comments will be looking at doing updates next week
HRV Embed Dims, ryan says he has, I have Angle working on them now, wtf?!!!
PIQ, melanie is setting up, I asked her to keep an eye out for the BIM ex plan and contact list
Michael said they have drug test this week, orientation on Monday
7/7/2026 - Cancelled
7/14/2026 - Melanie is going through EMT with cupertino to verify alignment
Isabella asked about clashing HRV, Peyton will be running coordination model for HRV as well as EMT
HRV Embed sheets need to be sent to Basebuild, adam mentioned
Still waiting on word a
1100amLEB Clash Sync With Jay
7/7/2026 - Touched based on LEB10, Cleared FTI ACC Clashes, I need to go through Turner ACC and check for clashes
1200pmTXE-Region3 Coordination Meeting
Jade B Lowe (Hensel Phelps)
Jade is in charge of Region 3
Kyle cummins is in charge of site
Filll out contact excel sheet, put bim lead and project manager
Kyle - LOD 450 project, all installed elements are modeled, then asbuilts are fed back in to model
Indicate in the model some where that the asbuilt has been applied and model has been adjusted
6/16/2026 - Decided not to go to this one since its Region 3, TXE6,7 undergound
07/15/26 - WED (+8 Meetings)
630amEMT - Daily BIM Alignment
Abe Hernandez
Scott gave an overall for the MES/HAC foot clash
Melanie Working through EMT Models, links needed repathed
Go Through EMT1 and EMT2 and make sure MES, TW and MP content are good
IF good, push to Revizto
Also check MSA/FSHAC Piping
EMT Does have IFC's for Base Build, Scott showed them yesteday, I coulda swore we didn't have any sheets, prob thinking of HRV
700amHRV - EoR Coordination Call
Ben Speese
CWC Neema Faryar(ARUP)
Gave thrust block info
Carl and Seth are present from CWC
Neema says stub ups need to be slurried, underground pipes need to be verified for undergound thrust and that passive soil will be sufficient
Above ground thrust will be satisfied by slurry and surrounding footers
MC Dean Bridged files
Danton Wein with MC Dean
MDI has steel and skids, fabrication
ENG has electrical equipment
They both have all links turned on, these need turned off
mcd plan for trench moving, not relating to Southland
Southland
MP Model connections to FW UG Stub ups
Need CWC Bypass, will they be included in the CWC Model we already have or in a separate above ground model?
Ben verified the models are good
Ben then went to stub ups and neema took the convo to RFI something, I said we were going to take a first pass at matching CWC Stub ups
Neema was talking about some kind of trnech shit moving that didn’t apply
Adam CWC said no update on the bypass for CWC
800amTXE/LEB Weekly Internal BIM Coordination | Meeting-Join | Microsoft Teams
Jay Keiser - FTI
LEB10 RO Hitting Column
LEB10 FLEX HOSE on 8" Flush skid hitting column, need to clear clashes
talked about email I sent about a list of which models to use for which trades as far as Walls, Wall Panels, Electrical, Arch, Structural etc
Kyle said he was still working on that
John Cowhey is asking about Lugs on the MES
I will chase this down, find who responded Johns email and start there
Robert Cheek responded on Monday saying he would get the answer same day, still waiting
I told Jay we are currently working through shop drawings and spools, while we are doing those we are paying attention to clashes and working through the clashes
I Brought up the FW underground being off and that we will be scanning and verifying CIA POC's, Should be doing this within a week
5/27/2026 - I BROUGHT UP LEB1 COORDINATING WITH CRIDER NO MODEL, USING HDR FOR UNDERGROUND COORDINATION
JAY BROUGHT UP TXE10 ANCHOR CLASH WITH WALL, ADAM SENT EMAIL ASKING ABOUT IT, SOMEONE SAID THEY WERE CHANGING WALL IN A EMAIL RESPONSE, ADAM REQUESTED MEETING, NO ONE RESPONDED
JAY ADDED THIS AS AN ACTION ITEM
EMMA SENT EMAIL REQUESTING CLARIFICATION, TRISTEN WAS CONFUSED
LUKE SAID HE WILL DISCUSS IN HIS MEETING WITH MORTENSON
JAY ADDED THIS AS AN ACTION ITEM
6/3/2026 - New LEB Mech and Plumbing meeting on Wed, John and Reece involved, going over FW stub up locations and F/F water gallery connections
Informed John of Convos with Greg to coordinate wall install with coring of anchor plate holes
Told Jay/John, Lance Holmes is coordinating with other trades on fix for LEB UG FW stubups not hitting POC points or dimensions
6/10/2026 - Verify Span models work on LEB10, 1, 2
6/17/2026 - Checked LEB1, Span_SS model is still only showing Labeled grids, no steel in revit linked model, 2models, same dates, different version, latest verison wont load, gives error
Bring up Walbringer as new MP contractor on LEB6, sent email out with dimension sheets for someone to get them the information
Coordination Sign off
Jay gave links to Turner and HP sign off locations
Clash Review
Jay said he will go through and filter out white noise, setup a meeting to over others. I told him whenever he wants and I will be there
Friday 6/19/22 9am
6/24/2026 - Check with Adam if he verified the lastest info from Crider lining up ug, LEB10
Check LEB1 model HDR Underground lining up with Model, We are lined up with HELM Bypass on LEB10
Luke will get with LEB and Turner for Verifying CIA Points
Louis will get with TXE and HP for Verifying CIA points
LEB6 - MP Model misalignment, I checked the Turner NWD, they are using a FTI Container that may have a misaligned MP NWC
I Put together and new NWD with current NWCs Available and everything lined up correctly
LEB, DCW Drops, Get with John to find out which way they want to go, then follow up with HDR and Helm and Waldinger
I sent John Rhee an email requesting update
7/1/2026 - Jay brought up LEB6 issue I emailed, I told them HDR still needs to update their pipe stup ups, they fixed the grid though
I brought up CIA from other GCs since they were talking about FTI Scanning HP elements, if HP didn't provide documented points what is FTI going to shoot?
Justin said yeah, it is a meta requirement but meta hasn’t really lined out what exactly is required
I told them FTI did such a great job on the document and spearheading it, I was wondering if the other GCs also maintained this document since we are connecting to systems from other trades
Jay follow up with Kyle on HP for going through HP clashing directly, can we access them, create issues, clear?
7/8/2026 - Brought up LEB10 turner models, stay with NWC, even though they have
Advised that I have moved our DCW POCs to match HELM and HDR
Advised of TXE10 Scanning schedule starting tomorrow
Waiting on Patrick B for response on HAC FCU orientation
7/15/2026 - Told Jay, I havent verified Turners FTI Container files are updated this week
TXE Told Jay, Adam noticed the Fan Coils may need rotated 180 degrees, sent email, waiting on Patrick B to look at it
Verify Bypass submittals to FTI for John Cowhey
Check LEB6 FTI Container updated
900amLightning HRV - Internal Detailing Meeting
Isabella Vesce Rivera
Bridged files from Colonial
Isabella will bring up we need bridged file
I requested to sit on base build coordination meetings with DPR/ Colonial
Adam wants form to access DPR, he will give it to all
Tomas maxell and chirdon talking to structural engineer about eliminating the middle anchor on DCB100
Adam added couplings to MSA that will allevaite having to add welds for field install
Packages were created in stratus, should be able to get dates by EOW
MSA to HAC needs some couplings removed
Depending on if Ryan can put the couplings on GMP Field because Fab is hard bid
Adam will remove from on site scope, per Ryan
Adam Dial in how we want to name NWS MSA for spool sheets
Adam wants to name them so they are more in line with the stratus packing naming
Deliverables -
Sign off and install schedule
7/15/2026
Waiting on Corbon to yay or nay the middle small anchor
MC Dean is still making adj to hac steel, they did state it shouldn't affect any of our content, ian is supposed to be complete on 9/24
Adam is supposed to put couplings in MSA to stop field weld
Need this update in stratus per Ean
All packages are created in Stratus with Dates
Get with stone and scott about getting FCU in the HAC for HRV
Southland will be running our own Clash Coordination
MC Dean provides a NWC, but we are choosing to use DPRs NWD in our own Model Coordination due to being more current and includes more trades
Keith, Melanie and Peyton will be putting this together
Melanie says not to clash with their NWD, not good
Either we will use DPR Forma Model coordination, if not available, we will ask if we can bridge their models directly to our forma to run our own Model Coordination and clashes
DCB100 NWS1/4 signoff 9/22
DCB100 NWS2/3 signoff 9/29
1000amBIM Round Up | Meeting-Join | Microsoft Teams
Michael Kolnik
Jeremy says they are supposed to be scanning in a week or 2
Jeremy needs Floor drain locations from Cerris so they know exactly where they land, Need to get with Patrick Marshall at Cerris and see if we can get some shop drawings.
6/3/2026 - MICHAEL ASKED ABOUT CURTIS GIVING HIM AN ORDER REQUEST THAT HE THOUGHT WAS SUPPOSED TO BE FOR FLUSH SKIDS
IT HAD 16X14 TEES, 14" 90S, 8" STAINLESS CAPS
HE DIDN’T KNOW WHERE THESE TEES CAME FROM
I TOLD HIM THEY WERE FOR THE MES LOOPS, NOT THE SKIDS
THE 14" 90S WERE PROBABLY FOR THE FLUSH SPOOL TO CONNECT TO THE FLEX SKID
MICHAEL SAID HE CANT GET THEM IN TIME, SIAD HE IS LOOKING AT DOING A MATERIAL SUBSTITUTE REQUEST, I SAID IT ASAP AND PUT CURTIS IN THE LOOP ON IT
6/10/2026 - Michael said he is having a meeting Friday about FW scanning and fix for fw off dims, with HP, FTI, Scanners,
6/17/2026 - Adam brought up supports, new design doesn't leave room for any adjustments
Michael says scanning will be around 7/1, if UG is off, michael says we will have to fix and charge HP
Are we going to have 8 unique supports
Paul says we will have to do it in the field
Paul and Michael agreed a new stand with Trapeze hangers will work, adam wil resubmit
Michael has order all fittings and pipe for TXE10 and TXE2 for MES loops
Region 1 is staying with 1 flush skid
2 flushes, twice as long, michael said it doesn’t schedule, not enough time for 2 flushes
6/22/2026 - Adam is telling Michael they need to create packages in stratus for how they want hac jumpers, bypasses split up
Adam is proposing a fabrication kick off meeting with Ryan and Curtis to get everyone on board
Micheal needs 8 weeks, Curtis needs 3 weeks for example
Jacob says curtis wants packages created by cost codes, but we are talking about splitting them by areas
Paul says give tom a curtisy that we are rele
Need to update the 6" flush skid and put a bleed olet on the return vertical
Paul says hes not sure where the Bypasses are as far as UG Bypass
Pual not sure when production will start for Near site, installing bypasses on HAC on near site
He will then put the spools in the appropriate package
6/30/2026 - Paul says caps are needed on MES TW and FW Ports, they can put drains on if they want
No drains on jumpers
Curtis is shipping spools to SOK
Curtis said no drains on caps, just need caps
Michael, going over spools
No Drains on jumpers
Look at TXE1-01-FWR-JMP-001, showing Flex coupling, need quick vic
Michael Ordered 16x14 tees, make sure we stayed with those and didn't update to full 16" to flush skid
7/8/2026 - Michael and Paul requested 6" and 14" Flush spools to be stainless
Sent info to Tom and Stefan, Tom says no, the flushing chemicals will clean it
7/15/2026 - Jacob says curtis put dates a month earlier than whats listed
I Told them Curtis is the one who would determine if we need to change material, stick with what he says, move the dates to 6 before install date, and get that request out, if they can't meet that, curtis will decided the next direction, weld?
Looked over installed bypasses at TXE10, everthing is off.
The Anchor plate was 5/16" off on ML1 area
1030amEMT - Mortenson BIM Coordination Meeting
Nate Black (Mortenson)
UCO3 Loop OH Coordiantion Sign off 7/24
Nate pointed to coordination models that will b
Scott asked about the container models and who is creating it
nate said if we can push our models to revizto directly, that would be great
Heath said he can do this
Need to notify heath when they
1100am-1145amHRV FSHAC Coordination
Arthur Foley (MC Dean)
Isabella Vesce Rivera, Dowoo Kim, Adam Brown, Scott
Arthur uploaded/ published new steel model to ACC, he can't see our model on his end
HRV Bim Weeklys hosted by Cameron, but its for BIM, discussing titleblocks
Danton says DPR, the engineer should be producing a federated model and coordinating a trade partner meeting
Says they will be creating a navis folder for all integrator and trade partners to pull from
Adam explained, we sit in GC1 Base build meetings along with GC3 (Faith) above ground meetings
GC1 is DPR, base build, not sure if they are using Revizto
AirUp is leading coordination for GC1
Colonial Web is doing underground, Adam already coordinated points and drawings with them
Darren says Tom Chirdon and Tom Maxwell have been sitting in meetings with Darren Ballesteros (MC Dean) Breakout mechanical meetings
We need Melanie, Ron, Heath to Go through BIM Execution plan, get contacts lined up and distributed, get model distribution set up or verified, sharing setup, need access to other trade NWCs (Desgin Arch, Struct, MP, Elect, Concrete) and Trade models, they need access to ours
Need Schedules
Submittals
Darren is Assistant PM, Arthur is HAC
Isabella Vesce Rivera is Southland PM, she asked about coordination with Colonial Web UG along with embed coordination
Ryan submitted to Dean and DPR anchor info
Corbin is structural designer, they are approving them according to Tom C
Adam is asking for concrete schedule to make sure we get them the embed info they need before pour, Ryan requested info from Curtis and DPR, said he will follow up
I brought up making sure the UG concrete trade is brought in on Embed discussions since more than likely they will be placing the embeds
7/8/2026 - Arthur said he believed the Colonial Web FW UG is installed, not backfilled
Darren and Danton are the BIM Leads for HRVs
1130amEMT - Mortenson BIM Component Call
Nate Black (Mortenson)
7/15/2026 - Cancelled
07/16/26 - THU (+8 Meetings)
630amEMT - Daily BIM Alignment
Abe Hernandez
Scott gave an overall for the MES/HAC foot clash
Melanie Working through EMT Models, links needed repathed
Go Through EMT1 and EMT2 and make sure MES, TW and MP content are good
IF good, push to Revizto
Also check MSA/FSHAC Piping
EMT Does have IFC's for Base Build, Scott showed them yesteday, I coulda swore we didn't have any sheets, prob thinking of HRV
7/16/2026 - Melanie says our MP model doesn’t line up with Eng Model, we are using Lightning Shared Coordinates, Eng is using ETM100
I told her our content, mes content lines up in revizto, if you change anything, it will no longer line up
Download arch model, link our models in and see who lines up
She says archs did change the g datum model a while back, she had to repath it and that’s when things stopped lining up correctly
630-710amLEB | BIM | Faith x Turner
Luke Jost - Joe Dorinsville
Edwin Perez from Turner hosted
5/14/26 - - Joe Brought up the access panels for Flush system, asked about rating, I would have to check submittals to verify. Me and Lance holmes informed joe the flush systems are temporary, once done, they get removed and the access panel stay
Anna said they were aware, but not the finalized locations, now they will be going through Valley for engineering, excel engineering to make sure everything is accounted for, engineered
Talked to Stefan, we are not providing the Access Panel, its GC2 wall, they are providing it
I need to check on RO system, ACCess panel and it looks like location may be borked
Scott asked about sign offs for lighting scope to base build duct connections, Joe said they havent covered it, sign off is around end of June. They will be circling back to loop area not that they have certain paperwork available
Joe said any issue can be brought up at anytime
5/21/265 - No John Rhee, Brent, Thomas Holler, NO PM TEAM
They went over stud wall model, Lance asking about raceways for security and bus ducts
5/28/2026 - They went over electrical stuff, skid placement, wall leave outs
Turner wants a meeting with Helm and Southland to go over Wall penetrations
Joe D discussed Span model naming, keeping them the same and consistant.
Will need to relink LEB Span models since they have new models with Nucor suffix
6/4/2026 - Eduardo Ibanez brought up Status of Facility Water Stubups asking if Verification of Stubups with Mortenson needed. Had Crider submitted? Lance was saying Ryan would have this info and asking if Ryan was in meeting
NO PM Team present
I sent PM Team a summary email
I explained, Ryan used HDR model for coordination, I worked with HDR to get everything line up, we provided dimensions, everyone agreed to them, now stub ups are off, Lance Resposnded to John Rhees email asking what is being done
I said we need to start having meeting to go over this issue since its so critical
Luke Jost told eduardo to add an action item for this and lance said he will head this off
6/11/2026 - I brought up the FW UG being off again, told the group Ben Kozel with crider said they were backfilling in layers and trying to get the stub ups on the POC/CIA points
Overhead Signoff is schedule for 6/30
Scott asked if it was entire building for NWB, Joe says yes
Joe Brought up IMP walls changing to Framed walls, Anna? Said it was still being worked on
Verify LEB10 POC For DCW
Verify DCW POCs line up with CIA
Lance said they are also providing a hose connection for discharge, I stated they are using the FLOOR Drains in center of gallery for discharge, Adam corrected me saying John has requested different discharge points. Wouldn've been nice to know.
Someone asked about the Flex piping from the 8" skid hitting the column, I told them it was flex pipe and temporary, that it will bend around the column
Vent in 6-19x6-D, adam told them to put in between MES Skid
Waldinger is doing the bypass on LEB6
Building 6 MES loops are showing misalignment with Waldinger Bypass
NO PM Team present
I said I would like it added to this meetings notes, Joe Dorinsville basically shut it down, saying it was a field issue
I said it was our issue also since we are constantly being asked to do overlays, which were happy to help any way we can, but this was more of a helm situation since they are the responsible party to connect to the UG and provide us with accurate points of contact according to the CIA
Joe reiterated it was a field issue
6/18/2026 - Edwin Perez is showing Verification on stub ups w mortneson needed. Pending Submittal. Eng. Drawings to be submitted - Crider and Crider. He said this is still on going
Edwins model view still shows MP Shifted to plan right, access panels were to the right of the wall they are supposed to be in
LEB6 Arch Coordination model is showing everyhting off, MES Skid not lining up, mp is to the right, access panels are to the right of the walls they are supposed to be in.
LEB10, checked with Joe D, things line up there.
6/25/2026 - Joe, Greg, Luke Long, Greg went over Electrical coordination
I sent email to PM Team, no one was present
Eduardo Ibanez brought up Status of Facility Water Stubups asking if Verification of Stubups with Mortenson needed. Had Crider submitted? He brought this up again. I explained again that we provided dimensions for LEB10 and LEB1 to Mortensen, Crider and HDR, they all agreed
I told group that I also emailed these dimensions to Waldinger for Region 2, but havent received any comments or response from anyone.
Scott asked about tracking for signoff on 6/30, eduardo said yes
Luke Jost asked about LEB10 Embeds to make sure they are getting tracked by turner
Edwin Perez asked about Waldinger Bypass and alignment to SI MES Loop Connection
I told Edwin Perez I provided poc dimensions and elevations, but havent received any response
Edwin said he will bring up in next BIM meeting
7/2/2026 - Get with john as far as who is providing what cam lock adapt for fip drops
Lance Holman also provided additional dishcharges (Drains) for Flush/ fill per john
They showed model, HDR DWC Drops are on face of column, I told group IFC shows they are on Web side, HDR Model doesn’t match HDR IFCs
John Rhee is communicating changes from model to FTI, Turner that they are not telling us, Discharge drains, DCW changes
The only reason I found out was because of the meeting flythrough, our pocs were on other side of corridor
John fucking totally ignored our information and didn't relay any information
I missed the HDR IFCs showing the drops on the plan south side of corridor
I explained LEB6 model misalignment was fixed, publishing issue, I will double check mondays model after the Saturday auto publish
I told group about the FW UG Dimension sheet that has been distributed multiple times and it details where the FW UG stubs are supposed to be ever since LEB1
I will double check LEB2 misalignment
They showed LEB6 and the 8" skids were into the columns again
I explained the deep dive I did last week, it shows everything aligned. There are issues with the FTI Container model that Turner is using for coordination
7/9/2026 - Setup LEB2 SI MP View off turner LEB2 Overall Building NWD, Crider is still off at Grid 2-50/ 2-D
Eduardo Ibanez hosted
LEB10
All Content on slab will be created in a file, progress is ongoing. Jay Asked what does this entail? Above Slab content?
LEB6
Our MP is still out of alignment in Turner LEB6 Overall Building.nwd, but Joe pulled in a recent nwd and it showed the FTI Container inside the Overall nwd is off
With joes pulled in NWD that shows us and waldinger aligned, Crider was still off around 8-10"
SI Duct and Waldinger do not align
Justin verified that Turner is using NWC files NOT the revit
Southland MP looks good
Southland MP model is still a little older, but non-critical
7/16/2026 - Joe D brought up some issue about control joints at LEB10, luke jost and jay kaiser will update as necessary
900amTXE-FTI Weekly Sync Meeting
Luke Justice
Luke was asking about scanning at TXE10, He said coordinate with Greg Hueramo, he will be setting up an origination email
I told luke they need to have all areas ready for scanning since the team cant be sent out every other day, reset up, etc
I asked for Control point map, he said get with Greg Hueramo
I explained to him what the scanning was
I told him they will need to add paul hernandex, jeremy miller and adam brown to email
John Cowhey said he has a 1 pager for Site orientation which will be 8 hours
They will be enforcing badging within the next few weeks. No badge no access, Visitor badges will be available but not allowed to work
Luke will put together a schedule for orientation
11/17/26 - is new date for 0 prep according to John Cowhey
Forward FW off email to Luke, original email was sent out 4/17. I resent to Luke Justice
I told him Jeff Balthrop was involved a few weeks back
Send Luke Discrepancy on Anchor locations with BZI Wall panels, NWCs etc from Adam email, Adam email 5/5, TXE Adam email 5/6
Verify anchors at TXE and LEB, check they've been submitted to FTI
Send notice to John Cowhey, luke justice
They asked when Southland is looking at manning the site, jeremy informed them no PM team were available at this time to answer
new schedule coming out Friday
Got with michael kolnik, he sent out Shop Drawing submittal request to Eric Boehger
5/28/2026 - Loop Keylan and Michael into the Anchor clash info and meeting for Friday
Luke says bypass are fabbed, not installed will be installed next week, sent out email to everyone, paul, jeremy, michael
Need to coordinate orientation, drug testing
Day zero schedule? Luke said he was supposed to get last Friday, not seeing anything new
Luke showed the Faith TXE Anchor Shop Drawing submittals, they are only for the TXE10,1,2 Plates don’t know why it has TXE3 on the label
Not showing any Shop drawing embed submittal info
NO PM Management was present, Keylan Rollins was for engineering
6/4/2026 - Luke Cancelled at 741am, Got DAMN MAN!!!!
6/11/2026 - Luke Cancelled at 741am, Got DAMN MAN!!!!
6/18/2026 - Luke asked about Issues, I was explaining a summary of Greg Heuromos meeting, then Michael Kolnik was there! It was nice
6/25/2026 - Michael says greg told him the bypass will be complete on 6/7, michael has scanning scheduled for 6/6
Jason with FTI will use truck to help scanning move around job
Scanners will need badges, they can be escorted according to michael who talked to security
Michael says no one onsite yet, they are on first of kind, michael and jacob did get badged
FTI does have a superintendant and a couple of upper management onsite
Fully mobilized first week of July
Luis says they have been requesting a lot of BIM information, Asbuilts, trench information, etc
Luke says a laser just got done for the Trench
Alec Harpel says first half of txe10 was scanned, still waiting for coordinates
Need FW stub ups, grounding whips and trenches
Luis is asking for points for the finish floor to verify elevation/flatness
TXE1 slab just started pouring last week, according to Luke
Micahel said they wont have water into the building, they need to truck it in and provide the minimum GPM with 3" connection
TXE10 shows 3" main with 3" drops
TXE1 shows 4" main with 3" drops
7/2/2026 - Luke Justice cancelled
7/9/2026 - Luke Justice cancelled
7/16/2026 - Keylan gave run down of Scanning and photos, scanning completed
Jacob stated carsen is locating revit files and uploading info
Should get scans by afternoon
900amEMT - Lightning Scope BIM Kickoff
Abe Hernandez (SI Senior Design Project Manager)
Heath/ Scott brough up coordination meeting
Arne Knutsen is the COORDINATION MANAGER with Peyton help
Scott brought up Keyplans off, grid bubble names are wrong
Heath and Melanie said they will be fixed
Abe in 3-4 weeks have the mofe content in the contructability models
Bring up Coordination with underground, Dim sheets issued
Schedule?
Chad Miller is over the base build Facility Underground
I need ot get them our POC Dim drawings
I brought up the CIA agreement, we need to push this hard
Melanine wants a meeting to go over model not lining up in Revizto
7/8/2026 - Adam had to attend Mid Atlantic meeting with Ean going over NWS MSA welds at HRV DCB100
UCO.3 Model coordination, Peyton not attending
Touch base with Underground Team for insuring alignment, share models and dimension shop drawings
Scott had to bring up misalinged sign off dates that Abe had, why isn't david on top of this
Peyton did show up late, I sent him a teams link and notice that the meeting was going on
Where is Tom Chirdon
Clash Detection using Forma, per Peyton,
Peyton confirmed he will be hosting a coordination meeting
Abe said he will give up the remainder of this meeting to peyton for clash issues once peython has the model setup
Wed at 1130 Mortenson Coordination meetings with underground
930amLEB | BIM COORDINATION LEB2
Emma will no longer be on this project
Kaushal Bagdekar with Turner ran the meeting, saying who to contact for what, I asked if he could send an email with that info
They went over underground clashes
5/28/2026 - Tristen with helm verified he is using LEB1 dimensions for LEB 2 elevations and locaitons for FW
6/11/2026 - No PM Team
Went Over UG issues, concrete pads
6/18/2026 - Kaushal Bagdekar
Did a flythrough for LEB2 going over exterior sectionalizers
LEB-2_SPAN_SS.rvt, verifying during meeting that the model is good, Checked LEB2 SPAN_SS model, couldn’t load content, says cant link in NuCOR
NO Interior Walls and framing, Valley, Diogo or Ruth said they will get with valley
No Interior Meta Wall Panels
6/25/2026 - NO PM TEAM
They went over UG issues for LEB2
7/2/2026 - LEB2, Showed model where Helm, SI and Crider not aligned, #2070
LEB2 Building Overall actually has Crider model, showing misaligned
Grid 1-50, 1-D is the only spot where Crider is off looking at Turners LEB2_Building_Overall model only
Everything else is aligned, MP, Duct, Steel, Walls, no issues
Sent email showing misaligned concrete and crider stub ups at 2-50
LEB-SI-MP-LEB2-R25 model lined up identical to LEB2-Building-Overall
Didn't see new DCW POC valves, did I update LEB2
Did see FLUSH VENTS AND DRAINS, VENT ON 2-50 IS OFF
7/9/2026 - Sent Email to Joe, Jay, Edwin, Eduardo and Joe forwarded to Kaushal
Kaushal asked about flush skids in front of door ways, need to send them a time frame for flushing before equipment gets removed
Concrete elevations different at Gird 2-29 and 2-32
Crider stub ups off at 2-50/2-D
Added to chat
7/16/2026 - Sent email to Triston with Jay and Kaushal cc'd about Helm bypass flanges not aligning to SI MP Flanges throughout building
LEB2 looked like it aligned good
1000 amLEB - BIM Coordination Meeting (Thu) | Meeting-Join | Microsoft Teams
Ryan Zoldan
LEB 6 due finalized next week
I requested a schedule from Ryan, he has the sign off, region schedule, I brought up a pull plan, be he says that will be through Turner
Mortensen is the Base build GC, why aren't they leading a pull plan schedule
John Rhee nor Brent were in this meeting
6/4/2026 - I brought up the LEB10 FW UG Stub ups totally missing the Dims, Ben Kozel was there and he stated they are bringing them back in to dimensions by backfilling a little and moving them, backfilling and moving them
He acknowledge that lance did contact him
6/11/2026 - Ben Kozel, said there were no issues that need to be talked about.
Richard lopez asked around the room for any issues regarding LEB10 or any others
NO PM Team
6/18/2026 - Richard Lopez Hosted, just asked for any issues with LEB10,1,2,3 Underground issues
Rantwiler asked when IWM for TXE10 was going to be signed off, Ethan says he will talke to kyle since they are not really split out
6/25/2026 - Going over LEB7,8
Ryan brought up LEB6, HDR model is not lining up with the Dimensions provided by SI
Ryan henderson said he will follow up
Ryan said we have all agreed to follow these dimesions, I added that I have distrubuted that dimesion sheet ot Waldinger and explained everything, but havent received a response yet
Ryan brought up LEB6, HDR model is not lining up and my email I sent out
I updated, still waiting for HDR to align the stubups
Ryan said Crider is using civil 3d, but we can work it out to actually use their model for coordination and linking in so I don't have to use HDR
7/9/2026 - No issues to cover, they went over UG clashing for elect, sanitary
TXE1 looks good for the loop area sign off next week
Same with TXE2
6/4/2026 - Own B ran the meeting going over TXE1 and 2
6/11/2026 - Owen B, says TXE10 Loop for sign off
TXE2 Core scheduled for next week
TXE10 AB Datahall and Loop are signed off
TXE3 Alan lopez is running region 2 for signe off
TXE2 Loop and AB South sign off
issue 2602 - Cerris Vent in corner is clashing with Technical water, Rantwiler is saying they don’t have our model, I told them our model has been there for 6 months, the fact that HP is viewing it, means the model is available. If it’s a bridging issue we will help Cerris work it out
Trevor said he will get with rantwiler and get the model bridged, they will offset that vent around our TW Piping
They made comments about the TW skid being so close to the FW valves. Its been this way for over 6 months. Trevor also stated the vent will need an accessible cleanout
6/25/2026 - They just went over IWM and specific Electrical clashes
7/9/2026 - TXE 2 all docs are out, all sign offs are out
TXE1, 2 sign offs left
DHCD 2 weeks from now
1130amLightning HRV - Global BIM Coordination Meeting
Isabella Vesce Rivera (SI)
Is there a coordination model we get access to? Revizto? Navis?
Get input on HDR Mockup I made for FW UG Stubup, Bypass and MES Loop connections
Colonial was trying to align to SI Desing model, that was all that was available for the bridging
Seth Blizzard says they arent obligated to meet our POC's, they follow the ARUP design. ARUP did let them know they are contracted to meet our POC's
Curtis Robbins said he just needs to click a button to enable the bridging to our actual Coordination Models
Seth started making comments about use being able to shift our pipes 3", I told them theres a lot more going on that what they were showing with our Engineered anchors, flush connections, MES and TWMU skids and TW Piping, there isnt much forgiveness
Still don’t have access to bridged Colonial files
07/17/26 - FRI (+1 Meetings)
630amEMT - Daily BIM Alignment
Abe Hernandez
Scott gave an overall for the MES/HAC foot clash
Melanie Working through EMT Models, links needed repathed
Go Through EMT1 and EMT2 and make sure MES, TW and MP content are good
IF good, push to Revizto
Also check MSA/FSHAC Piping
EMT Does have IFC's for Base Build, Scott showed them yesteday, I coulda swore we didn't have any sheets, prob thinking of HRV
7/16/2026 - Melanie says our MP model doesn’t line up with Eng Model, we are using Lightning Shared Coordinates, Eng is using ETM100
Abe - Attached Sign off schedule to summary email, have content populated and coordinated ahead of signoff dates highlighted in RED, these dates line up with Mortenson
I told her our content, mes content lines up in revizto, if you change anything, it will no longer line up
Download arch model, link our models in and see who lines up
She says archs did change the g datum model a while back, she had to repath it and that’s when things stopped lining up correctly
7/17/2026 - Cancelled
7/6/26 - 7/12/26
07/06/26 - MON (+3 Meetings)
700amLightning Ketchup
Adam Brown
900amLightning TXE Staff Meeting | Meeting-Join | Microsoft Teams
Jacob Gelhousen
Will do scans after Cerris installs bypasses
6/1/2026 - Noel Nunez says Alehandro Chew will be safety manager
Michael said he sent TXE3 embeds along with PDF dimension in mid April
Doesn’t think TXE3 has been poured, think they are behind schedule
Says we havent been funded for Region 2, he is sending out embeds as needed
Michael asked what the question was about RO and TW, I said it was going over how to connect to the RO skid, from DCW and to TW MES
Michael asked if MES Loops were completed, adam said yes, he created new BOMs
Michael said his goal is to get everything ordered
Michale Paul said they thought the walls weren't going to be in until they could do anchor
They said that was what was agreed to
6/8/2026 - Michael said they had a PM Coins Mandatory meeting and couldn't host the meeting
6/15/2026 - Chris Moss came on board from TSMC, Pipe fitter, GF
Jose Alejandro Chew, new Safety Manager for TXE
6/22/2026 - Shop drawings (Engineer Drawings) looking at submittal on Frid, 6/26
6/29/2026 - Keylan Cancelled
7/6/2026 - Carson will scan on Thursday
1130amMW Detailing Weekly Meeting
6/29/2026 - Marshall Cancelled
07/07/26 - TUE (+5 Meetings)
800amWeekly BIM Coordination Meeting - Region 2 (ZOOM)
Alan Lopez, Kyle Cummings (Hensel Phelps) / Ethen Berry
No one started the meeting, I sent an email, they said Alan was PTO and they started meeting late
They went over Region 2 underground, sign off later this week
5/26/26 - Allen Lopez Went over Region 2 again, said they were going to do a main signoff then a branch signoff. Covered a lot of UG clashes
6/2/2026
2 weeks sign off branch
6/9/2026
6/16/2026
Allen Lopez says he doesn't see Sure Steel model in TXE3, Kyle says also no Diversified, but Sure Steel model is there, needs added
Signoff schedule was not bridged, the one on FTI is outdated. Kyle and Justin said they would get the bridge up to date
Files - Data Management
6/23/2026
6/30/2026
7/7/2026
TXE3 Overhead Loop signoff next week
TXE3 Overhead Datahall signoff is July 27th
830amLEB - BIM Coordination Meeting (Tue) | Meeting-Join | Microsoft Teams
Ryan Zoldan, Mortenson (GC1)
Missed for the 8am meeting
6/16/2026
6/23/2026
6/30/2026
7/7/2026
Ryan brought up their grids were off, crider and crider will be aligned today and HDR will be aligned. For LEB6
1000amLightning-Eng-Coord Huddle | Meeting-Join | Microsoft Teams
Tia/ Tom
Follow up on HAC Panel clashes with Patrick Brinnehal
Meeting to go over stratus and models with all PMs, Adam, Scott, Supers sometime next week, look at schedules
Chris Chase is the PM of EMT
5/26/2026 - Check if Adam got the 4" Welded Bypass to Shop, from 5/5/25 email in Inbox "Im shooting to have the LTG build out scope package done by end of week (For Review only not for construction). "
Verify what spools have been put on stratus for TIA/TOM Lightning huddle
Need meeting to discuss, txe10 anchor clashing with interior of walls, adam sent info out about conflicting models, but as of today, there is still clashes
RFI says they are changing wall to Gypsm board and expanding toward corridor 2.5"
6/2/2026 - We did get 2 more sites in Ohio
SI will be integrator
Heath introduced Peyton Steveons as VDC supervisor
Starting with HRV
Melanie introduced Vasi, VDC specialist helping out ron and melanie
Tia went over deliverable schedules
Per site, per building
She setup a break out meeting
Adam said they are moving the walls away from anchors so we are clear
Adam said we are 1/2" clear from plate, it will be a field issue installing the plate
Michael said he will talk to paul, he doesn't know what to do, he will call greg
only 2 walls changed from IMP, 2 others are still IMP
Michael said Greg told him they are putting walls up next week
Told Tia I sent snip of Dog Leg Metraflex in chat, didn’t get any smiles
Let her know we have LEB complete, TXE10,1,2 is complete
Adam said he will give link to CIAs, TXE3-12 and LEB3-12 not ready
Adam had meeting with HRV, told them to start using our coordination models for coordination
Quick hello, this is who we are meeting
with MC Dean
Mealnie says they will be updating projects to new architect model
Type F - 4 buildings
Type G - 2 buildings
6/9/2026 - Adam said they are going to move the MSA, HAC spools to the Lighting Program, for one source
Melanie and Keylan said it can be done
6/30/2026 - FTI wants scanners badged
TXE1 special Support approved
H Support hanger, supposed to get stamped this week
HRV supposed to get linked in models setup so we can coordinate ug
Need to verify LEB and TXE CIA points
SS Headers are in fab per EAN
John Rhee asked about Waldinger misaligned, we are now good, sending email showing HDR is off
Toms Eng review comments will be looking at doing updates next week
HRV Embed Dims, ryan says he has, I have Angle working on them now, wtf?!!!
PIQ, melanie is setting up, I asked her to keep an eye out for the BIM ex plan and contact list
Michael said they have drug test this week, orientation on Monday
7/7/2026 - Cancelled
1100amLEB Clash Sync With Jay
7/7/2026 - Touched based on LEB10, Cleared FTI ACC Clashes, I need to go through Turner ACC and check for clashes
1200pmTXE-Region3 Coordination Meeting
Jade B Lowe (Hensel Phelps)
Jade is in charge of Region 3
Kyle cummins is in charge of site
Filll out contact excel sheet, put bim lead and project manager
Kyle - LOD 450 project, all installed elements are modeled, then asbuilts are fed back in to model
Indicate in the model some where that the asbuilt has been applied and model has been adjusted
6/16/2026 - Decided not to go to this one since its Region 3, TXE6,7 undergound
07/08/26 - WED (+7 Meetings)
700amEMT - Lightning Scope BIM Kickoff
Abe Hernandez (SI Senior Design Project Manager)
Heath/ Scott brough up coordination meeting
Arne Knutsen is the COORDINATION MANAGER with Peyton help
Scott brought up Keyplans off, grid bubble names are wrong
Heath and Melanie said they will be fixed
Abe in 3-4 weeks have the mofe content in the contructability models
Bring up Coordination with underground, Dim sheets issued
Schedule?
Chad Miller is over the base build Facility Underground
I need ot get them our POC Dim drawings
I brought up the CIA agreement, we need to push this hard
Melanine wants a meeting to go over model not lining up in Revizto
7/8/2026 - Adam had to attend Mid Atlantic meeting with Ean going over NWS MSA welds at HRV DCB100
UCO.3 Model coordination, Peyton not attending
Touch base with Underground Team for insuring alignment, share models and dimension shop drawings
Scott had to bring up misalinged sign off dates that Abe had, why isn't david on top of this
Peyton did show up late, I sent him a teams link and notice that the meeting was going on
Where is Tom Chirdon
Clash Detection using Forma, per Peyton,
Peyton confirmed he will be hosting a coordination meeting
Abe said he will give up the remainder of this meeting to peyton for clash issues once peython has the model setup
Wed at 1130 Mortenson Coordination meetings with underground
800amTXE/LEB Weekly Internal BIM Coordination | Meeting-Join | Microsoft Teams
Jay Keiser - FTI
LEB10 RO Hitting Column
LEB10 FLEX HOSE on 8" Flush skid hitting column, need to clear clashes
talked about email I sent about a list of which models to use for which trades as far as Walls, Wall Panels, Electrical, Arch, Structural etc
Kyle said he was still working on that
John Cowhey is asking about Lugs on the MES
I will chase this down, find who responded Johns email and start there
Robert Cheek responded on Monday saying he would get the answer same day, still waiting
I told Jay we are currently working through shop drawings and spools, while we are doing those we are paying attention to clashes and working through the clashes
I Brought up the FW underground being off and that we will be scanning and verifying CIA POC's, Should be doing this within a week
5/27/2026 - I BROUGHT UP LEB1 COORDINATING WITH CRIDER NO MODEL, USING HDR FOR UNDERGROUND COORDINATION
JAY BROUGHT UP TXE10 ANCHOR CLASH WITH WALL, ADAM SENT EMAIL ASKING ABOUT IT, SOMEONE SAID THEY WERE CHANGING WALL IN A EMAIL RESPONSE, ADAM REQUESTED MEETING, NO ONE RESPONDED
JAY ADDED THIS AS AN ACTION ITEM
EMMA SENT EMAIL REQUESTING CLARIFICATION, TRISTEN WAS CONFUSED
LUKE SAID HE WILL DISCUSS IN HIS MEETING WITH MORTENSON
JAY ADDED THIS AS AN ACTION ITEM
6/3/2026 - New LEB Mech and Plumbing meeting on Wed, John and Reece involved, going over FW stub up locations and F/F water gallery connections
Informed John of Convos with Greg to coordinate wall install with coring of anchor plate holes
Told Jay/John, Lance Holmes is coordinating with other trades on fix for LEB UG FW stubups not hitting POC points or dimensions
6/10/2026 - Verify Span models work on LEB10, 1, 2
6/17/2026 - Checked LEB1, Span_SS model is still only showing Labeled grids, no steel in revit linked model, 2models, same dates, different version, latest verison wont load, gives error
Bring up Walbringer as new MP contractor on LEB6, sent email out with dimension sheets for someone to get them the information
Coordination Sign off
Jay gave links to Turner and HP sign off locations
Clash Review
Jay said he will go through and filter out white noise, setup a meeting to over others. I told him whenever he wants and I will be there
Friday 6/19/22 9am
6/24/2026 - Check with Adam if he verified the lastest info from Crider lining up ug, LEB10
Check LEB1 model HDR Underground lining up with Model, We are lined up with HELM Bypass on LEB10
Luke will get with LEB and Turner for Verifying CIA Points
Louis will get with TXE and HP for Verifying CIA points
LEB6 - MP Model misalignment, I checked the Turner NWD, they are using a FTI Container that may have a misaligned MP NWC
I Put together and new NWD with current NWCs Available and everything lined up correctly
LEB, DCW Drops, Get with John to find out which way they want to go, then follow up with HDR and Helm and Waldinger
I sent John Rhee an email requesting update
7/1/2026 - Jay brought up LEB6 issue I emailed, I told them HDR still needs to update their pipe stup ups, they fixed the grid though
I brought up CIA from other GCs since they were talking about FTI Scanning HP elements, if HP didn't provide documented points what is FTI going to shoot?
Justin said yeah, it is a meta requirement but meta hasn’t really lined out what exactly is required
I told them FTI did such a great job on the document and spearheading it, I was wondering if the other GCs also maintained this document since we are connecting to systems from other trades
Jay follow up with Kyle on HP for going through HP clashing directly, can we access them, create issues, clear?
7/8/2026 - Brought up LEB10 turner models, stay with NWC, even though they have
Advised that I have moved our DCW POCs to match HELM and HDR
Advised of TXE10 Scanning schedule starting tomorrow
Waiting on Patrick B for response on HAC FCU orientation
900amLightning HRV - Internal Detailing Meeting
Isabella Vesce Rivera
Bridged files from Colonial
Isabella will bring up we need bridged file
I requested to sit on base build coordination meetings with DPR/ Colonial
Adam wants form to access DPR, he will give it to all
Tomas maxell and chirdon talking to structural engineer about eliminating the middle anchor on DCB100
Adam added couplings to MSA that will allevaite having to add welds for field install
Packages were created in stratus, should be able to get dates by EOW
MSA to HAC needs some couplings removed
Depending on if Ryan can put the couplings on GMP Field because Fab is hard bid
Adam will remove from on site scope, per Ryan
Adam Dial in how we want to name NWS MSA for spool sheets
Adam wants to name them so they are more in line with the stratus packing naming
Deliverables -
Sign off and install schedule
1000amBIM Round Up | Meeting-Join | Microsoft Teams
Michael Kolnik
Jeremy says they are supposed to be scanning in a week or 2
Jeremy needs Floor drain locations from Cerris so they know exactly where they land, Need to get with Patrick Marshall at Cerris and see if we can get some shop drawings.
6/3/2026 - MICHAEL ASKED ABOUT CURTIS GIVING HIM AN ORDER REQUEST THAT HE THOUGHT WAS SUPPOSED TO BE FOR FLUSH SKIDS
IT HAD 16X14 TEES, 14" 90S, 8" STAINLESS CAPS
HE DIDN’T KNOW WHERE THESE TEES CAME FROM
I TOLD HIM THEY WERE FOR THE MES LOOPS, NOT THE SKIDS
THE 14" 90S WERE PROBABLY FOR THE FLUSH SPOOL TO CONNECT TO THE FLEX SKID
MICHAEL SAID HE CANT GET THEM IN TIME, SIAD HE IS LOOKING AT DOING A MATERIAL SUBSTITUTE REQUEST, I SAID IT ASAP AND PUT CURTIS IN THE LOOP ON IT
6/10/2026 - Michael said he is having a meeting Friday about FW scanning and fix for fw off dims, with HP, FTI, Scanners,
6/17/2026 - Adam brought up supports, new design doesn't leave room for any adjustments
Michael says scanning will be around 7/1, if UG is off, michael says we will have to fix and charge HP
Are we going to have 8 unique supports
Paul says we will have to do it in the field
Paul and Michael agreed a new stand with Trapeze hangers will work, adam wil resubmit
Michael has order all fittings and pipe for TXE10 and TXE2 for MES loops
Region 1 is staying with 1 flush skid
2 flushes, twice as long, michael said it doesn’t schedule, not enough time for 2 flushes
6/22/2026 - Adam is telling Michael they need to create packages in stratus for how they want hac jumpers, bypasses split up
Adam is proposing a fabrication kick off meeting with Ryan and Curtis to get everyone on board
Micheal needs 8 weeks, Curtis needs 3 weeks for example
Jacob says curtis wants packages created by cost codes, but we are talking about splitting them by areas
Paul says give tom a curtisy that we are rele
Need to update the 6" flush skid and put a bleed olet on the return vertical
Paul says hes not sure where the Bypasses are as far as UG Bypass
Pual not sure when production will start for Near site, installing bypasses on HAC on near site
He will then put the spools in the appropriate package
6/30/2026 - Paul says caps are needed on MES TW and FW Ports, they can put drains on if they want
No drains on jumpers
Curtis is shipping spools to SOK
Curtis said no drains on caps, just need caps
Michael, going over spools
No Drains on jumpers
Look at TXE1-01-FWR-JMP-001, showing Flex coupling, need quick vic
Michael Ordered 16x14 tees, make sure we stayed with those and didn't update to full 16" to flush skid
7/8/2026 - Michael and Paul requested 6" and 14" Flush spools to be stainless
Sent info to Tom and Stefan, Tom says no, the flushing chemicals will clean it
1030amEMT - Mortenson BIM Coordination Meeting
Nate Black (Mortenson)
UCO3 Loop OH Coordiantion Sign off 7/24
Nate pointed to coordination models that will b
Scott asked about the container models and who is creating it
nate said if we can push our models to revizto directly, that would be great
Heath said he can do this
Need to notify heath when they
1100am-1145amHRV FSHAC Coordination
Arthur Foley (MC Dean)
Isabella Vesce Rivera, Dowoo Kim, Adam Brown, Scott
Arthur uploaded/ published new steel model to ACC, he can't see our model on his end
HRV Bim Weeklys hosted by Cameron, but its for BIM, discussing titleblocks
Danton says DPR, the engineer should be producing a federated model and coordinating a trade partner meeting
Says they will be creating a navis folder for all integrator and trade partners to pull from
Adam explained, we sit in GC1 Base build meetings along with GC3 (Faith) above ground meetings
GC1 is DPR, base build, not sure if they are using Revizto
AirUp is leading coordination for GC1
Colonial Web is doing underground, Adam already coordinated points and drawings with them
Darren says Tom Chirdon and Tom Maxwell have been sitting in meetings with Darren Ballesteros (MC Dean) Breakout mechanical meetings
We need Melanie, Ron, Heath to Go through BIM Execution plan, get contacts lined up and distributed, get model distribution set up or verified, sharing setup, need access to other trade NWCs (Desgin Arch, Struct, MP, Elect, Concrete) and Trade models, they need access to ours
Need Schedules
Submittals
Darren is Assistant PM, Arthur is HAC
Isabella Vesce Rivera is Southland PM, she asked about coordination with Colonial Web UG along with embed coordination
Ryan submitted to Dean and DPR anchor info
Corbin is structural designer, they are approving them according to Tom C
Adam is asking for concrete schedule to make sure we get them the embed info they need before pour, Ryan requested info from Curtis and DPR, said he will follow up
I brought up making sure the UG concrete trade is brought in on Embed discussions since more than likely they will be placing the embeds
7/8/2026 - Arthur said he believed the Colonial Web FW UG is installed, not backfilled
Darren and Danton are the BIM Leads for HRVs
1130amEMT - Mortenson BIM Component Call
Nate Black (Mortenson)
07/09/26 - THU (+6 Meetings)
630-710amLEB | BIM | Faith x Turner
Luke Jost - Joe Dorinsville
Edwin Perez from Turner hosted
5/14/26 - - Joe Brought up the access panels for Flush system, asked about rating, I would have to check submittals to verify. Me and Lance holmes informed joe the flush systems are temporary, once done, they get removed and the access panel stay
Anna said they were aware, but not the finalized locations, now they will be going through Valley for engineering, excel engineering to make sure everything is accounted for, engineered
Talked to Stefan, we are not providing the Access Panel, its GC2 wall, they are providing it
I need to check on RO system, ACCess panel and it looks like location may be borked
Scott asked about sign offs for lighting scope to base build duct connections, Joe said they havent covered it, sign off is around end of June. They will be circling back to loop area not that they have certain paperwork available
Joe said any issue can be brought up at anytime
5/21/265 - No John Rhee, Brent, Thomas Holler, NO PM TEAM
They went over stud wall model, Lance asking about raceways for security and bus ducts
5/28/2026 - They went over electrical stuff, skid placement, wall leave outs
Turner wants a meeting with Helm and Southland to go over Wall penetrations
Joe D discussed Span model naming, keeping them the same and consistant.
Will need to relink LEB Span models since they have new models with Nucor suffix
6/4/2026 - Eduardo Ibanez brought up Status of Facility Water Stubups asking if Verification of Stubups with Mortenson needed. Had Crider submitted? Lance was saying Ryan would have this info and asking if Ryan was in meeting
NO PM Team present
I sent PM Team a summary email
I explained, Ryan used HDR model for coordination, I worked with HDR to get everything line up, we provided dimensions, everyone agreed to them, now stub ups are off, Lance Resposnded to John Rhees email asking what is being done
I said we need to start having meeting to go over this issue since its so critical
Luke Jost told eduardo to add an action item for this and lance said he will head this off
6/11/2026 - I brought up the FW UG being off again, told the group Ben Kozel with crider said they were backfilling in layers and trying to get the stub ups on the POC/CIA points
Overhead Signoff is schedule for 6/30
Scott asked if it was entire building for NWB, Joe says yes
Joe Brought up IMP walls changing to Framed walls, Anna? Said it was still being worked on
Verify LEB10 POC For DCW
Verify DCW POCs line up with CIA
Lance said they are also providing a hose connection for discharge, I stated they are using the FLOOR Drains in center of gallery for discharge, Adam corrected me saying John has requested different discharge points. Wouldn've been nice to know.
Someone asked about the Flex piping from the 8" skid hitting the column, I told them it was flex pipe and temporary, that it will bend around the column
Vent in 6-19x6-D, adam told them to put in between MES Skid
Waldinger is doing the bypass on LEB6
Building 6 MES loops are showing misalignment with Waldinger Bypass
NO PM Team present
I said I would like it added to this meetings notes, Joe Dorinsville basically shut it down, saying it was a field issue
I said it was our issue also since we are constantly being asked to do overlays, which were happy to help any way we can, but this was more of a helm situation since they are the responsible party to connect to the UG and provide us with accurate points of contact according to the CIA
Joe reiterated it was a field issue
6/18/2026 - Edwin Perez is showing Verification on stub ups w mortneson needed. Pending Submittal. Eng. Drawings to be submitted - Crider and Crider. He said this is still on going
Edwins model view still shows MP Shifted to plan right, access panels were to the right of the wall they are supposed to be in
LEB6 Arch Coordination model is showing everyhting off, MES Skid not lining up, mp is to the right, access panels are to the right of the walls they are supposed to be in.
LEB10, checked with Joe D, things line up there.
6/25/2026 - Joe, Greg, Luke Long, Greg went over Electrical coordination
I sent email to PM Team, no one was present
Eduardo Ibanez brought up Status of Facility Water Stubups asking if Verification of Stubups with Mortenson needed. Had Crider submitted? He brought this up again. I explained again that we provided dimensions for LEB10 and LEB1 to Mortensen, Crider and HDR, they all agreed
I told group that I also emailed these dimensions to Waldinger for Region 2, but havent received any comments or response from anyone.
Scott asked about tracking for signoff on 6/30, eduardo said yes
Luke Jost asked about LEB10 Embeds to make sure they are getting tracked by turner
Edwin Perez asked about Waldinger Bypass and alignment to SI MES Loop Connection
I told Edwin Perez I provided poc dimensions and elevations, but havent received any response
Edwin said he will bring up in next BIM meeting
7/2/2026 - Get with john as far as who is providing what cam lock adapt for fip drops
Lance Holman also provided additional dishcharges (Drains) for Flush/ fill per john
They showed model, HDR DWC Drops are on face of column, I told group IFC shows they are on Web side, HDR Model doesn’t match HDR IFCs
John Rhee is communicating changes from model to FTI, Turner that they are not telling us, Discharge drains, DCW changes
The only reason I found out was because of the meeting flythrough, our pocs were on other side of corridor
John fucking totally ignored our information and didn't relay any information
I missed the HDR IFCs showing the drops on the plan south side of corridor
I explained LEB6 model misalignment was fixed, publishing issue, I will double check mondays model after the Saturday auto publish
I told group about the FW UG Dimension sheet that has been distributed multiple times and it details where the FW UG stubs are supposed to be ever since LEB1
I will double check LEB2 misalignment
They showed LEB6 and the 8" skids were into the columns again
I explained the deep dive I did last week, it shows everything aligned. There are issues with the FTI Container model that Turner is using for coordination
7/9/2026 - Setup LEB2 SI MP View off turner LEB2 Overall Building NWD, Crider is still off at Grid 2-50/ 2-D
Eduardo Ibanez hosted
LEB10
All Content on slab will be created in a file, progress is ongoing. Jay Asked what does this entail? Above Slab content?
LEB6
Our MP is still out of alignment in Turner LEB6 Overall Building.nwd, but Joe pulled in a recent nwd and it showed the FTI Container inside the Overall nwd is off
With joes pulled in NWD that shows us and waldinger aligned, Crider was still off around 8-10"
SI Duct and Waldinger do not align
Justin verified that Turner is using NWC files NOT the revit
Southland MP looks good
Southland MP model is still a little older, but non-critical
900amTXE-FTI Weekly Sync Meeting
Luke Justice
Luke was asking about scanning at TXE10, He said coordinate with Greg Hueramo, he will be setting up an origination email
I told luke they need to have all areas ready for scanning since the team cant be sent out every other day, reset up, etc
I asked for Control point map, he said get with Greg Hueramo
I explained to him what the scanning was
I told him they will need to add paul hernandex, jeremy miller and adam brown to email
John Cowhey said he has a 1 pager for Site orientation which will be 8 hours
They will be enforcing badging within the next few weeks. No badge no access, Visitor badges will be available but not allowed to work
Luke will put together a schedule for orientation
11/17/26 - is new date for 0 prep according to John Cowhey
Forward FW off email to Luke, original email was sent out 4/17. I resent to Luke Justice
I told him Jeff Balthrop was involved a few weeks back
Send Luke Discrepancy on Anchor locations with BZI Wall panels, NWCs etc from Adam email, Adam email 5/5, TXE Adam email 5/6
Verify anchors at TXE and LEB, check they've been submitted to FTI
Send notice to John Cowhey, luke justice
They asked when Southland is looking at manning the site, jeremy informed them no PM team were available at this time to answer
new schedule coming out Friday
Got with michael kolnik, he sent out Shop Drawing submittal request to Eric Boehger
5/28/2026 - Loop Keylan and Michael into the Anchor clash info and meeting for Friday
Luke says bypass are fabbed, not installed will be installed next week, sent out email to everyone, paul, jeremy, michael
Need to coordinate orientation, drug testing
Day zero schedule? Luke said he was supposed to get last Friday, not seeing anything new
Luke showed the Faith TXE Anchor Shop Drawing submittals, they are only for the TXE10,1,2 Plates don’t know why it has TXE3 on the label
Not showing any Shop drawing embed submittal info
NO PM Management was present, Keylan Rollins was for engineering
6/4/2026 - Luke Cancelled at 741am, Got DAMN MAN!!!!
6/11/2026 - Luke Cancelled at 741am, Got DAMN MAN!!!!
6/18/2026 - Luke asked about Issues, I was explaining a summary of Greg Heuromos meeting, then Michael Kolnik was there! It was nice
6/25/2026 - Michael says greg told him the bypass will be complete on 6/7, michael has scanning scheduled for 6/6
Jason with FTI will use truck to help scanning move around job
Scanners will need badges, they can be escorted according to michael who talked to security
Michael says no one onsite yet, they are on first of kind, michael and jacob did get badged
FTI does have a superintendant and a couple of upper management onsite
Fully mobilized first week of July
Luis says they have been requesting a lot of BIM information, Asbuilts, trench information, etc
Luke says a laser just got done for the Trench
Alec Harpel says first half of txe10 was scanned, still waiting for coordinates
Need FW stub ups, grounding whips and trenches
Luis is asking for points for the finish floor to verify elevation/flatness
TXE1 slab just started pouring last week, according to Luke
Micahel said they wont have water into the building, they need to truck it in and provide the minimum GPM with 3" connection
TXE10 shows 3" main with 3" drops
TXE1 shows 4" main with 3" drops
7/2/2026 - Luke Justice cancelled
7/9/2026 - Luke Justice cancelled
930amLEB | BIM COORDINATION LEB2
Emma will no longer be on this project
Kaushal Bagdekar with Turner ran the meeting, saying who to contact for what, I asked if he could send an email with that info
They went over underground clashes
5/28/2026 - Tristen with helm verified he is using LEB1 dimensions for LEB 2 elevations and locaitons for FW
6/11/2026 - No PM Team
Went Over UG issues, concrete pads
6/18/2026 - Kaushal Bagdekar
Did a flythrough for LEB2 going over exterior sectionalizers
LEB-2_SPAN_SS.rvt, verifying during meeting that the model is good, Checked LEB2 SPAN_SS model, couldn’t load content, says cant link in NuCOR
NO Interior Walls and framing, Valley, Diogo or Ruth said they will get with valley
No Interior Meta Wall Panels
6/25/2026 - NO PM TEAM
They went over UG issues for LEB2
7/2/2026 - LEB2, Showed model where Helm, SI and Crider not aligned, #2070
LEB2 Building Overall actually has Crider model, showing misaligned
Grid 1-50, 1-D is the only spot where Crider is off looking at Turners LEB2_Building_Overall model only
Everything else is aligned, MP, Duct, Steel, Walls, no issues
Sent email showing misaligned concrete and crider stub ups at 2-50
LEB-SI-MP-LEB2-R25 model lined up identical to LEB2-Building-Overall
Didn't see new DCW POC valves, did I update LEB2
Did see FLUSH VENTS AND DRAINS, VENT ON 2-50 IS OFF
7/9/2026 - Sent Email to Joe, Jay, Edwin, Eduardo and Joe forwarded to Kaushal
Kaushal asked about flush skids in front of door ways, need to send them a time frame for flushing before equipment gets removed
Concrete elevations different at Gird 2-29 and 2-32
Crider stub ups off at 2-50/2-D
Added to chat
1000 amLEB - BIM Coordination Meeting (Thu) | Meeting-Join | Microsoft Teams
Ryan Zoldan
LEB 6 due finalized next week
I requested a schedule from Ryan, he has the sign off, region schedule, I brought up a pull plan, be he says that will be through Turner
Mortensen is the Base build GC, why aren't they leading a pull plan schedule
John Rhee nor Brent were in this meeting
6/4/2026 - I brought up the LEB10 FW UG Stub ups totally missing the Dims, Ben Kozel was there and he stated they are bringing them back in to dimensions by backfilling a little and moving them, backfilling and moving them
He acknowledge that lance did contact him
6/11/2026 - Ben Kozel, said there were no issues that need to be talked about.
Richard lopez asked around the room for any issues regarding LEB10 or any others
NO PM Team
6/18/2026 - Richard Lopez Hosted, just asked for any issues with LEB10,1,2,3 Underground issues
Rantwiler asked when IWM for TXE10 was going to be signed off, Ethan says he will talke to kyle since they are not really split out
6/25/2026 - Going over LEB7,8
Ryan brought up LEB6, HDR model is not lining up with the Dimensions provided by SI
Ryan henderson said he will follow up
Ryan said we have all agreed to follow these dimesions, I added that I have distrubuted that dimesion sheet ot Waldinger and explained everything, but havent received a response yet
Ryan brought up LEB6, HDR model is not lining up and my email I sent out
I updated, still waiting for HDR to align the stubups
Ryan said Crider is using civil 3d, but we can work it out to actually use their model for coordination and linking in so I don't have to use HDR
7/9/2026 - No issues to cover, they went over UG clashing for elect, sanitary
TXE1 looks good for the loop area sign off next week
Same with TXE2
6/4/2026 - Own B ran the meeting going over TXE1 and 2
6/11/2026 - Owen B, says TXE10 Loop for sign off
TXE2 Core scheduled for next week
TXE10 AB Datahall and Loop are signed off
TXE3 Alan lopez is running region 2 for signe off
TXE2 Loop and AB South sign off
issue 2602 - Cerris Vent in corner is clashing with Technical water, Rantwiler is saying they don’t have our model, I told them our model has been there for 6 months, the fact that HP is viewing it, means the model is available. If it’s a bridging issue we will help Cerris work it out
Trevor said he will get with rantwiler and get the model bridged, they will offset that vent around our TW Piping
They made comments about the TW skid being so close to the FW valves. Its been this way for over 6 months. Trevor also stated the vent will need an accessible cleanout
6/25/2026 - They just went over IWM and specific Electrical clashes
7/9/2026 - TXE 2 all docs are out, all sign offs are out
TXE1, 2 sign offs left
DHCD 2 weeks from now
1130amLightning HRV - Global BIM Coordination Meeting
Isabella Vesce Rivera (SI)
Is there a coordination model we get access to? Revizto? Navis?
Get input on HDR Mockup I made for FW UG Stubup, Bypass and MES Loop connections
Colonial was trying to align to SI Desing model, that was all that was available for the bridging
Seth Blizzard says they arent obligated to meet our POC's, they follow the ARUP design. ARUP did let them know they are contracted to meet our POC's
Curtis Robbins said he just needs to click a button to enable the bridging to our actual Coordination Models
Seth started making comments about use being able to shift our pipes 3", I told them theres a lot more going on that what they were showing with our Engineered anchors, flush connections, MES and TWMU skids and TW Piping, there isnt much forgiveness
Still don’t have access to bridged Colonial files
6/29/26 - 7/5/26
06/30/26 - TUE (+1 Meetings)
700amHRV Meeting
Arthur says he will facilitate the Bridging for link models
Hes says preston is the facilitator, but
Darren kept giving static as far as linking in separate trade models
Said him, tom, and air up have all been in talks about this
I told them repeatedly we need Trade Models to coordinate against, 1" deviation between trade model and design model can be devastating
Jam Jam asked if Fan coil units would be modeled in the linked in model, I told them I would pass that over to scott
07/01/26 - WED (+3 Meetings)
700amEMT - Lightning Scope BIM Kickoff
Abe Hernandez (SI Senior Design Project Manager)
Heath/ Scott brough up coordination meeting
Arne Knutsen is the COORDINATION MANAGER with Peyton help
Scott brought up Keyplans off, grid bubble names are wrong
Heath and Melanie said they will be fixed
Abe in 3-4 weeks have the mofe content in the contructability models
Bring up Coordination with underground, Dim sheets issued
Schedule?
Chad Miller is over the base build Facility Underground
I need ot get them our POC Dim drawings
I brought up the CIA agreement, we need to push this hard
Melanine wants a meeting to go over model not lining up in Revizto
800amTXE/LEB Weekly Internal BIM Coordination | Meeting-Join | Microsoft Teams
Jay Keiser - FTI
LEB10 RO Hitting Column
LEB10 FLEX HOSE on 8" Flush skid hitting column, need to clear clashes
talked about email I sent about a list of which models to use for which trades as far as Walls, Wall Panels, Electrical, Arch, Structural etc
Kyle said he was still working on that
John Cowhey is asking about Lugs on the MES
I will chase this down, find who responded Johns email and start there
Robert Cheek responded on Monday saying he would get the answer same day, still waiting
I told Jay we are currently working through shop drawings and spools, while we are doing those we are paying attention to clashes and working through the clashes
I Brought up the FW underground being off and that we will be scanning and verifying CIA POC's, Should be doing this within a week
5/27/2026 - I BROUGHT UP LEB1 COORDINATING WITH CRIDER NO MODEL, USING HDR FOR UNDERGROUND COORDINATION
JAY BROUGHT UP TXE10 ANCHOR CLASH WITH WALL, ADAM SENT EMAIL ASKING ABOUT IT, SOMEONE SAID THEY WERE CHANGING WALL IN A EMAIL RESPONSE, ADAM REQUESTED MEETING, NO ONE RESPONDED
JAY ADDED THIS AS AN ACTION ITEM
EMMA SENT EMAIL REQUESTING CLARIFICATION, TRISTEN WAS CONFUSED
LUKE SAID HE WILL DISCUSS IN HIS MEETING WITH MORTENSON
JAY ADDED THIS AS AN ACTION ITEM
6/3/2026 - New LEB Mech and Plumbing meeting on Wed, John and Reece involved, going over FW stub up locations and F/F water gallery connections
Informed John of Convos with Greg to coordinate wall install with coring of anchor plate holes
Told Jay/John, Lance Holmes is coordinating with other trades on fix for LEB UG FW stubups not hitting POC points or dimensions
6/10/2026 - Verify Span models work on LEB10, 1, 2
6/17/2026 - Checked LEB1, Span_SS model is still only showing Labeled grids, no steel in revit linked model, 2models, same dates, different version, latest verison wont load, gives error
Bring up Walbringer as new MP contractor on LEB6, sent email out with dimension sheets for someone to get them the information
Coordination Sign off
Jay gave links to Turner and HP sign off locations
Clash Review
Jay said he will go through and filter out white noise, setup a meeting to over others. I told him whenever he wants and I will be there
Friday 6/19/22 9am
6/24/2026 - Check with Adam if he verified the lastest info from Crider lining up ug, LEB10
Check LEB1 model HDR Underground lining up with Model, We are lined up with HELM Bypass on LEB10
Luke will get with LEB and Turner for Verifying CIA Points
Louis will get with TXE and HP for Verifying CIA points
LEB6 - MP Model misalignment, I checked the Turner NWD, they are using a FTI Container that may have a misaligned MP NWC
I Put together and new NWD with current NWCs Available and everything lined up correctly
LEB, DCW Drops, Get with John to find out which way they want to go, then follow up with HDR and Helm and Waldinger
I sent John Rhee an email requesting update
7/1/2026 - Jay brought up LEB6 issue I emailed, I told them HDR still needs to update their pipe stup ups, they fixed the grid though
I brought up CIA from other GCs since they were talking about FTI Scanning HP elements, if HP didn't provide documented points what is FTI going to shoot?
Justin said yeah, it is a meta requirement but meta hasn’t really lined out what exactly is required
I told them FTI did such a great job on the document and spearheading it, I was wondering if the other GCs also maintained this document since we are connecting to systems from other trades
Jay follow up with Kyle on HP for going through HP clashing directly, can we access them, create issues, clear?
1000amBIM Round Up | Meeting-Join | Microsoft Teams
Michael Kolnik
Jeremy says they are supposed to be scanning in a week or 2
Jeremy needs Floor drain locations from Cerris so they know exactly where they land, Need to get with Patrick Marshall at Cerris and see if we can get some shop drawings.
6/3/2026 - MICHAEL ASKED ABOUT CURTIS GIVING HIM AN ORDER REQUEST THAT HE THOUGHT WAS SUPPOSED TO BE FOR FLUSH SKIDS
IT HAD 16X14 TEES, 14" 90S, 8" STAINLESS CAPS
HE DIDN’T KNOW WHERE THESE TEES CAME FROM
I TOLD HIM THEY WERE FOR THE MES LOOPS, NOT THE SKIDS
THE 14" 90S WERE PROBABLY FOR THE FLUSH SPOOL TO CONNECT TO THE FLEX SKID
MICHAEL SAID HE CANT GET THEM IN TIME, SIAD HE IS LOOKING AT DOING A MATERIAL SUBSTITUTE REQUEST, I SAID IT ASAP AND PUT CURTIS IN THE LOOP ON IT
6/10/2026 - Michael said he is having a meeting Friday about FW scanning and fix for fw off dims, with HP, FTI, Scanners,
6/17/2026 - Adam brought up supports, new design doesn't leave room for any adjustments
Michael says scanning will be around 7/1, if UG is off, michael says we will have to fix and charge HP
Are we going to have 8 unique supports
Paul says we will have to do it in the field
Paul and Michael agreed a new stand with Trapeze hangers will work, adam wil resubmit
Michael has order all fittings and pipe for TXE10 and TXE2 for MES loops
Region 1 is staying with 1 flush skid
2 flushes, twice as long, michael said it doesn’t schedule, not enough time for 2 flushes
6/22/2026 - Adam is telling Michael they need to create packages in stratus for how they want hac jumpers, bypasses split up
Adam is proposing a fabrication kick off meeting with Ryan and Curtis to get everyone on board
Micheal needs 8 weeks, Curtis needs 3 weeks for example
Jacob says curtis wants packages created by cost codes, but we are talking about splitting them by areas
Paul says give tom a curtisy that we are rele
Need to update the 6" flush skid and put a bleed olet on the return vertical
Paul says hes not sure where the Bypasses are as far as UG Bypass
Pual not sure when production will start for Near site, installing bypasses on HAC on near site
He will then put the spools in the appropriate package
6/30/2026 - Paul says caps are needed on MES TW and FW Ports, they can put drains on if they want
No drains on jumpers
Curtis is shipping spools to SOK
Curtis said no drains on caps, just need caps
Michael, going over spools
No Drains on jumpers
Look at TXE1-01-FWR-JMP-001, showing Flex coupling, need quick vic
Michael Ordered 16x14 tees, make sure we stayed with those and didn't update to full 16" to flush skid
07/02/26 - THU (+6 Meetings)
630-710amLEB | BIM | Faith x Turner
Luke Jost - Joe Dorinsville
Edwin Perez from Turner hosted
5/14/26 - - Joe Brought up the access panels for Flush system, asked about rating, I would have to check submittals to verify. Me and Lance holmes informed joe the flush systems are temporary, once done, they get removed and the access panel stay
Anna said they were aware, but not the finalized locations, now they will be going through Valley for engineering, excel engineering to make sure everything is accounted for, engineered
Talked to Stefan, we are not providing the Access Panel, its GC2 wall, they are providing it
I need to check on RO system, ACCess panel and it looks like location may be borked
Scott asked about sign offs for lighting scope to base build duct connections, Joe said they havent covered it, sign off is around end of June. They will be circling back to loop area not that they have certain paperwork available
Joe said any issue can be brought up at anytime
5/21/265 - No John Rhee, Brent, Thomas Holler, NO PM TEAM
They went over stud wall model, Lance asking about raceways for security and bus ducts
5/28/2026 - They went over electrical stuff, skid placement, wall leave outs
Turner wants a meeting with Helm and Southland to go over Wall penetrations
Joe D discussed Span model naming, keeping them the same and consistant.
Will need to relink LEB Span models since they have new models with Nucor suffix
6/4/2026 - Eduardo Ibanez brought up Status of Facility Water Stubups asking if Verification of Stubups with Mortenson needed. Had Crider submitted? Lance was saying Ryan would have this info and asking if Ryan was in meeting
NO PM Team present
I sent PM Team a summary email
I explained, Ryan used HDR model for coordination, I worked with HDR to get everything line up, we provided dimensions, everyone agreed to them, now stub ups are off, Lance Resposnded to John Rhees email asking what is being done
I said we need to start having meeting to go over this issue since its so critical
Luke Jost told eduardo to add an action item for this and lance said he will head this off
6/11/2026 - I brought up the FW UG being off again, told the group Ben Kozel with crider said they were backfilling in layers and trying to get the stub ups on the POC/CIA points
Overhead Signoff is schedule for 6/30
Scott asked if it was entire building for NWB, Joe says yes
Joe Brought up IMP walls changing to Framed walls, Anna? Said it was still being worked on
Verify LEB10 POC For DCW
Verify DCW POCs line up with CIA
Lance said they are also providing a hose connection for discharge, I stated they are using the FLOOR Drains in center of gallery for discharge, Adam corrected me saying John has requested different discharge points. Wouldn've been nice to know.
Someone asked about the Flex piping from the 8" skid hitting the column, I told them it was flex pipe and temporary, that it will bend around the column
Vent in 6-19x6-D, adam told them to put in between MES Skid
Waldinger is doing the bypass on LEB6
Building 6 MES loops are showing misalignment with Waldinger Bypass
NO PM Team present
I said I would like it added to this meetings notes, Joe Dorinsville basically shut it down, saying it was a field issue
I said it was our issue also since we are constantly being asked to do overlays, which were happy to help any way we can, but this was more of a helm situation since they are the responsible party to connect to the UG and provide us with accurate points of contact according to the CIA
Joe reiterated it was a field issue
6/18/2026 - Edwin Perez is showing Verification on stub ups w mortneson needed. Pending Submittal. Eng. Drawings to be submitted - Crider and Crider. He said this is still on going
Edwins model view still shows MP Shifted to plan right, access panels were to the right of the wall they are supposed to be in
LEB6 Arch Coordination model is showing everyhting off, MES Skid not lining up, mp is to the right, access panels are to the right of the walls they are supposed to be in.
LEB10, checked with Joe D, things line up there.
6/25/2026 - Joe, Greg, Luke Long, Greg went over Electrical coordination
I sent email to PM Team, no one was present
Eduardo Ibanez brought up Status of Facility Water Stubups asking if Verification of Stubups with Mortenson needed. Had Crider submitted? He brought this up again. I explained again that we provided dimensions for LEB10 and LEB1 to Mortensen, Crider and HDR, they all agreed
I told group that I also emailed these dimensions to Waldinger for Region 2, but havent received any comments or response from anyone.
Scott asked about tracking for signoff on 6/30, eduardo said yes
Luke Jost asked about LEB10 Embeds to make sure they are getting tracked by turner
Edwin Perez asked about Waldinger Bypass and alignment to SI MES Loop Connection
I told Edwin Perez I provided poc dimensions and elevations, but havent received any response
Edwin said he will bring up in next BIM meeting
7/2/2026 - Get with john as far as who is providing what cam lock adapt for fip drops
Lance Holman also provided additional dishcharges (Drains) for Flush/ fill per john
They showed model, HDR DWC Drops are on face of column, I told group IFC shows they are on Web side, HDR Model doesn’t match HDR IFCs
John Rhee is communicating changes from model to FTI, Turner that they are not telling us, Discharge drains, DCW changes
The only reason I found out was because of the meeting flythrough, our pocs were on other side of corridor
John fucking totally ignored our information and didn't relay any information
I missed the HDR IFCs showing the drops on the plan south side of corridor
I explained LEB6 model misalignment was fixed, publishing issue, I will double check mondays model after the Saturday auto publish
I told group about the FW UG Dimension sheet that has been distributed multiple times and it details where the FW UG stubs are supposed to be ever since LEB1
I will double check LEB2 misalignment
They showed LEB6 and the 8" skids were into the columns again
I explained the deep dive I did last week, it shows everything aligned. There are issues with the FTI Container model that Turner is using for coordination
830amLEB | BIM COORDINATION LEB2
Emma will no longer be on this project
Kaushal Bagdekar with Turner ran the meeting, saying who to contact for what, I asked if he could send an email with that info
They went over underground clashes
5/28/2026 - Tristen with helm verified he is using LEB1 dimensions for LEB 2 elevations and locaitons for FW
6/11/2026 - No PM Team
Went Over UG issues, concrete pads
6/18/2026 - Kaushal Bagdekar
Did a flythrough for LEB2 going over exterior sectionalizers
LEB-2_SPAN_SS.rvt, verifying during meeting that the model is good, Checked LEB2 SPAN_SS model, couldn’t load content, says cant link in NuCOR
NO Interior Walls and framing, Valley, Diogo or Ruth said they will get with valley
No Interior Meta Wall Panels
6/25/2026 - NO PM TEAM
They went over UG issues for LEB2
7/2/2026 - LEB2, Showed model where Helm, SI and Crider not aligned, #2070
LEB2 Building Overall actually has Crider model, showing misaligned
Grid 1-50, 1-D is the only spot where Crider is off looking at Turners LEB2_Building_Overall model only
Everything else is aligned, MP, Duct, Steel, Walls, no issues
Sent email showing misaligned concrete and crider stub ups at 2-50
LEB-SI-MP-LEB2-R25 model lined up identical to LEB2-Building-Overall
Didn't see new DCW POC valves, did I update LEB2
Did see FLUSH VENTS AND DRAINS, VENT ON 2-50 IS OFF
900amTXE-FTI Weekly Sync Meeting
Luke Justice
Luke was asking about scanning at TXE10, He said coordinate with Greg Hueramo, he will be setting up an origination email
I told luke they need to have all areas ready for scanning since the team cant be sent out every other day, reset up, etc
I asked for Control point map, he said get with Greg Hueramo
I explained to him what the scanning was
I told him they will need to add paul hernandex, jeremy miller and adam brown to email
John Cowhey said he has a 1 pager for Site orientation which will be 8 hours
They will be enforcing badging within the next few weeks. No badge no access, Visitor badges will be available but not allowed to work
Luke will put together a schedule for orientation
11/17/26 - is new date for 0 prep according to John Cowhey
Forward FW off email to Luke, original email was sent out 4/17. I resent to Luke Justice
I told him Jeff Balthrop was involved a few weeks back
Send Luke Discrepancy on Anchor locations with BZI Wall panels, NWCs etc from Adam email, Adam email 5/5, TXE Adam email 5/6
Verify anchors at TXE and LEB, check they've been submitted to FTI
Send notice to John Cowhey, luke justice
They asked when Southland is looking at manning the site, jeremy informed them no PM team were available at this time to answer
new schedule coming out Friday
Got with michael kolnik, he sent out Shop Drawing submittal request to Eric Boehger
5/28/2026 - Loop Keylan and Michael into the Anchor clash info and meeting for Friday
Luke says bypass are fabbed, not installed will be installed next week, sent out email to everyone, paul, jeremy, michael
Need to coordinate orientation, drug testing
Day zero schedule? Luke said he was supposed to get last Friday, not seeing anything new
Luke showed the Faith TXE Anchor Shop Drawing submittals, they are only for the TXE10,1,2 Plates don’t know why it has TXE3 on the label
Not showing any Shop drawing embed submittal info
NO PM Management was present, Keylan Rollins was for engineering
6/4/2026 - Luke Cancelled at 741am, Got DAMN MAN!!!!
6/11/2026 - Luke Cancelled at 741am, Got DAMN MAN!!!!
6/18/2026 - Luke asked about Issues, I was explaining a summary of Greg Heuromos meeting, then Michael Kolnik was there! It was nice
6/25/2026 - Michael says greg told him the bypass will be complete on 6/7, michael has scanning scheduled for 6/6
Jason with FTI will use truck to help scanning move around job
Scanners will need badges, they can be escorted according to michael who talked to security
Michael says no one onsite yet, they are on first of kind, michael and jacob did get badged
FTI does have a superintendant and a couple of upper management onsite
Fully mobilized first week of July
Luis says they have been requesting a lot of BIM information, Asbuilts, trench information, etc
Luke says a laser just got done for the Trench
Alec Harpel says first half of txe10 was scanned, still waiting for coordinates
Need FW stub ups, grounding whips and trenches
Luis is asking for points for the finish floor to verify elevation/flatness
TXE1 slab just started pouring last week, according to Luke
Micahel said they wont have water into the building, they need to truck it in and provide the minimum GPM with 3" connection
TXE10 shows 3" main with 3" drops
TXE1 shows 4" main with 3" drops
7/2/2026 - Luke Justice cancelled
1000 amLEB - BIM Coordination Meeting (Thu) | Meeting-Join | Microsoft Teams
Ryan Zoldan
LEB 6 due finalized next week
I requested a schedule from Ryan, he has the sign off, region schedule, I brought up a pull plan, be he says that will be through Turner
Mortensen is the Base build GC, why aren't they leading a pull plan schedule
John Rhee nor Brent were in this meeting
6/4/2026 - I brought up the LEB10 FW UG Stub ups totally missing the Dims, Ben Kozel was there and he stated they are bringing them back in to dimensions by backfilling a little and moving them, backfilling and moving them
He acknowledge that lance did contact him
6/11/2026 - Ben Kozel, said there were no issues that need to be talked about.
Richard lopez asked around the room for any issues regarding LEB10 or any others
NO PM Team
6/18/2026 - Richard Lopez Hosted, just asked for any issues with LEB10,1,2,3 Underground issues
Rantwiler asked when IWM for TXE10 was going to be signed off, Ethan says he will talke to kyle since they are not really split out
6/25/2026 - Going over LEB7,8
Ryan brought up LEB6, HDR model is not lining up with the Dimensions provided by SI
Ryan henderson said he will follow up
Ryan said we have all agreed to follow these dimesions, I added that I have distrubuted that dimesion sheet ot Waldinger and explained everything, but havent received a response yet
Ryan brought up LEB6, HDR model is not lining up and my email I sent out
I updated, still waiting for HDR to align the stubups
Ryan said Crider is using civil 3d, but we can work it out to actually use their model for coordination and linking in so I don't have to use HDR
TXE1 looks good for the loop area sign off next week
Same with TXE2
6/4/2026 - Own B ran the meeting going over TXE1 and 2
6/11/2026 - Owen B, says TXE10 Loop for sign off
TXE2 Core scheduled for next week
TXE10 AB Datahall and Loop are signed off
TXE3 Alan lopez is running region 2 for signe off
TXE2 Loop and AB South sign off
issue 2602 - Cerris Vent in corner is clashing with Technical water, Rantwiler is saying they don’t have our model, I told them our model has been there for 6 months, the fact that HP is viewing it, means the model is available. If it’s a bridging issue we will help Cerris work it out
Trevor said he will get with rantwiler and get the model bridged, they will offset that vent around our TW Piping
They made comments about the TW skid being so close to the FW valves. Its been this way for over 6 months. Trevor also stated the vent will need an accessible cleanout
6/25/2026 - They just went over IWM and specific Electrical clashes
1100amHRV Facility Water Coordinatiohn
Justin Kroening DPR
Is there a coordination model we get access to? Revizto? Navis?
Get input on HDR Mockup I made for FW UG Stubup, Bypass and MES Loop connections
Colonial was trying to align to SI Desing model, that was all that was available for the bridging
Seth Blizzard says they arent obligated to meet our POC's, they follow the ARUP design. ARUP did let them know they are contracted to meet our POC's
Curtis Robbins said he just needs to click a button to enable the bridging to our actual Coordination Models
Seth started making comments about use being able to shift our pipes 3", I told them theres a lot more going on that what they were showing with our Engineered anchors, flush connections, MES and TWMU skids and TW Piping, there isnt much forgiveness
Still don’t have access to bridged Colonial files
6/22/26 - 6/28/26
06/22/26 - MON (+4 Meetings)
900amLightning TXE Staff Meeting | Meeting-Join | Microsoft Teams
Jacob Gelhousen
Will do scans after Cerris installs bypasses
6/1/2026 - Noel Nunez says Alehandro Chew will be safety manager
Michael said he sent TXE3 embeds along with PDF dimension in mid April
Doesn’t think TXE3 has been poured, think they are behind schedule
Says we havent been funded for Region 2, he is sending out embeds as needed
Michael asked what the question was about RO and TW, I said it was going over how to connect to the RO skid, from DCW and to TW MES
Michael asked if MES Loops were completed, adam said yes, he created new BOMs
Michael said his goal is to get everything ordered
Michale Paul said they thought the walls weren't going to be in until they could do anchor
They said that was what was agreed to
6/8/2026 - Michael said they had a PM Coins Mandatory meeting and couldn't host the meeting
6/15/2026 - Chris Moss came on board from TSMC, Pipe fitter, GF
Jose Alejandro Chew, new Safety Manager for TXE
6/22/2026 - Shop drawings (Engineer Drawings) looking at submittal on Frid, 6/26
900amLightning TXE Staff Meeting | Meeting-Join | Microsoft Teams
Jacob Gelhousen
Will do scans after Cerris installs bypasses
6/1/2026 - Noel Nunez says Alehandro Chew will be safety manager
Michael said he sent TXE3 embeds along with PDF dimension in mid April
Doesn’t think TXE3 has been poured, think they are behind schedule
Says we havent been funded for Region 2, he is sending out embeds as needed
Michael asked what the question was about RO and TW, I said it was going over how to connect to the RO skid, from DCW and to TW MES
Michael asked if MES Loops were completed, adam said yes, he created new BOMs
Michael said his goal is to get everything ordered
Michale Paul said they thought the walls weren't going to be in until they could do anchor
They said that was what was agreed to
6/8/2026 - Michael said they had a PM Coins Mandatory meeting and couldn't host the meeting
6/15/2026 - Chris Moss came on board from TSMC, Pipe fitter, GF
Jose Alejandro Chew, new Safety Manager for TXE
6/22/2026 - Shop drawings (Engineer Drawings) looking at submittal on Frid, 6/26
6/29/2026 - Keylan Cancelled
1130amMW Detailing Weekly Meeting
1130amMW Detailing Weekly Meeting
6/29/2026 - Marshall Cancelled
06/23/26 - TUE (+10 Meetings)
700am-745amHRV FSHAC Coordination
Arthur Foley (MC Dean)
Isabella Vesce Rivera, Dowoo Kim, Adam Brown, Scott
Arthur uploaded/ published new steel model to ACC, he can't see our model on his end
HRV Bim Weeklys hosted by Cameron, but its for BIM, discussing titleblocks
Danton says DPR, the engineer should be producing a federated model and coordinating a trade partner meeting
Says they will be creating a navis folder for all integrator and trade partners to pull from
Adam explained, we sit in GC1 Base build meetings along with GC3 (Faith) above ground meetings
GC1 is DPR, base build, not sure if they are using Revizto
AirUp is leading coordination for GC1
Colonial Web is doing underground, Adam already coordinated points and drawings with them
Darren says Tom Chirdon and Tom Maxwell have been sitting in meetings with Darren Ballesteros (MC Dean) Breakout mechanical meetings
We need Melanie, Ron, Heath to Go through BIM Execution plan, get contacts lined up and distributed, get model distribution set up or verified, sharing setup, need access to other trade NWCs (Desgin Arch, Struct, MP, Elect, Concrete) and Trade models, they need access to ours
Need Schedules
Submittals
Darren is Assistant PM, Arthur is HAC
Isabella Vesce Rivera is Southland PM, she asked about coordination with Colonial Web UG along with embed coordination
Ryan submitted to Dean and DPR anchor info
Corbin is structural designer, they are approving them according to Tom C
Adam is asking for concrete schedule to make sure we get them the embed info they need before pour, Ryan requested info from Curtis and DPR, said he will follow up
I brought up making sure the UG concrete trade is brought in on Embed discussions since more than likely they will be placing the embeds
700am-745amHRV FSHAC Coordination
Arthur Foley (MC Dean)
Isabella Vesce Rivera, Dowoo Kim, Adam Brown, Scott
Arthur uploaded/ published new steel model to ACC, he can't see our model on his end
HRV Bim Weeklys hosted by Cameron, but its for BIM, discussing titleblocks
Danton says DPR, the engineer should be producing a federated model and coordinating a trade partner meeting
Says they will be creating a navis folder for all integrator and trade partners to pull from
Adam explained, we sit in GC1 Base build meetings along with GC3 (Faith) above ground meetings
GC1 is DPR, base build, not sure if they are using Revizto
AirUp is leading coordination for GC1
Colonial Web is doing underground, Adam already coordinated points and drawings with them
Darren says Tom Chirdon and Tom Maxwell have been sitting in meetings with Darren Ballesteros (MC Dean) Breakout mechanical meetings
We need Melanie, Ron, Heath to Go through BIM Execution plan, get contacts lined up and distributed, get model distribution set up or verified, sharing setup, need access to other trade NWCs (Desgin Arch, Struct, MP, Elect, Concrete) and Trade models, they need access to ours
Need Schedules
Submittals
Darren is Assistant PM, Arthur is HAC
Isabella Vesce Rivera is Southland PM, she asked about coordination with Colonial Web UG along with embed coordination
Ryan submitted to Dean and DPR anchor info
Corbin is structural designer, they are approving them according to Tom C
Adam is asking for concrete schedule to make sure we get them the embed info they need before pour, Ryan requested info from Curtis and DPR, said he will follow up
I brought up making sure the UG concrete trade is brought in on Embed discussions since more than likely they will be placing the embeds
800amWeekly BIM Coordination Meeting - Region 2 (ZOOM)
Alan Lopez, Kyle Cummings (Hensel Phelps) / Ethen Berry
No one started the meeting, I sent an email, they said Alan was PTO and they started meeting late
They went over Region 2 underground, sign off later this week
5/26/26 - Allen Lopez Went over Region 2 again, said they were going to do a main signoff then a branch signoff. Covered a lot of UG clashes
6/2/2026
2 weeks sign off branch
6/9/2026
6/16/2026
Allen Lopez says he doesn't see Sure Steel model in TXE3, Kyle says also no Diversified, but Sure Steel model is there, needs added
Signoff schedule was not bridged, the one on FTI is outdated. Kyle and Justin said they would get the bridge up to date
Files - Data Management
6/23/2026
800amWeekly BIM Coordination Meeting - Region 2 (ZOOM)
Alan Lopez, Kyle Cummings (Hensel Phelps) / Ethen Berry
No one started the meeting, I sent an email, they said Alan was PTO and they started meeting late
They went over Region 2 underground, sign off later this week
5/26/26 - Allen Lopez Went over Region 2 again, said they were going to do a main signoff then a branch signoff. Covered a lot of UG clashes
6/2/2026
2 weeks sign off branch
6/9/2026
6/16/2026
Allen Lopez says he doesn't see Sure Steel model in TXE3, Kyle says also no Diversified, but Sure Steel model is there, needs added
Signoff schedule was not bridged, the one on FTI is outdated. Kyle and Justin said they would get the bridge up to date
Files - Data Management
6/23/2026
6/30/2026
830amLEB - BIM Coordination Meeting (Tue) | Meeting-Join | Microsoft Teams
Ryan Zoldan, Mortenson (GC1)
Missed for the 8am meeting
6/16/2026
830amLEB - BIM Coordination Meeting (Tue) | Meeting-Join | Microsoft Teams
Ryan Zoldan, Mortenson (GC1)
Missed for the 8am meeting
6/16/2026
6/23/2026
6/30/2026
1000amLightning-Eng-Coord Huddle | Meeting-Join | Microsoft Teams
Tia/ Tom
Follow up on HAC Panel clashes with Patrick Brinnehal
Meeting to go over stratus and models with all PMs, Adam, Scott, Supers sometime next week, look at schedules
Chris Chase is the PM of EMT
5/26/2026 - Check if Adam got the 4" Welded Bypass to Shop, from 5/5/25 email in Inbox "Im shooting to have the LTG build out scope package done by end of week (For Review only not for construction). "
Verify what spools have been put on stratus for TIA/TOM Lightning huddle
Need meeting to discuss, txe10 anchor clashing with interior of walls, adam sent info out about conflicting models, but as of today, there is still clashes
RFI says they are changing wall to Gypsm board and expanding toward corridor 2.5"
6/2/2026 - We did get 2 more sites in Ohio
SI will be integrator
Heath introduced Peyton Steveons as VDC supervisor
Starting with HRV
Melanie introduced Vasi, VDC specialist helping out ron and melanie
Tia went over deliverable schedules
Per site, per building
She setup a break out meeting
Adam said they are moving the walls away from anchors so we are clear
Adam said we are 1/2" clear from plate, it will be a field issue installing the plate
Michael said he will talk to paul, he doesn't know what to do, he will call greg
only 2 walls changed from IMP, 2 others are still IMP
Michael said Greg told him they are putting walls up next week
Told Tia I sent snip of Dog Leg Metraflex in chat, didn’t get any smiles
Let her know we have LEB complete, TXE10,1,2 is complete
Adam said he will give link to CIAs, TXE3-12 and LEB3-12 not ready
Adam had meeting with HRV, told them to start using our coordination models for coordination
Quick hello, this is who we are meeting
with MC Dean
Mealnie says they will be updating projects to new architect model
Type F - 4 buildings
Type G - 2 buildings
6/9/2026 - Adam said they are going to move the MSA, HAC spools to the Lighting Program, for one source
Melanie and Keylan said it can be done
1000amLightning-Eng-Coord Huddle | Meeting-Join | Microsoft Teams
Tia/ Tom
Follow up on HAC Panel clashes with Patrick Brinnehal
Meeting to go over stratus and models with all PMs, Adam, Scott, Supers sometime next week, look at schedules
Chris Chase is the PM of EMT
5/26/2026 - Check if Adam got the 4" Welded Bypass to Shop, from 5/5/25 email in Inbox "Im shooting to have the LTG build out scope package done by end of week (For Review only not for construction). "
Verify what spools have been put on stratus for TIA/TOM Lightning huddle
Need meeting to discuss, txe10 anchor clashing with interior of walls, adam sent info out about conflicting models, but as of today, there is still clashes
RFI says they are changing wall to Gypsm board and expanding toward corridor 2.5"
6/2/2026 - We did get 2 more sites in Ohio
SI will be integrator
Heath introduced Peyton Steveons as VDC supervisor
Starting with HRV
Melanie introduced Vasi, VDC specialist helping out ron and melanie
Tia went over deliverable schedules
Per site, per building
She setup a break out meeting
Adam said they are moving the walls away from anchors so we are clear
Adam said we are 1/2" clear from plate, it will be a field issue installing the plate
Michael said he will talk to paul, he doesn't know what to do, he will call greg
only 2 walls changed from IMP, 2 others are still IMP
Michael said Greg told him they are putting walls up next week
Told Tia I sent snip of Dog Leg Metraflex in chat, didn’t get any smiles
Let her know we have LEB complete, TXE10,1,2 is complete
Adam said he will give link to CIAs, TXE3-12 and LEB3-12 not ready
Adam had meeting with HRV, told them to start using our coordination models for coordination
Quick hello, this is who we are meeting
with MC Dean
Mealnie says they will be updating projects to new architect model
Type F - 4 buildings
Type G - 2 buildings
6/9/2026 - Adam said they are going to move the MSA, HAC spools to the Lighting Program, for one source
Melanie and Keylan said it can be done
6/30/2026 - FTI wants scanners badged
TXE1 special Support approved
H Support hanger, supposed to get stamped this week
HRV supposed to get linked in models setup so we can coordinate ug
Need to verify LEB and TXE CIA points
SS Headers are in fab per EAN
John Rhee asked about Waldinger misaligned, we are now good, sending email showing HDR is off
Toms Eng review comments will be looking at doing updates next week
HRV Embed Dims, ryan says he has, I have Angle working on them now, wtf?!!!
PIQ, melanie is setting up, I asked her to keep an eye out for the BIM ex plan and contact list
Michael said they have drug test this week, orientation on Monday
1200pmTXE-Region3 Coordination Meeting
Jade B Lowe (Hensel Phelps)
Jade is in charge of Region 3
Kyle cummins is in charge of site
Filll out contact excel sheet, put bim lead and project manager
Kyle - LOD 450 project, all installed elements are modeled, then asbuilts are fed back in to model
Indicate in the model some where that the asbuilt has been applied and model has been adjusted
1200pmTXE-Region3 Coordination Meeting
Jade B Lowe (Hensel Phelps)
Jade is in charge of Region 3
Kyle cummins is in charge of site
Filll out contact excel sheet, put bim lead and project manager
Kyle - LOD 450 project, all installed elements are modeled, then asbuilts are fed back in to model
Indicate in the model some where that the asbuilt has been applied and model has been adjusted
6/16/2026 - Decided not to go to this one since its Region 3, TXE6,7 undergound
06/24/26 - WED (+2 Meetings)
800amTXE/LEB Weekly Internal BIM Coordination | Meeting-Join | Microsoft Teams
Jay Keiser - FTI
LEB10 RO Hitting Column
LEB10 FLEX HOSE on 8" Flush skid hitting column, need to clear clashes
talked about email I sent about a list of which models to use for which trades as far as Walls, Wall Panels, Electrical, Arch, Structural etc
Kyle said he was still working on that
John Cowhey is asking about Lugs on the MES
I will chase this down, find who responded Johns email and start there
Robert Cheek responded on Monday saying he would get the answer same day, still waiting
I told Jay we are currently working through shop drawings and spools, while we are doing those we are paying attention to clashes and working through the clashes
I Brought up the FW underground being off and that we will be scanning and verifying CIA POC's, Should be doing this within a week
5/27/2026 - I BROUGHT UP LEB1 COORDINATING WITH CRIDER NO MODEL, USING HDR FOR UNDERGROUND COORDINATION
JAY BROUGHT UP TXE10 ANCHOR CLASH WITH WALL, ADAM SENT EMAIL ASKING ABOUT IT, SOMEONE SAID THEY WERE CHANGING WALL IN A EMAIL RESPONSE, ADAM REQUESTED MEETING, NO ONE RESPONDED
JAY ADDED THIS AS AN ACTION ITEM
EMMA SENT EMAIL REQUESTING CLARIFICATION, TRISTEN WAS CONFUSED
LUKE SAID HE WILL DISCUSS IN HIS MEETING WITH MORTENSON
JAY ADDED THIS AS AN ACTION ITEM
6/3/2026 - New LEB Mech and Plumbing meeting on Wed, John and Reece involved, going over FW stub up locations and F/F water gallery connections
Informed John of Convos with Greg to coordinate wall install with coring of anchor plate holes
Told Jay/John, Lance Holmes is coordinating with other trades on fix for LEB UG FW stubups not hitting POC points or dimensions
6/10/2026 - Verify Span models work on LEB10, 1, 2
6/17/2026 - Checked LEB1, Span_SS model is still only showing Labeled grids, no steel in revit linked model, 2models, same dates, different version, latest verison wont load, gives error
Bring up Walbringer as new MP contractor on LEB6, sent email out with dimension sheets for someone to get them the information
Coordination Sign off
Jay gave links to Turner and HP sign off locations
Clash Review
Jay said he will go through and filter out white noise, setup a meeting to over others. I told him whenever he wants and I will be there
Friday 6/19/22 9am
6/24/2026 - Check with Adam if he verified the lastest info from Crider lining up ug, LEB10
Check LEB1 model HDR Underground lining up with Model, We are lined up with HELM Bypass on LEB10
Luke will get with LEB and Turner for Verifying CIA Points
Louis will get with TXE and HP for Verifying CIA points
LEB6 - MP Model misalignment, I checked the Turner NWD, they are using a FTI Container that may have a misaligned MP NWC
I Put together and new NWD with current NWCs Available and everything lined up correctly
LEB, DCW Drops, Get with John to find out which way they want to go, then follow up with HDR and Helm and Waldinger
I sent John Rhee an email requesting update
1000amBIM Round Up | Meeting-Join | Microsoft Teams
Michael Kolnik
Jeremy says they are supposed to be scanning in a week or 2
Jeremy needs Floor drain locations from Cerris so they know exactly where they land, Need to get with Patrick Marshall at Cerris and see if we can get some shop drawings.
6/3/2026 - MICHAEL ASKED ABOUT CURTIS GIVING HIM AN ORDER REQUEST THAT HE THOUGHT WAS SUPPOSED TO BE FOR FLUSH SKIDS
IT HAD 16X14 TEES, 14" 90S, 8" STAINLESS CAPS
HE DIDN’T KNOW WHERE THESE TEES CAME FROM
I TOLD HIM THEY WERE FOR THE MES LOOPS, NOT THE SKIDS
THE 14" 90S WERE PROBABLY FOR THE FLUSH SPOOL TO CONNECT TO THE FLEX SKID
MICHAEL SAID HE CANT GET THEM IN TIME, SIAD HE IS LOOKING AT DOING A MATERIAL SUBSTITUTE REQUEST, I SAID IT ASAP AND PUT CURTIS IN THE LOOP ON IT
6/10/2026 - Michael said he is having a meeting Friday about FW scanning and fix for fw off dims, with HP, FTI, Scanners,
6/17/2026 - Adam brought up supports, new design doesn't leave room for any adjustments
Michael says scanning will be around 7/1, if UG is off, michael says we will have to fix and charge HP
Are we going to have 8 unique supports
Paul says we will have to do it in the field
Paul and Michael agreed a new stand with Trapeze hangers will work, adam wil resubmit
Michael has order all fittings and pipe for TXE10 and TXE2 for MES loops
Region 1 is staying with 1 flush skid
2 flushes, twice as long, michael said it doesn’t schedule, not enough time for 2 flushes
6/22/2026 - Adam is telling Michael they need to create packages in stratus for how they want hac jumpers, bypasses split up
Adam is proposing a fabrication kick off meeting with Ryan and Curtis to get everyone on board
Micheal needs 8 weeks, Curtis needs 3 weeks for example
Jacob says curtis wants packages created by cost codes, but we are talking about splitting them by areas
Paul says give tom a curtisy that we are rele
Need to update the 6" flush skid and put a bleed olet on the return vertical
Paul says hes not sure where the Bypasses are as far as UG Bypass
Pual not sure when production will start for Near site, installing bypasses on HAC on near site
He will then put the spools in the appropriate package
06/25/26 - THU (+5 Meetings)
630-710amLEB | BIM | Faith x Turner
Luke Jost - Joe Dorinsville
Edwin Perez from Turner hosted
5/14/26 - - Joe Brought up the access panels for Flush system, asked about rating, I would have to check submittals to verify. Me and Lance holmes informed joe the flush systems are temporary, once done, they get removed and the access panel stay
Anna said they were aware, but not the finalized locations, now they will be going through Valley for engineering, excel engineering to make sure everything is accounted for, engineered
Talked to Stefan, we are not providing the Access Panel, its GC2 wall, they are providing it
I need to check on RO system, ACCess panel and it looks like location may be borked
Scott asked about sign offs for lighting scope to base build duct connections, Joe said they havent covered it, sign off is around end of June. They will be circling back to loop area not that they have certain paperwork available
Joe said any issue can be brought up at anytime
5/21/265 - No John Rhee, Brent, Thomas Holler, NO PM TEAM
They went over stud wall model, Lance asking about raceways for security and bus ducts
5/28/2026 - They went over electrical stuff, skid placement, wall leave outs
Turner wants a meeting with Helm and Southland to go over Wall penetrations
Joe D discussed Span model naming, keeping them the same and consistant.
Will need to relink LEB Span models since they have new models with Nucor suffix
6/4/2026 - Eduardo Ibanez brought up Status of Facility Water Stubups asking if Verification of Stubups with Mortenson needed. Had Crider submitted? Lance was saying Ryan would have this info and asking if Ryan was in meeting
NO PM Team present
I sent PM Team a summary email
I explained, Ryan used HDR model for coordination, I worked with HDR to get everything line up, we provided dimensions, everyone agreed to them, now stub ups are off, Lance Resposnded to John Rhees email asking what is being done
I said we need to start having meeting to go over this issue since its so critical
Luke Jost told eduardo to add an action item for this and lance said he will head this off
6/11/2026 - I brought up the FW UG being off again, told the group Ben Kozel with crider said they were backfilling in layers and trying to get the stub ups on the POC/CIA points
Overhead Signoff is schedule for 6/30
Scott asked if it was entire building for NWB, Joe says yes
Joe Brought up IMP walls changing to Framed walls, Anna? Said it was still being worked on
Verify LEB10 POC For DCW
Verify DCW POCs line up with CIA
Lance said they are also providing a hose connection for discharge, I stated they are using the FLOOR Drains in center of gallery for discharge, Adam corrected me saying John has requested different discharge points. Wouldn've been nice to know.
Someone asked about the Flex piping from the 8" skid hitting the column, I told them it was flex pipe and temporary, that it will bend around the column
Vent in 6-19x6-D, adam told them to put in between MES Skid
Waldinger is doing the bypass on LEB6
Building 6 MES loops are showing misalignment with Waldinger Bypass
NO PM Team present
I said I would like it added to this meetings notes, Joe Dorinsville basically shut it down, saying it was a field issue
I said it was our issue also since we are constantly being asked to do overlays, which were happy to help any way we can, but this was more of a helm situation since they are the responsible party to connect to the UG and provide us with accurate points of contact according to the CIA
Joe reiterated it was a field issue
6/18/2026 - Edwin Perez is showing Verification on stub ups w mortneson needed. Pending Submittal. Eng. Drawings to be submitted - Crider and Crider. He said this is still on going
Edwins model view still shows MP Shifted to plan right, access panels were to the right of the wall they are supposed to be in
LEB6 Arch Coordination model is showing everyhting off, MES Skid not lining up, mp is to the right, access panels are to the right of the walls they are supposed to be in.
LEB10, checked with Joe D, things line up there.
6/25/2026 - Joe, Greg, Luke Long, Greg went over Electrical coordination
I sent email to PM Team, no one was present
Eduardo Ibanez brought up Status of Facility Water Stubups asking if Verification of Stubups with Mortenson needed. Had Crider submitted? He brought this up again. I explained again that we provided dimensions for LEB10 and LEB1 to Mortensen, Crider and HDR, they all agreed
I told group that I also emailed these dimensions to Waldinger for Region 2, but havent received any comments or response from anyone.
Scott asked about tracking for signoff on 6/30, eduardo said yes
Luke Jost asked about LEB10 Embeds to make sure they are getting tracked by turner
Edwin Perez asked about Waldinger Bypass and alignment to SI MES Loop Connection
I told Edwin Perez I provided poc dimensions and elevations, but havent received any response
Edwin said he will bring up in next BIM meeting
900amTXE-FTI Weekly Sync Meeting
Luke Justice
Luke was asking about scanning at TXE10, He said coordinate with Greg Hueramo, he will be setting up an origination email
I told luke they need to have all areas ready for scanning since the team cant be sent out every other day, reset up, etc
I asked for Control point map, he said get with Greg Hueramo
I explained to him what the scanning was
I told him they will need to add paul hernandex, jeremy miller and adam brown to email
John Cowhey said he has a 1 pager for Site orientation which will be 8 hours
They will be enforcing badging within the next few weeks. No badge no access, Visitor badges will be available but not allowed to work
Luke will put together a schedule for orientation
11/17/26 - is new date for 0 prep according to John Cowhey
Forward FW off email to Luke, original email was sent out 4/17. I resent to Luke Justice
I told him Jeff Balthrop was involved a few weeks back
Send Luke Discrepancy on Anchor locations with BZI Wall panels, NWCs etc from Adam email, Adam email 5/5, TXE Adam email 5/6
Verify anchors at TXE and LEB, check they've been submitted to FTI
Send notice to John Cowhey, luke justice
They asked when Southland is looking at manning the site, jeremy informed them no PM team were available at this time to answer
new schedule coming out Friday
Got with michael kolnik, he sent out Shop Drawing submittal request to Eric Boehger
5/28/2026 - Loop Keylan and Michael into the Anchor clash info and meeting for Friday
Luke says bypass are fabbed, not installed will be installed next week, sent out email to everyone, paul, jeremy, michael
Need to coordinate orientation, drug testing
Day zero schedule? Luke said he was supposed to get last Friday, not seeing anything new
Luke showed the Faith TXE Anchor Shop Drawing submittals, they are only for the TXE10,1,2 Plates don’t know why it has TXE3 on the label
Not showing any Shop drawing embed submittal info
NO PM Management was present, Keylan Rollins was for engineering
6/4/2026 - Luke Cancelled at 741am, Got DAMN MAN!!!!
6/11/2026 - Luke Cancelled at 741am, Got DAMN MAN!!!!
6/18/2026 - Luke asked about Issues, I was explaining a summary of Greg Heuromos meeting, then Michael Kolnik was there! It was nice
6/25/2026 - Michael says greg told him the bypass will be complete on 6/7, michael has scanning scheduled for 6/6
Jason with FTI will use truck to help scanning move around job
Scanners will need badges, they can be escorted according to michael who talked to security
Michael says no one onsite yet, they are on first of kind, michael and jacob did get badged
FTI does have a superintendant and a couple of upper management onsite
Fully mobilized first week of July
Luis says they have been requesting a lot of BIM information, Asbuilts, trench information, etc
Luke says a laser just got done for the Trench
Alec Harpel says first half of txe10 was scanned, still waiting for coordinates
Need FW stub ups, grounding whips and trenches
Luis is asking for points for the finish floor to verify elevation/flatness
TXE1 slab just started pouring last week, according to Luke
Micahel said they wont have water into the building, they need to truck it in and provide the minimum GPM with 3" connection
TXE10 shows 3" main with 3" drops
TXE1 shows 4" main with 3" drops
930amLEB | BIM COORDINATION LEB2
Emma will no longer be on this project
Kaushal Bagdekar with Turner ran the meeting, saying who to contact for what, I asked if he could send an email with that info
They went over underground clashes
5/28/2026 - Tristen with helm verified he is using LEB1 dimensions for LEB 2 elevations and locaitons for FW
6/11/2026 - No PM Team
Went Over UG issues, concrete pads
6/18/2026 - Kaushal Bagdekar
Did a flythrough for LEB2 going over exterior sectionalizers
LEB-2_SPAN_SS.rvt, verifying during meeting that the model is good, Checked LEB2 SPAN_SS model, couldn’t load content, says cant link in NuCOR
NO Interior Walls and framing, Valley, Diogo or Ruth said they will get with valley
No Interior Meta Wall Panels
6/25/2026 - NO PM TEAM
They went over UG issues for LEB2
1000 amLEB - BIM Coordination Meeting (Thu) | Meeting-Join | Microsoft Teams
Ryan Zoldan
LEB 6 due finalized next week
I requested a schedule from Ryan, he has the sign off, region schedule, I brought up a pull plan, be he says that will be through Turner
Mortensen is the Base build GC, why aren't they leading a pull plan schedule
John Rhee nor Brent were in this meeting
6/4/2026 - I brought up the LEB10 FW UG Stub ups totally missing the Dims, Ben Kozel was there and he stated they are bringing them back in to dimensions by backfilling a little and moving them, backfilling and moving them
He acknowledge that lance did contact him
6/11/2026 - Ben Kozel, said there were no issues that need to be talked about.
Richard lopez asked around the room for any issues regarding LEB10 or any others
NO PM Team
6/18/2026 - Richard Lopez Hosted, just asked for any issues with LEB10,1,2,3 Underground issues
Rantwiler asked when IWM for TXE10 was going to be signed off, Ethan says he will talke to kyle since they are not really split out
6/25/2026 - Going over LEB7,8
Ryan brought up LEB6, HDR model is not lining up with the Dimensions provided by SI
Ryan henderson said he will follow up
Ryan said we have all agreed to follow these dimesions, I added that I have distrubuted that dimesion sheet ot Waldinger and explained everything, but havent received a response yet
TXE1 looks good for the loop area sign off next week
Same with TXE2
6/4/2026 - Own B ran the meeting going over TXE1 and 2
6/11/2026 - Owen B, says TXE10 Loop for sign off
TXE2 Core scheduled for next week
TXE10 AB Datahall and Loop are signed off
TXE3 Alan lopez is running region 2 for signe off
TXE2 Loop and AB South sign off
issue 2602 - Cerris Vent in corner is clashing with Technical water, Rantwiler is saying they don’t have our model, I told them our model has been there for 6 months, the fact that HP is viewing it, means the model is available. If it’s a bridging issue we will help Cerris work it out
Trevor said he will get with rantwiler and get the model bridged, they will offset that vent around our TW Piping
They made comments about the TW skid being so close to the FW valves. Its been this way for over 6 months. Trevor also stated the vent will need an accessible cleanout
6/25/2026 - They just went over IWM and specific Electrical clashes
06/26/26 - FRI (+2 Meetings)
830amFTI & XPL LEB10 EMBED Plates Coordination with TCCO-SPO
Edwin Perez
Reece, Thomas Haller and Jake Moore were present with SI PM Team
XPL Cable tray
LEB1 and 2 is ESI Electrical
LEB6 and 7 Hunt and Alarmco
Jake Moore
Been dealing with Lance from Turner for concrete coordination
1000amLTG Ketchup
Tom is sending notes for Engineer Review drawings
HRV - Access Panels and Embed Location drawings
use TXE as example for HRV Access Panel,
HRV 100 and EMT100 have anchor drawings in network suite building
Use LEB for embed drawing example
EMT Component interface drawings
NO olets on jumpers, adam is taking off
Need to batch LEB HAC Bypass, Pups and Jumpers
Interior outside fw bypass Even, interior is odd
These will be pencil whipped in BlueBeam, not actual batched in revit
Curtis says he doesn’t care about tracking each one, he just needs a count
Jumpers will be 1 for supply and 1 for return
Do pup pieces together, suply and return on 1 sheet
Adam told daniel to get the batching done in lebnwb revit
All buildings need batched, published to stratus this gives QR codes, then use SI Tools to put QR Codes on Assemblies
Then go to Blue Beam and use a blank sheet with QR Code, put custom name on sheet
Daniel will use Fernando to Batch then Isiah to penil whip
Once we get the MES new pipe supports back from Engineering, need to update models, update spools, get info out
6/15/26 - 6/21/26
06/15/26 - MON (+1 Meetings)
900amLightning TXE Staff Meeting | Meeting-Join | Microsoft Teams
Jacob Gelhousen
Will do scans after Cerris installs bypasses
6/1/2026 - Noel Nunez says Alehandro Chew will be safety manager
Michael said he sent TXE3 embeds along with PDF dimension in mid April
Doesn’t think TXE3 has been poured, think they are behind schedule
Says we havent been funded for Region 2, he is sending out embeds as needed
Michael asked what the question was about RO and TW, I said it was going over how to connect to the RO skid, from DCW and to TW MES
Michael asked if MES Loops were completed, adam said yes, he created new BOMs
Michael said his goal is to get everything ordered
Michale Paul said they thought the walls weren't going to be in until they could do anchor
They said that was what was agreed to
6/8/2026 - Michael said they had a PM Coins Mandatory meeting and couldn't host the meeting
6/15/2026 - Chris Moss came on board from TSMC, Pipe fitter, GF
Jose Alejandro Chew, new Safety Manager for TXE
06/16/26 - TUE (+4 Meetings)
800amWeekly BIM Coordination Meeting - Region 2 (ZOOM)
Alan Lopez, Kyle Cummings (Hensel Phelps) / Ethen Berry
No one started the meeting, I sent an email, they said Alan was PTO and they started meeting late
They went over Region 2 underground, sign off later this week
5/26/26 - Allen Lopez Went over Region 2 again, said they were going to do a main signoff then a branch signoff. Covered a lot of UG clashes
6/2/2026
2 weeks sign off branch
6/9/2026
6/16/2026
Allen Lopez says he doesn't see Sure Steel model in TXE3, Kyle says also no Diversified, but Sure Steel model is there, needs added
Signoff schedule was not bridged, the one on FTI is outdated. Kyle and Justin said they would get the bridge up to date
Files - Data Management
830amLEB - BIM Coordination Meeting (Tue) | Meeting-Join | Microsoft Teams
Ryan Zoldan, Mortenson (GC1)
Missed for the 8am meeting
6/16/2026
1000amLightning-Eng-Coord Huddle | Meeting-Join | Microsoft Teams
Tia/ Tom
Follow up on HAC Panel clashes with Patrick Brinnehal
Meeting to go over stratus and models with all PMs, Adam, Scott, Supers sometime next week, look at schedules
Chris Chase is the PM of EMT
5/26/2026 - Check if Adam got the 4" Welded Bypass to Shop, from 5/5/25 email in Inbox "Im shooting to have the LTG build out scope package done by end of week (For Review only not for construction). "
Verify what spools have been put on stratus for TIA/TOM Lightning huddle
Need meeting to discuss, txe10 anchor clashing with interior of walls, adam sent info out about conflicting models, but as of today, there is still clashes
RFI says they are changing wall to Gypsm board and expanding toward corridor 2.5"
6/2/2026 - We did get 2 more sites in Ohio
SI will be integrator
Heath introduced Peyton Steveons as VDC supervisor
Starting with HRV
Melanie introduced Vasi, VDC specialist helping out ron and melanie
Tia went over deliverable schedules
Per site, per building
She setup a break out meeting
Adam said they are moving the walls away from anchors so we are clear
Adam said we are 1/2" clear from plate, it will be a field issue installing the plate
Michael said he will talk to paul, he doesn't know what to do, he will call greg
only 2 walls changed from IMP, 2 others are still IMP
Michael said Greg told him they are putting walls up next week
Told Tia I sent snip of Dog Leg Metraflex in chat, didn’t get any smiles
Let her know we have LEB complete, TXE10,1,2 is complete
Adam said he will give link to CIAs, TXE3-12 and LEB3-12 not ready
Adam had meeting with HRV, told them to start using our coordination models for coordination
Quick hello, this is who we are meeting
with MC Dean
Mealnie says they will be updating projects to new architect model
Type F - 4 buildings
Type G - 2 buildings
6/9/2026 - Adam said they are going to move the MSA, HAC spools to the Lighting Program, for one source
Melanie and Keylan said it can be done
1200pmTXE-Region3 Coordination Meeting
Jade B Lowe (Hensel Phelps)
Jade is in charge of Region 3
Kyle cummins is in charge of site
Filll out contact excel sheet, put bim lead and project manager
Kyle - LOD 450 project, all installed elements are modeled, then asbuilts are fed back in to model
Indicate in the model some where that the asbuilt has been applied and model has been adjusted
06/18/26 - THU (+5 Meetings)
630-710amLEB | BIM | Faith x Turner
Luke Jost - Joe Dorinsville
Edwin Perez from Turner hosted
5/14/26 - - Joe Brought up the access panels for Flush system, asked about rating, I would have to check submittals to verify. Me and Lance holmes informed joe the flush systems are temporary, once done, they get removed and the access panel stay
Anna said they were aware, but not the finalized locations, now they will be going through Valley for engineering, excel engineering to make sure everything is accounted for, engineered
Talked to Stefan, we are not providing the Access Panel, its GC2 wall, they are providing it
I need to check on RO system, ACCess panel and it looks like location may be borked
Scott asked about sign offs for lighting scope to base build duct connections, Joe said they havent covered it, sign off is around end of June. They will be circling back to loop area not that they have certain paperwork available
Joe said any issue can be brought up at anytime
5/21/265 - No John Rhee, Brent, Thomas Holler, NO PM TEAM
They went over stud wall model, Lance asking about raceways for security and bus ducts
5/28/2026 - They went over electrical stuff, skid placement, wall leave outs
Turner wants a meeting with Helm and Southland to go over Wall penetrations
Joe D discussed Span model naming, keeping them the same and consistant.
Will need to relink LEB Span models since they have new models with Nucor suffix
6/4/2026 - Eduardo Ibanez brought up Status of Facility Water Stubups asking if Verification of Stubups with Mortenson needed. Had Crider submitted? Lance was saying Ryan would have this info and asking if Ryan was in meeting
NO PM Team present
I sent PM Team a summary email
I explained, Ryan used HDR model for coordination, I worked with HDR to get everything line up, we provided dimensions, everyone agreed to them, now stub ups are off, Lance Resposnded to John Rhees email asking what is being done
I said we need to start having meeting to go over this issue since its so critical
Luke Jost told eduardo to add an action item for this and lance said he will head this off
6/11/2026 - I brought up the FW UG being off again, told the group Ben Kozel with crider said they were backfilling in layers and trying to get the stub ups on the POC/CIA points
Overhead Signoff is schedule for 6/30
Scott asked if it was entire building for NWB, Joe says yes
Joe Brought up IMP walls changing to Framed walls, Anna? Said it was still being worked on
Verify LEB10 POC For DCW
Verify DCW POCs line up with CIA
Lance said they are also providing a hose connection for discharge, I stated they are using the FLOOR Drains in center of gallery for discharge, Adam corrected me saying John has requested different discharge points. Wouldn've been nice to know.
Someone asked about the Flex piping from the 8" skid hitting the column, I told them it was flex pipe and temporary, that it will bend around the column
Vent in 6-19x6-D, adam told them to put in between MES Skid
Waldinger is doing the bypass on LEB6
Building 6 MES loops are showing misalignment with Waldinger Bypass
NO PM Team present
I said I would like it added to this meetings notes, Joe Dorinsville basically shut it down, saying it was a field issue
I said it was our issue also since we are constantly being asked to do overlays, which were happy to help any way we can, but this was more of a helm situation since they are the responsible party to connect to the UG and provide us with accurate points of contact according to the CIA
Joe reiterated it was a field issue
6/18/2026 - Edwin Perez is showing Verification on stub ups w mortneson needed. Pending Submittal. Eng. Drawings to be submitted - Crider and Crider. He said this is still on going
Edwins model view still shows MP Shifted to plan right, access panels were to the right of the wall they are supposed to be in
LEB6 Arch Coordination model is showing everyhting off, MES Skid not lining up, mp is to the right, access panels are to the right of the walls they are supposed to be in.
LEB10, checked with Joe D, things line up there.
900amTXE-FTI Weekly Sync Meeting
Luke Justice
Luke was asking about scanning at TXE10, He said coordinate with Greg Hueramo, he will be setting up an origination email
I told luke they need to have all areas ready for scanning since the team cant be sent out every other day, reset up, etc
I asked for Control point map, he said get with Greg Hueramo
I explained to him what the scanning was
I told him they will need to add paul hernandex, jeremy miller and adam brown to email
John Cowhey said he has a 1 pager for Site orientation which will be 8 hours
They will be enforcing badging within the next few weeks. No badge no access, Visitor badges will be available but not allowed to work
Luke will put together a schedule for orientation
11/17/26 - is new date for 0 prep according to John Cowhey
Forward FW off email to Luke, original email was sent out 4/17. I resent to Luke Justice
I told him Jeff Balthrop was involved a few weeks back
Send Luke Discrepancy on Anchor locations with BZI Wall panels, NWCs etc from Adam email, Adam email 5/5, TXE Adam email 5/6
Verify anchors at TXE and LEB, check they've been submitted to FTI
Send notice to John Cowhey, luke justice
They asked when Southland is looking at manning the site, jeremy informed them no PM team were available at this time to answer
new schedule coming out Friday
Got with michael kolnik, he sent out Shop Drawing submittal request to Eric Boehger
5/28/2026 - Loop Keylan and Michael into the Anchor clash info and meeting for Friday
Luke says bypass are fabbed, not installed will be installed next week, sent out email to everyone, paul, jeremy, michael
Need to coordinate orientation, drug testing
Day zero schedule? Luke said he was supposed to get last Friday, not seeing anything new
Luke showed the Faith TXE Anchor Shop Drawing submittals, they are only for the TXE10,1,2 Plates don’t know why it has TXE3 on the label
Not showing any Shop drawing embed submittal info
NO PM Management was present, Keylan Rollins was for engineering
6/4/2026 - Luke Cancelled at 741am, Got DAMN MAN!!!!
6/11/2026 - Luke Cancelled at 741am, Got DAMN MAN!!!!
6/18/2026 - Luke asked about Issues, I was explaining a summary of Greg Heuromos meeting, then Michael Kolnik was there! It was nice
930amLEB | BIM COORDINATION LEB2
Emma will no longer be on this project
Kaushal Bagdekar with Turner ran the meeting, saying who to contact for what, I asked if he could send an email with that info
They went over underground clashes
5/28/2026 - Tristen with helm verified he is using LEB1 dimensions for LEB 2 elevations and locaitons for FW
6/11/2026 - No PM Team
Went Over UG issues, concrete pads
6/18/2026 - Kaushal Bagdekar
Did a flythrough for LEB2 going over exterior sectionalizers
LEB-2_SPAN_SS.rvt, verifying during meeting that the model is good, Checked LEB2 SPAN_SS model, couldn’t load content, says cant link in NuCOR
NO Interior Walls and framing, Valley, Diogo or Ruth said they will get with valley
No Interior Meta Wall Panels
1000 amLEB - BIM Coordination Meeting (Thu) | Meeting-Join | Microsoft Teams
Ryan Zoldan
LEB 6 due finalized next week
I requested a schedule from Ryan, he has the sign off, region schedule, I brought up a pull plan, be he says that will be through Turner
Mortensen is the Base build GC, why aren't they leading a pull plan schedule
John Rhee nor Brent were in this meeting
6/4/2026 - I brought up the LEB10 FW UG Stub ups totally missing the Dims, Ben Kozel was there and he stated they are bringing them back in to dimensions by backfilling a little and moving them, backfilling and moving them
He acknowledge that lance did contact him
6/11/2026 - Ben Kozel, said there were no issues that need to be talked about.
Richard lopez asked around the room for any issues regarding LEB10 or any others
NO PM Team
6/18/2026 - Richard Lopez Hosted, just asked for any issues with LEB10,1,2,3 Underground issues
Rantwiler asked when IWM for TXE10 was going to be signed off, Ethan says he will talke to kyle since they are not really split out
TXE1 looks good for the loop area sign off next week
Same with TXE2
6/4/2026 - Own B ran the meeting going over TXE1 and 2
6/11/2026 - Owen B, says TXE10 Loop for sign off
TXE2 Core scheduled for next week
TXE10 AB Datahall and Loop are signed off
TXE3 Alan lopez is running region 2 for signe off
TXE2 Loop and AB South sign off
issue 2602 - Cerris Vent in corner is clashing with Technical water, Rantwiler is saying they don’t have our model, I told them our model has been there for 6 months, the fact that HP is viewing it, means the model is available. If it’s a bridging issue we will help Cerris work it out
Trevor said he will get with rantwiler and get the model bridged, they will offset that vent around our TW Piping
They made comments about the TW skid being so close to the FW valves. Its been this way for over 6 months. Trevor also stated the vent will need an accessible cleanout
06/19/26 - FRI (+1 Meetings)
900amLEB1, 3/4/26 HELM Bypass not aligned, I told Jay they were cleared and looking good
LEB6 with waldinger is another issue
TXE issue 182, cerris plate for Testing loop clashing with our MES Loop, this could be a timing issue if they don't remove their testing loop before our install schedule
TXE issue #363 BZI wall component going through pipe
TXE issue #362, REI Plate hitting our anchor
TXE Isse #359, Cerris will offset their vent around our TW
#358
#357 acces panels with BZI components
#354 REI Strut hitting our MES Pipe
#350 REI Hitting ACCESS door
#348 REI Hitting our TW with conduit
#346 - PVC is running through access panel and hitting flushing pipe
Issue #182 - Cerris Test loop plates hitting our MES Loops sent info to patrick marshall, don’t remember a response
I mentioned that since we now have access to HP and Turner, I can attend directly to the clashes and issues on their site to hopefuly expedite any solutions and decrease the amount of situations that flow down the chain.
6/8/26 - 6/14/26
06/08/26 - MON (+3 Meetings)
630amLightning Technical Water Header Status
Made notes, emailed to everyone
700amLightning Ketchup meeting
Adam wants spools and engineer sheets done by end of week for Review early next week
900amLightning TXE Staff Meeting | Meeting-Join | Microsoft Teams
Jacob Gelhousen
Will do scans after Cerris installs bypasses
6/1/2026 - Noel Nunez says Alehandro Chew will be safety manager
Michael said he sent TXE3 embeds along with PDF dimension in mid April
Doesn’t think TXE3 has been poured, think they are behind schedule
Says we havent been funded for Region 2, he is sending out embeds as needed
Michael asked what the question was about RO and TW, I said it was going over how to connect to the RO skid, from DCW and to TW MES
Michael asked if MES Loops were completed, adam said yes, he created new BOMs
Michael said his goal is to get everything ordered
Michale Paul said they thought the walls weren't going to be in until they could do anchor
They said that was what was agreed to
6/8/2026 - Michael said they had a PM Coins Mandatory meeting and couldn't host the meeting
06/09/26 - TUE (+4 Meetings)
800amWeekly BIM Coordination Meeting - Region 2 (ZOOM)
Alan Lopez, Kyle Cummings (Hensel Phelps) / Ethen Berry
No one started the meeting, I sent an email, they said Alan was PTO and they started meeting late
They went over Region 2 underground, sign off later this week
5/26/26 - Allen Lopez Went over Region 2 again, said they were going to do a main signoff then a branch signoff. Covered a lot of UG clashes
6/2/2026
2 weeks sign off branch
6/9/2026
830amLEB - BIM Coordination Meeting (Tue) | Meeting-Join | Microsoft Teams
Ryan Zoldan, Mortenson (GC1)
Missed for the 8am meeting
1000amLightning-Eng-Coord Huddle | Meeting-Join | Microsoft Teams
Tia/ Tom
Follow up on HAC Panel clashes with Patrick Brinnehal
Meeting to go over stratus and models with all PMs, Adam, Scott, Supers sometime next week, look at schedules
Chris Chase is the PM of EMT
5/26/2026 - Check if Adam got the 4" Welded Bypass to Shop, from 5/5/25 email in Inbox "Im shooting to have the LTG build out scope package done by end of week (For Review only not for construction). "
Verify what spools have been put on stratus for TIA/TOM Lightning huddle
Need meeting to discuss, txe10 anchor clashing with interior of walls, adam sent info out about conflicting models, but as of today, there is still clashes
RFI says they are changing wall to Gypsm board and expanding toward corridor 2.5"
6/2/2026 - We did get 2 more sites in Ohio
SI will be integrator
Heath introduced Peyton Steveons as VDC supervisor
Starting with HRV
Melanie introduced Vasi, VDC specialist helping out ron and melanie
Tia went over deliverable schedules
Per site, per building
She setup a break out meeting
Adam said they are moving the walls away from anchors so we are clear
Adam said we are 1/2" clear from plate, it will be a field issue installing the plate
Michael said he will talk to paul, he doesn't know what to do, he will call greg
only 2 walls changed from IMP, 2 others are still IMP
Michael said Greg told him they are putting walls up next week
Told Tia I sent snip of Dog Leg Metraflex in chat, didn’t get any smiles
Let her know we have LEB complete, TXE10,1,2 is complete
Adam said he will give link to CIAs, TXE3-12 and LEB3-12 not ready
Adam had meeting with HRV, told them to start using our coordination models for coordination
Quick hello, this is who we are meeting
with MC Dean
Mealnie says they will be updating projects to new architect model
Type F - 4 buildings
Type G - 2 buildings
6/9/2026 - Adam said they are going to move the MSA, HAC spools to the Lighting Program, for one source
Melanie and Keylan said it can be done
1200pmTXE-Region3 Coordination Meeting
Jade B Lowe (Hensel Phelps)
Jade is in charge of Region 3
Kyle cummins is in charge of site
Filll out contact excel sheet, put bim lead and project manager
Kyle - LOD 450 project, all installed elements are modeled, then asbuilts are fed back in to model
Indicate in the model some where that the asbuilt has been applied and model has been adjusted
06/10/26 - WED (+6 Meetings)
800amTXE/LEB Weekly Internal BIM Coordination | Meeting-Join | Microsoft Teams
Jay Keiser - FTI
LEB10 RO Hitting Column
LEB10 FLEX HOSE on 8" Flush skid hitting column, need to clear clashes
talked about email I sent about a list of which models to use for which trades as far as Walls, Wall Panels, Electrical, Arch, Structural etc
Kyle said he was still working on that
John Cowhey is asking about Lugs on the MES
I will chase this down, find who responded Johns email and start there
Robert Cheek responded on Monday saying he would get the answer same day, still waiting
I told Jay we are currently working through shop drawings and spools, while we are doing those we are paying attention to clashes and working through the clashes
I Brought up the FW underground being off and that we will be scanning and verifying CIA POC's, Should be doing this within a week
5/27/2026 - I BROUGHT UP LEB1 COORDINATING WITH CRIDER NO MODEL, USING HDR FOR UNDERGROUND COORDINATION
JAY BROUGHT UP TXE10 ANCHOR CLASH WITH WALL, ADAM SENT EMAIL ASKING ABOUT IT, SOMEONE SAID THEY WERE CHANGING WALL IN A EMAIL RESPONSE, ADAM REQUESTED MEETING, NO ONE RESPONDED
JAY ADDED THIS AS AN ACTION ITEM
EMMA SENT EMAIL REQUESTING CLARIFICATION, TRISTEN WAS CONFUSED
LUKE SAID HE WILL DISCUSS IN HIS MEETING WITH MORTENSON
JAY ADDED THIS AS AN ACTION ITEM
6/3/2026 - New LEB Mech and Plumbing meeting on Wed, John and Reece involved, going over FW stub up locations and F/F water gallery connections
Informed John of Convos with Greg to coordinate wall install with coring of anchor plate holes
Told Jay/John, Lance Holmes is coordinating with other trades on fix for LEB UG FW stubups not hitting POC points or dimensions
6/10/2026 - Verify Span models work on LEB10, 1, 2
800amTXE/LEB Weekly Internal BIM Coordination | Meeting-Join | Microsoft Teams
Jay Keiser - FTI
LEB10 RO Hitting Column
LEB10 FLEX HOSE on 8" Flush skid hitting column, need to clear clashes
talked about email I sent about a list of which models to use for which trades as far as Walls, Wall Panels, Electrical, Arch, Structural etc
Kyle said he was still working on that
John Cowhey is asking about Lugs on the MES
I will chase this down, find who responded Johns email and start there
Robert Cheek responded on Monday saying he would get the answer same day, still waiting
I told Jay we are currently working through shop drawings and spools, while we are doing those we are paying attention to clashes and working through the clashes
I Brought up the FW underground being off and that we will be scanning and verifying CIA POC's, Should be doing this within a week
5/27/2026 - I BROUGHT UP LEB1 COORDINATING WITH CRIDER NO MODEL, USING HDR FOR UNDERGROUND COORDINATION
JAY BROUGHT UP TXE10 ANCHOR CLASH WITH WALL, ADAM SENT EMAIL ASKING ABOUT IT, SOMEONE SAID THEY WERE CHANGING WALL IN A EMAIL RESPONSE, ADAM REQUESTED MEETING, NO ONE RESPONDED
JAY ADDED THIS AS AN ACTION ITEM
EMMA SENT EMAIL REQUESTING CLARIFICATION, TRISTEN WAS CONFUSED
LUKE SAID HE WILL DISCUSS IN HIS MEETING WITH MORTENSON
JAY ADDED THIS AS AN ACTION ITEM
6/3/2026 - New LEB Mech and Plumbing meeting on Wed, John and Reece involved, going over FW stub up locations and F/F water gallery connections
Informed John of Convos with Greg to coordinate wall install with coring of anchor plate holes
Told Jay/John, Lance Holmes is coordinating with other trades on fix for LEB UG FW stubups not hitting POC points or dimensions
6/10/2026 - Verify Span models work on LEB10, 1, 2
6/17/2026 - Checked LEB1, Span_SS model is still only showing Labeled grids, no steel in revit linked model, 2models, same dates, different version, latest verison wont load, gives error
Bring up Walbringer as new MP contractor on LEB6, sent email out with dimension sheets for someone to get them the information
Coordination Sign off
Jay gave links to Turner and HP sign off locations
Clash Review
Jay said he will go through and filter out white noise, setup a meeting to over others. I told him whenever he wants and I will be there
Friday 6/19/22 9am
900amSouthland Management Mid year Check In
Was AI Recorded, watch the notes
900amSouthland Management Mid year Check In
Was AI Recorded, watch the notes
1000amBIM Round Up | Meeting-Join | Microsoft Teams
Michael Kolnik
Jeremy says they are supposed to be scanning in a week or 2
Jeremy needs Floor drain locations from Cerris so they know exactly where they land, Need to get with Patrick Marshall at Cerris and see if we can get some shop drawings.
6/3/2026 - MICHAEL ASKED ABOUT CURTIS GIVING HIM AN ORDER REQUEST THAT HE THOUGHT WAS SUPPOSED TO BE FOR FLUSH SKIDS
IT HAD 16X14 TEES, 14" 90S, 8" STAINLESS CAPS
HE DIDN’T KNOW WHERE THESE TEES CAME FROM
I TOLD HIM THEY WERE FOR THE MES LOOPS, NOT THE SKIDS
THE 14" 90S WERE PROBABLY FOR THE FLUSH SPOOL TO CONNECT TO THE FLEX SKID
MICHAEL SAID HE CANT GET THEM IN TIME, SIAD HE IS LOOKING AT DOING A MATERIAL SUBSTITUTE REQUEST, I SAID IT ASAP AND PUT CURTIS IN THE LOOP ON IT
1000amBIM Round Up | Meeting-Join | Microsoft Teams
Michael Kolnik
Jeremy says they are supposed to be scanning in a week or 2
Jeremy needs Floor drain locations from Cerris so they know exactly where they land, Need to get with Patrick Marshall at Cerris and see if we can get some shop drawings.
6/3/2026 - MICHAEL ASKED ABOUT CURTIS GIVING HIM AN ORDER REQUEST THAT HE THOUGHT WAS SUPPOSED TO BE FOR FLUSH SKIDS
IT HAD 16X14 TEES, 14" 90S, 8" STAINLESS CAPS
HE DIDN’T KNOW WHERE THESE TEES CAME FROM
I TOLD HIM THEY WERE FOR THE MES LOOPS, NOT THE SKIDS
THE 14" 90S WERE PROBABLY FOR THE FLUSH SPOOL TO CONNECT TO THE FLEX SKID
MICHAEL SAID HE CANT GET THEM IN TIME, SIAD HE IS LOOKING AT DOING A MATERIAL SUBSTITUTE REQUEST, I SAID IT ASAP AND PUT CURTIS IN THE LOOP ON IT
6/10/2026 - Michael said he is having a meeting Friday about FW scanning and fix for fw off dims, with HP, FTI, Scanners,
6/17/2026 - Adam brought up supports, new design doesn't leave room for any adjustments
Michael says scanning will be around 7/1, if UG is off, michael says we will have to fix and charge HP
Are we going to have 8 unique supports
Paul says we will have to do it in the field
Paul and Michael agreed a new stand with Trapeze hangers will work, adam wil resubmit
Michael has order all fittings and pipe for TXE10 and TXE2 for MES loops
Region 1 is staying with 1 flush skid
06/12/26 - FRI (+1 Meetings)
800amFacility Water scan (TXE 10 )
Greg Hueramo HP
First set of bypasses, west side and middle installed on 6/22, Greg will sent out email to Michael, zach when the next sets will be done
After scanning they will be able to determine what will be needed to drill anchors
Cant drill anchors until after scanning in case they need to adjust anchors locations
Greg will send out control points to james and michael
6/1/26 - 6/7/26
06/01/26 - MON (+2 Meetings)
700amLEB ACC Training
Peter Tiebout, Mortenson, QC Engineer
Email Peter directly for any questions
Mortenson ACC
BUILD
Insight - 3rd party testing, inspection request, need to be filled out
To request inspection for third party inspection
Not sure as of now if they are going to use for city
Sheets
use search, discipline, set to filter
use compare to see differences between sets
use bottom right grid button to navigate to other sheets instead of closing sheet and picking new one
Save searches to be able to quick navigate back to that search
Files
Sent out weekly
Pull schedules
Some permissions can restrict access to certain folders or files
Try not to use files to browse sheets, use sheets module, more efficient, more accurate
Specifications
View required specifications, materials, methods for different phases/trades/ systems
Forms
Forms will need to be filled out for equipment, Turner and Faith own majority of OFCI equipment
Create Checklists using forms for specific tasks, location, due date, general information
Meta and Third party do go through forms, issues, so they are important
Reason for forms, Mortenson inspects 100% of their work and use forms to coordinate, verify checklists, proof of inspections
Photos
RFI
Mortenson -> HDR -> Mortenson will distribute
Every Friday, Peter has meetings with Faith/Turner to insure bridging of RFIs and make sure they are distributed
For trade
New RFI, Open for Manager, Select Julie as manager in Ball in Court
Submittals
Meetings
Can create action items, notes, etc
Coorespondence
Schedule
Assets
Reports
Members
900amLightning TXE Staff Meeting | Meeting-Join | Microsoft Teams
Jacob Gelhousen
Will do scans after Cerris installs bypasses
6/1/2026 - Noel Nunez says Alehandro Chew will be safety manager
Michael said he sent TXE3 embeds along with PDF dimension in mid April
Doesn’t think TXE3 has been poured, think they are behind schedule
Says we havent been funded for Region 2, he is sending out embeds as needed
Michael asked what the question was about RO and TW, I said it was going over how to connect to the RO skid, from DCW and to TW MES
Michael asked if MES Loops were completed, adam said yes, he created new BOMs
Michael said his goal is to get everything ordered
Michale Paul said they thought the walls weren't going to be in until they could do anchor
06/02/26 - TUE (+4 Meetings)
715am-815amLightning Ketchup
Adam Brown
I brought up VDC exporting the FTI Export Views for the MES Models. I started, seen the FTI Export views were missing from TXE8 and said fuck it, let VDC do their own job
800amWeekly BIM Coordination Meeting - Region 2 (ZOOM)
Alan Lopez, Kyle Cummings (Hensel Phelps) / Ethen Berry
No one started the meeting, I sent an email, they said Alan was PTO and they started meeting late
They went over Region 2 underground, sign off later this week
5/26/26 - Allen Lopez Went over Region 2 again, said they were going to do a main signoff then a branch signoff. Covered a lot of UG clashes
6/2/2026
2 weeks sign off branch
830amLEB - BIM Coordination Meeting (Tue) | Meeting-Join | Microsoft Teams
Ryan Zoldan, Mortenson (GC1)
Missed for the 8am meeting
1000amLightning-Eng-Coord Huddle | Meeting-Join | Microsoft Teams
Tia/ Tom
Follow up on HAC Panel clashes with Patrick Brinnehal
Meeting to go over stratus and models with all PMs, Adam, Scott, Supers sometime next week, look at schedules
Chris Chase is the PM of EMT
5/26/2026 - Check if Adam got the 4" Welded Bypass to Shop, from 5/5/25 email in Inbox "Im shooting to have the LTG build out scope package done by end of week (For Review only not for construction). "
Verify what spools have been put on stratus for TIA/TOM Lightning huddle
Need meeting to discuss, txe10 anchor clashing with interior of walls, adam sent info out about conflicting models, but as of today, there is still clashes
RFI says they are changing wall to Gypsm board and expanding toward corridor 2.5"
6/2/2026 - We did get 2 more sites in Ohio
SI will be integrator
Heath introduced Peyton Steveons as VDC supervisor
Starting with HRV
Melanie introduced Vasi, VDC specialist helping out ron and melanie
Tia went over deliverable schedules
Per site, per building
She setup a break out meeting
Adam said they are moving the walls away from anchors so we are clear
Adam said we are 1/2" clear from plate, it will be a field issue installing the plate
Michael said he will talk to paul, he doesn't know what to do, he will call greg
only 2 walls changed from IMP, 2 others are still IMP
Michael said Greg told him they are putting walls up next week
Told Tia I sent snip of Dog Leg Metraflex in chat, didn’t get any smiles
Let her know we have LEB complete, TXE10,1,2 is complete
Adam said he will give link to CIAs, TXE3-12 and LEB3-12 not ready
Adam had meeting with HRV, told them to start using our coordination models for coordination
Quick hello, this is who we are meeting
with MC Dean
Mealnie says they will be updating projects to new architect model
Type F - 4 buildings
Type G - 2 buildings
06/04/26 - THU (+10 Meetings)
630-710amLEB | BIM | Faith x Turner
Luke Jost - Joe Dorinsville
Edwin Perez from Turner hosted
5/14/26 - - Joe Brought up the access panels for Flush system, asked about rating, I would have to check submittals to verify. Me and Lance holmes informed joe the flush systems are temporary, once done, they get removed and the access panel stay
Anna said they were aware, but not the finalized locations, now they will be going through Valley for engineering, excel engineering to make sure everything is accounted for, engineered
Talked to Stefan, we are not providing the Access Panel, its GC2 wall, they are providing it
I need to check on RO system, ACCess panel and it looks like location may be borked
Scott asked about sign offs for lighting scope to base build duct connections, Joe said they havent covered it, sign off is around end of June. They will be circling back to loop area not that they have certain paperwork available
Joe said any issue can be brought up at anytime
5/21/265 - No John Rhee, Brent, Thomas Holler, NO PM TEAM
They went over stud wall model, Lance asking about raceways for security and bus ducts
5/28/2026 - They went over electrical stuff, skid placement, wall leave outs
Turner wants a meeting with Helm and Southland to go over Wall penetrations
Joe D discussed Span model naming, keeping them the same and consistant.
Will need to relink LEB Span models since they have new models with Nucor suffix
6/4/2026 - Eduardo Ibanez brought up Status of Facility Water Stubups asking if Verification of Stubups with Mortenson needed. Had Crider submitted? Lance was saying Ryan would have this info and asking if Ryan was in meeting
NO PM Team present
I sent PM Team a summary email
I explained, Ryan used HDR model for coordination, I worked with HDR to get everything line up, we provided dimensions, everyone agreed to them, now stub ups are off, Lance Resposnded to John Rhees email asking what is being done
I said we need to start having meeting to go over this issue since its so critical
Luke Jost told eduardo to add an action item for this and lance said he will head this off
630-710amLEB | BIM | Faith x Turner
Luke Jost - Joe Dorinsville
Edwin Perez from Turner hosted
5/14/26 - - Joe Brought up the access panels for Flush system, asked about rating, I would have to check submittals to verify. Me and Lance holmes informed joe the flush systems are temporary, once done, they get removed and the access panel stay
Anna said they were aware, but not the finalized locations, now they will be going through Valley for engineering, excel engineering to make sure everything is accounted for, engineered
Talked to Stefan, we are not providing the Access Panel, its GC2 wall, they are providing it
I need to check on RO system, ACCess panel and it looks like location may be borked
Scott asked about sign offs for lighting scope to base build duct connections, Joe said they havent covered it, sign off is around end of June. They will be circling back to loop area not that they have certain paperwork available
Joe said any issue can be brought up at anytime
5/21/265 - No John Rhee, Brent, Thomas Holler, NO PM TEAM
They went over stud wall model, Lance asking about raceways for security and bus ducts
5/28/2026 - They went over electrical stuff, skid placement, wall leave outs
Turner wants a meeting with Helm and Southland to go over Wall penetrations
Joe D discussed Span model naming, keeping them the same and consistant.
Will need to relink LEB Span models since they have new models with Nucor suffix
6/4/2026 - Eduardo Ibanez brought up Status of Facility Water Stubups asking if Verification of Stubups with Mortenson needed. Had Crider submitted? Lance was saying Ryan would have this info and asking if Ryan was in meeting
NO PM Team present
I sent PM Team a summary email
I explained, Ryan used HDR model for coordination, I worked with HDR to get everything line up, we provided dimensions, everyone agreed to them, now stub ups are off, Lance Resposnded to John Rhees email asking what is being done
I said we need to start having meeting to go over this issue since its so critical
Luke Jost told eduardo to add an action item for this and lance said he will head this off
6/11/2026 - I brought up the FW UG being off again, told the group Ben Kozel with crider said they were backfilling in layers and trying to get the stub ups on the POC/CIA points
Overhead Signoff is schedule for 6/30
Scott asked if it was entire building for NWB, Joe says yes
Joe Brought up IMP walls changing to Framed walls, Anna? Said it was still being worked on
Verify LEB10 POC For DCW
Verify DCW POCs line up with CIA
Lance said they are also providing a hose connection for discharge, I stated they are using the FLOOR Drains in center of gallery for discharge, Adam corrected me saying John has requested different discharge points. Wouldn've been nice to know.
Someone asked about the Flex piping from the 8" skid hitting the column, I told them it was flex pipe and temporary, that it will bend around the column
Vent in 6-19x6-D, adam told them to put in between MES Skid
Waldinger is doing the bypass on LEB6
Building 6 MES loops are showing misalignment with Waldinger Bypass
NO PM Team present
I said I would like it added to this meetings notes, Joe Dorinsville basically shut it down, saying it was a field issue
I said it was our issue also since we are constantly being asked to do overlays, which were happy to help any way we can, but this was more of a helm situation since they are the responsible party to connect to the UG and provide us with accurate points of contact according to the CIA
Joe reiterated it was a field issue
900amTXE-FTI Weekly Sync Meeting
Luke Justice
Luke was asking about scanning at TXE10, He said coordinate with Greg Hueramo, he will be setting up an origination email
I told luke they need to have all areas ready for scanning since the team cant be sent out every other day, reset up, etc
I asked for Control point map, he said get with Greg Hueramo
I explained to him what the scanning was
I told him they will need to add paul hernandex, jeremy miller and adam brown to email
John Cowhey said he has a 1 pager for Site orientation which will be 8 hours
They will be enforcing badging within the next few weeks. No badge no access, Visitor badges will be available but not allowed to work
Luke will put together a schedule for orientation
11/17/26 - is new date for 0 prep according to John Cowhey
Forward FW off email to Luke, original email was sent out 4/17. I resent to Luke Justice
I told him Jeff Balthrop was involved a few weeks back
Send Luke Discrepancy on Anchor locations with BZI Wall panels, NWCs etc from Adam email, Adam email 5/5, TXE Adam email 5/6
Verify anchors at TXE and LEB, check they've been submitted to FTI
Send notice to John Cowhey, luke justice
They asked when Southland is looking at manning the site, jeremy informed them no PM team were available at this time to answer
new schedule coming out Friday
Got with michael kolnik, he sent out Shop Drawing submittal request to Eric Boehger
5/28/2026 - Loop Keylan and Michael into the Anchor clash info and meeting for Friday
Luke says bypass are fabbed, not installed will be installed next week, sent out email to everyone, paul, jeremy, michael
Need to coordinate orientation, drug testing
Day zero schedule? Luke said he was supposed to get last Friday, not seeing anything new
Luke showed the Faith TXE Anchor Shop Drawing submittals, they are only for the TXE10,1,2 Plates don’t know why it has TXE3 on the label
Not showing any Shop drawing embed submittal info
NO PM Management was present, Keylan Rollins was for engineering
6/4/2026 - Luke Cancelled at 741am, Got DAMN MAN!!!!
900amTXE-FTI Weekly Sync Meeting
Luke Justice
Luke was asking about scanning at TXE10, He said coordinate with Greg Hueramo, he will be setting up an origination email
I told luke they need to have all areas ready for scanning since the team cant be sent out every other day, reset up, etc
I asked for Control point map, he said get with Greg Hueramo
I explained to him what the scanning was
I told him they will need to add paul hernandex, jeremy miller and adam brown to email
John Cowhey said he has a 1 pager for Site orientation which will be 8 hours
They will be enforcing badging within the next few weeks. No badge no access, Visitor badges will be available but not allowed to work
Luke will put together a schedule for orientation
11/17/26 - is new date for 0 prep according to John Cowhey
Forward FW off email to Luke, original email was sent out 4/17. I resent to Luke Justice
I told him Jeff Balthrop was involved a few weeks back
Send Luke Discrepancy on Anchor locations with BZI Wall panels, NWCs etc from Adam email, Adam email 5/5, TXE Adam email 5/6
Verify anchors at TXE and LEB, check they've been submitted to FTI
Send notice to John Cowhey, luke justice
They asked when Southland is looking at manning the site, jeremy informed them no PM team were available at this time to answer
new schedule coming out Friday
Got with michael kolnik, he sent out Shop Drawing submittal request to Eric Boehger
5/28/2026 - Loop Keylan and Michael into the Anchor clash info and meeting for Friday
Luke says bypass are fabbed, not installed will be installed next week, sent out email to everyone, paul, jeremy, michael
Need to coordinate orientation, drug testing
Day zero schedule? Luke said he was supposed to get last Friday, not seeing anything new
Luke showed the Faith TXE Anchor Shop Drawing submittals, they are only for the TXE10,1,2 Plates don’t know why it has TXE3 on the label
Not showing any Shop drawing embed submittal info
NO PM Management was present, Keylan Rollins was for engineering
6/4/2026 - Luke Cancelled at 741am, Got DAMN MAN!!!!
6/11/2026 - Luke Cancelled at 741am, Got DAMN MAN!!!!
930amLEB | BIM COORDINATION LEB #2
Emma will no longer be on this project
Kaushal Bagdekar with Turner ran the meeting, saying who to contact for what, I asked if he could send an email with that info
They went over underground clashes
5/28/2026 - Tristen with helm verified he is using LEB1 dimensions for LEB 2 elevations and locaitons for FW
930amLEB | BIM COORDINATION LEB #2
Emma will no longer be on this project
Kaushal Bagdekar with Turner ran the meeting, saying who to contact for what, I asked if he could send an email with that info
They went over underground clashes
5/28/2026 - Tristen with helm verified he is using LEB1 dimensions for LEB 2 elevations and locaitons for FW
6/11/2026 - No PM Team
Went Over UG issues, concrete pads
1000 amLEB - BIM Coordination Meeting (Thu) | Meeting-Join | Microsoft Teams
Ryan Zoldan
LEB 6 due finalized next week
I requested a schedule from Ryan, he has the sign off, region schedule, I brought up a pull plan, be he says that will be through Turner
Mortensen is the Base build GC, why aren't they leading a pull plan schedule
John Rhee nor Brent were in this meeting
6/4/2026 - I brought up the LEB10 FW UG Stub ups totally missing the Dims, Ben Kozel was there and he stated they are bringing them back in to dimensions by backfilling a little and moving them, backfilling and moving them
He acknowledge that lance did contact him
1000 amLEB - BIM Coordination Meeting (Thu) | Meeting-Join | Microsoft Teams
Ryan Zoldan
LEB 6 due finalized next week
I requested a schedule from Ryan, he has the sign off, region schedule, I brought up a pull plan, be he says that will be through Turner
Mortensen is the Base build GC, why aren't they leading a pull plan schedule
John Rhee nor Brent were in this meeting
6/4/2026 - I brought up the LEB10 FW UG Stub ups totally missing the Dims, Ben Kozel was there and he stated they are bringing them back in to dimensions by backfilling a little and moving them, backfilling and moving them
He acknowledge that lance did contact him
6/11/2026 - Ben Kozel, said there were no issues that need to be talked about.
Richard lopez asked around the room for any issues regarding LEB10 or any others
TXE1 looks good for the loop area sign off next week
Same with TXE2
6/4/2026 - Own B ran the meeting going over TXE1 and 2
6/11/2026 - Owen B, says TXE10 Loop for sign off
TXE2 Core scheduled for next week
TXE10 AB Datahall and Loop are signed off
TXE3 Alan lopez is running region 2 for signe off
TXE2 Loop and AB South sign off
issue 2602 - Cerris Vent in corner is clashing with Technical water, Rantwiler is saying they don’t have our model, I told them our model has been there for 6 months, the fact that HP is viewing it, means the model is available. If it’s a bridging issue we will help Cerris work it out
Trevor said he will get with rantwiler and get the model bridged, they will offset that vent around our TW Piping
06/05/26 - FRI (+1 Meetings)
730amMW Detailing Weekly Meeting
Marshall Hampton
Bill Clayton did tips and tricks on PDF inserting
5/25/26 - 5/31/26
05/26/26 - TUE (+3 Meetings)
800amWeekly BIM Coordination Meeting - Region 2 (ZOOM)
Alan Lopez, Kyle Cummings (Hensel Phelps) / Ethen Berry
No one started the meeting, I sent an email, they said Alan was PTO and they started meeting late
They went over Region 2 underground, sign off later this week
5/26/26 - Allen Lopez Went over Region 2 again, said they were going to do a main signoff then a branch signoff. Covered a lot of UG clashes
830amLEB - BIM Coordination Meeting (Tue) | Meeting-Join | Microsoft Teams
Ryan Zoldan, Mortenson (GC1)
Missed for the 8am meeting
1000amLightning-Eng-Coord Huddle | Meeting-Join | Microsoft Teams
Tia/ Tom
Follow up on HAC Panel clashes with Patrick Brinnehal
Meeting to go over stratus and models with all PMs, Adam, Scott, Supers sometime next week, look at schedules
Chris Chase is the PM of EMT
5/26/2026
Verify what spools have been put on stratus for TIA/TOM Lightning huddle
Need meeting to discuss, txe10 anchor clashing with interior of walls, adam sent info out about conflicting models, but as of today, there is still clashes
05/27/26 - WED (+6 Meetings)
730-800amAdam Lightning Ketchup
Updated one note to show tasks
800amTXE/LEB Weekly Internal BIM Coordination | Meeting-Join | Microsoft Teams
Jay Keiser - FTI
LEB10 RO Hitting Column
LEB10 FLEX HOSE on 8" Flush skid hitting column, need to clear clashes
talked about email I sent about a list of which models to use for which trades as far as Walls, Wall Panels, Electrical, Arch, Structural etc
Kyle said he was still working on that
John Cowhey is asking about Lugs on the MES
I will chase this down, find who responded Johns email and start there
Robert Cheek responded on Monday saying he would get the answer same day, still waiting
I told Jay we are currently working through shop drawings and spools, while we are doing those we are paying attention to clashes and working through the clashes
I Brought up the FW underground being off and that we will be scanning and verifying CIA POC's, Should be doing this within a week
5/27/2026 - I BROUGHT UP LEB1 COORDINATING WITH CRIDER NO MODEL, USING HDR FOR UNDERGROUND COORDINATION
JAY BROUGHT UP TXE10 ANCHOR CLASH WITH WALL, ADAM SENT EMAIL ASKING ABOUT IT, SOMEONE SAID THEY WERE CHANGING WALL IN A EMAIL RESPONSE, ADAM REQUESTED MEETING, NO ONE RESPONDED
JAY ADDED THIS AS AN ACTION ITEM
EMMA SENT EMAIL REQUESTING CLARIFICATION, TRISTEN WAS CONFUSED
LUKE SAID HE WILL DISCUSS IN HIS MEETING WITH MORTENSON
JAY ADDED THIS AS AN ACTION ITEM
800amTXE/LEB Weekly Internal BIM Coordination | Meeting-Join | Microsoft Teams
Jay Keiser - FTI
LEB10 RO Hitting Column
LEB10 FLEX HOSE on 8" Flush skid hitting column, need to clear clashes
talked about email I sent about a list of which models to use for which trades as far as Walls, Wall Panels, Electrical, Arch, Structural etc
Kyle said he was still working on that
John Cowhey is asking about Lugs on the MES
I will chase this down, find who responded Johns email and start there
Robert Cheek responded on Monday saying he would get the answer same day, still waiting
I told Jay we are currently working through shop drawings and spools, while we are doing those we are paying attention to clashes and working through the clashes
I Brought up the FW underground being off and that we will be scanning and verifying CIA POC's, Should be doing this within a week
5/27/2026 - I BROUGHT UP LEB1 COORDINATING WITH CRIDER NO MODEL, USING HDR FOR UNDERGROUND COORDINATION
JAY BROUGHT UP TXE10 ANCHOR CLASH WITH WALL, ADAM SENT EMAIL ASKING ABOUT IT, SOMEONE SAID THEY WERE CHANGING WALL IN A EMAIL RESPONSE, ADAM REQUESTED MEETING, NO ONE RESPONDED
JAY ADDED THIS AS AN ACTION ITEM
EMMA SENT EMAIL REQUESTING CLARIFICATION, TRISTEN WAS CONFUSED
LUKE SAID HE WILL DISCUSS IN HIS MEETING WITH MORTENSON
JAY ADDED THIS AS AN ACTION ITEM
6/3/2026 - New LEB Mech and Plumbing meeting on Wed, John and Reece involved, going over FW stub up locations and F/F water gallery connections
Informed John of Convos with Greg to coordinate wall install with coring of anchor plate holes
Told Jay/John, Lance Holmes is coordinating with other trades on fix for LEB UG FW stubups not hitting POC points or dimensions
900amSouthland Management Mid year Check In
Was AI Recorded, watch the notes
1000amBIM Round Up | Meeting-Join | Microsoft Teams
Michael Kolnik
Jeremy says they are supposed to be scanning in a week or 2
Jeremy needs Floor drain locations from Cerris so they know exactly where they land, Need to get with Patrick Marshall at Cerris and see if we can get some shop drawings.
1000amBIM Round Up | Meeting-Join | Microsoft Teams
Michael Kolnik
Jeremy says they are supposed to be scanning in a week or 2
Jeremy needs Floor drain locations from Cerris so they know exactly where they land, Need to get with Patrick Marshall at Cerris and see if we can get some shop drawings.
6/3/2026 - MICHAEL ASKED ABOUT CURTIS GIVING HIM AN ORDER REQUEST THAT HE THOUGHT WAS SUPPOSED TO BE FOR FLUSH SKIDS
IT HAD 16X14 TEES, 14" 90S, 8" STAINLESS CAPS
HE DIDN’T KNOW WHERE THESE TEES CAME FROM
I TOLD HIM THEY WERE FOR THE MES LOOPS, NOT THE SKIDS
THE 14" 90S WERE PROBABLY FOR THE FLUSH SPOOL TO CONNECT TO THE FLEX SKID
MICHAEL SAID HE CANT GET THEM IN TIME, SIAD HE IS LOOKING AT DOING A MATERIAL SUBSTITUTE REQUEST, I SAID IT ASAP AND PUT CURTIS IN THE LOOP ON IT
05/28/26 - THU (+5 Meetings)
630-710amLEB | BIM | Faith x Turner
Luke Jost - Joe Dorinsville
Edwin Perez from Turner hosted
5/14/26 - - Joe Brought up the access panels for Flush system, asked about rating, I would have to check submittals to verify. Me and Lance holmes informed joe the flush systems are temporary, once done, they get removed and the access panel stay
Anna said they were aware, but not the finalized locations, now they will be going through Valley for engineering, excel engineering to make sure everything is accounted for, engineered
Talked to Stefan, we are not providing the Access Panel, its GC2 wall, they are providing it
I need to check on RO system, ACCess panel and it looks like location may be borked
Scott asked about sign offs for lighting scope to base build duct connections, Joe said they havent covered it, sign off is around end of June. They will be circling back to loop area not that they have certain paperwork available
Joe said any issue can be brought up at anytime
5/21/265 - No John Rhee, Brent, Thomas Holler, NO PM TEAM
They went over stud wall model, Lance asking about raceways for security and bus ducts
5/28/2026 - They went over electrical stuff, skid placement, wall leave outs
Turner wants a meeting with Helm and Southland to go over Wall penetrations
Joe D discussed Span model naming, keeping them the same and consistant.
Will need to relink LEB Span models since they have new models with Nucor suffix
900amTXE-FTI Weekly Sync Meeting
Luke Justice
Luke was asking about scanning at TXE10, He said coordinate with Greg Hueramo, he will be setting up an origination email
I told luke they need to have all areas ready for scanning since the team cant be sent out every other day, reset up, etc
I asked for Control point map, he said get with Greg Hueramo
I explained to him what the scanning was
I told him they will need to add paul hernandex, jeremy miller and adam brown to email
John Cowhey said he has a 1 pager for Site orientation which will be 8 hours
They will be enforcing badging within the next few weeks. No badge no access, Visitor badges will be available but not allowed to work
Luke will put together a schedule for orientation
11/17/26 - is new date for 0 prep according to John Cowhey
Forward FW off email to Luke, original email was sent out 4/17. I resent to Luke Justice
I told him Jeff Balthrop was involved a few weeks back
Send Luke Discrepancy on Anchor locations with BZI Wall panels, NWCs etc from Adam email, Adam email 5/5, TXE Adam email 5/6
Verify anchors at TXE and LEB, check they've been submitted to FTI
Send notice to John Cowhey, luke justice
They asked when Southland is looking at manning the site, jeremy informed them no PM team were available at this time to answer
new schedule coming out Friday
Got with michael kolnik, he sent out Shop Drawing submittal request to Eric Boehger
5/28/2026 - Loop Keylan and Michael into the Anchor clash info and meeting for Friday
Luke says bypass are fabbed, not installed will be installed next week, sent out email to everyone, paul, jeremy, michael
Need to coordinate orientation, drug testing
Day zero schedule? Luke said he was supposed to get last Friday, not seeing anything new
Luke showed the Faith TXE Anchor Shop Drawing submittals, they are only for the TXE10,1,2 Plates don’t know why it has TXE3 on the label
Not showing any Shop drawing embed submittal info
NO PM Management was present, Keylan Rollins was for engineering
930amLEB | BIM COORDINATION LEB #2
Emma will no longer be on this project
Kaushal Bagdekar with Turner ran the meeting, saying who to contact for what, I asked if he could send an email with that info
They went over underground clashes
5/28/2026 - Tristen with helm verified he is using LEB1 dimensions for LEB 2 elevations and locaitons for FW
1000 amLEB - BIM Coordination Meeting (Thu) | Meeting-Join | Microsoft Teams
Ryan Zoldan
LEB 6 due finalized next week
I requested a schedule from Ryan, he has the sign off, region schedule, I brought up a pull plan, be he says that will be through Turner
Mortensen is the Base build GC, why aren't they leading a pull plan schedule
TXE1 looks good for the loop area sign off next week
Same with TXE2
05/29/26 - FRI (+2 Meetings)
730amMW Detailing Weekly Meeting
Marshall Hamptom
Marshall talked about having a spooling team headed by Daniel De Le Cruz with others working under him
To keep piping detailers working on coordination and modeling
5/29/2026 - Align 14, if we get, will start in june
Utah, QTS should get next one
Carusoe project, Maracopa should be getting
Adam Tips and Tricks, PyRevit
using pyrevit to copy filters from iso view to section view. Jamie and Bill pointed out you can also just use a template now
1000am(EXT) TXE10 ANCHOR CLASH COORDINATION
John Cowhey (FTI)
Adam brought up at least coring the holes before the walls go in
5/18/26 - 5/24/26
05/18/26 - MON (+2 Meetings)
900amLightning TXE Staff Meeting | Meeting-Join | Microsoft Teams
Jacob Gelhousen
Will do scans after Cerris installs bypasses
1000amMeeting with Adam, Cory, Angel, Dan
05/19/26 - TUE (+3 Meetings)
800amWeekly BIM Coordination Meeting - Region 2 (ZOOM)
Alan Lopez, Kyle Cummings (Hensel Phelps) / Ethen Berry
No one started the meeting, I sent an email, they said Alan was PTO and they started meeting late
They went over Region 2 underground, sign off later this week
830amLEB - BIM Coordination Meeting (Tue) | Meeting-Join | Microsoft Teams
Ryan Zoldan, Mortenson (GC1)
Missed for the 8am meeting
1000amLightning-Eng-Coord Huddle | Meeting-Join | Microsoft Teams
Tia/ Tom
Follow up on HAC Panel clashes with Patrick Brinnehal
Meeting to go over stratus and models with all PMs, Adam, Scott, Supers sometime next week, look at schedules
05/20/26 - WED (+2 Meetings)
800amTXE/LEB Weekly Internal BIM Coordination | Meeting-Join | Microsoft Teams
Jay Keiser - FTI
LEB10 RO Hitting Column
LEB10 FLEX HOSE on 8" Flush skid hitting column, need to clear clashes
talked about email I sent about a list of which models to use for which trades as far as Walls, Wall Panels, Electrical, Arch, Structural etc
Kyle said he was still working on that
John Cowhey is asking about Lugs on the MES
I will chase this down, find who responded Johns email and start there
Robert Cheek responded on Monday saying he would get the answer same day, still waiting
I told Jay we are currently working through shop drawings and spools, while we are doing those we are paying attention to clashes and working through the clashes
I Brought up the FW underground being off and that we will be scanning and verifying CIA POC's, Should be doing this within a week
1000amBIM Round Up | Meeting-Join | Microsoft Teams
Michael Kolnik
Jeremy says they are supposed to be scanning in a week or 2
Jeremy needs Floor drain locations from Cerris so they know exactly where they land, Need to get with Patrick Marshall at Cerris and see if we can get some shop drawings.
05/21/26 - THU (+5 Meetings)
630-710amLEB | BIM | Faith x Turner
Luke Jost - Joe Dorinsville
5/14/26 -
Anna said they were aware, but not the finalized locations, now they will be going through Valley for engineering, excel engineering to make sure everything is accounted for, engineered
Talked to Stefan, we are not providing the Access Panel, its GC2 wall, they are providing it
I need to check on RO system, ACCess panel and it looks like location may be borked
Scott asked about sign offs for lighting scope to base build duct connections, Joe said they havent covered it, sign off is around end of June. They will be circling back to loop area not that they have certain paperwork available
Joe said any issue can be brought up at anytime
5/21/265 - No John Rhee, Brent, Thomas Holler, NO PM TEAM
They went over stud wall model, Lance asking about raceways for security and bus ducts
900amTXE-FTI Weekly Sync Meeting
Luke Justice
Luke was asking about scanning at TXE10, He said coordinate with Greg Hueramo, he will be setting up an origination email
I told luke they need to have all areas ready for scanning since the team cant be sent out every other day, reset up, etc
I asked for Control point map, he said get with Greg Hueramo
I explained to him what the scanning was
I told him they will need to add paul hernandex, jeremy miller and adam brown to email
John Cowhey said he has a 1 pager for Site orientation which will be 8 hours
They will be enforcing badging within the next few weeks. No badge no access, Visitor badges will be available but not allowed to work
Luke will put together a schedule for orientation
11/17/26 - is new date for 0 prep according to John Cowhey
Forward FW off email to Luke, original email was sent out 4/17. I resent to Luke Justice
I told him Jeff Balthrop was involved a few weeks back
Send Luke Discrepancy on Anchor locations with BZI Wall panels, NWCs etc from Adam email, Adam email 5/5, TXE Adam email 5/6
Verify anchors at TXE and LEB, check they've been submitted to FTI
Send notice to John Cowhey, luke justice
They asked when Southland is looking at manning the site, jeremy informed them no PM team were available at this time to answer
new schedule coming out Friday
930amLEB | BIM COORDINATION LEB #2
Emma will no longer be on this project
Kaushal Bagdekar with Turner ran the meeting, saying who to contact for what, I asked if he could send an email with that info
They went over underground clashes
1000 amLEB - BIM Coordination Meeting (Thu) | Meeting-Join | Microsoft Teams
Ryan Zoldan
LEB 6 due finalized next week
I requested a schedule from Ryan, he has the sign off, region schedule, I brought up a pull plan, be he says that will be through Turner
Mortensen is the Base build GC, why aren't they leading a pull plan schedule
900amLightning TXE Staff Meeting | Meeting-Join | Microsoft Teams
Jacob Gelhousen
Noel Brought up protecting electrical equipment durring fill and flush
FTI is asking who is protecting it, does it need it?
Zach said it seems the MES are still in walls
Michael said its 1-10, from center of pipe to edge of anchor but theyre saying its 1-8
Asked Adam to get him dims
Zach says once they get the piping in scan it
05/12/26 - TUE (+3 Meetings)
800amWeekly BIM Coordination Meeting - Region 2 (ZOOM)
Kyle Cummings (Hensel Phelps) / Ethen Berry
This week clashes til may 18th, bldg 3 and 5 and MCUP for underground, region 2
Checking Faiths ACC for TXE, cant find any schedules for anything
830amLEB - BIM Coordination Meeting (Tue) | Meeting-Join | Microsoft Teams
Ryan Zoldan, Mortenson (GC1)
1000amLightning-Eng-Coord Huddle | Meeting-Join | Microsoft Teams
Tia/ Tom
Follow up on HAC Panel clashes with Patrick Brinnehal
05/15/26 - FRI (+1 Meetings)
730amMW Detailing Weekly Meeting
Marshall Hamptom
5/4/26 - 5/10/26
05/04/26 - MON (+1 Meetings)
900amLightning TXE Staff Meeting | Meeting-Join | Microsoft Teams
Jacob Gelhousen
Adam says we got a new guy coming on Wed to start on Eng Review drawings with Corey
Probably would've been nice to know
Adam redrew the HAC FW Bypass, waiting for field to look at it and see if it will work
05/05/26 - TUE (+3 Meetings)
800amWeekly BIM Coordination Meeting - Region 2 (ZOOM)
Kyle Cummings/ Ethen Berry
830amLEB - BIM Coordination Meeting (Tue) | Meeting-Join | Microsoft Teams
Ryan Zoldan, Mortenson (GC1)
1000amLightning-Eng-Coord Huddle | Meeting-Join | Microsoft Teams
Tia/ Tom
Follow up on HAC Panel clashes with Patrick Brinnehal
05/06/26 - WED (+6 Meetings)
700amPlaceholder - TXE Site Specific Submittals Kicko
Luis Saldana
700amLightning Check In
Health
Heath was looking for delivable dates for creating Hanger, Engineer Review, etc sheets and when other models/projects need created
I brought up the dirty files/ models
Clean unused materials and poo (purge) - over 25k Roof materials that bloat the model file
Clean out non MP Filters and templates for MP models.
Fix linked model errors. When Opening models, get link errors.
I brought up the 2.5 hours to export Navis/ FTI NWCs, heath said he would look at it
800amTXE/LEB Weekly Internal BIM Coordination | Meeting-Join | Microsoft Teams
Luis Saldana
LEB10 RO Hitting Column
LEB10 FLEX HOSE on 8" Flush skid hitting column, need to clear clashes
800amTXE/LEB Weekly Internal BIM Coordination | Meeting-Join | Microsoft Teams
Jay Keiser - FTI
LEB10 RO Hitting Column
LEB10 FLEX HOSE on 8" Flush skid hitting column, need to clear clashes
1000amBIM Round Up | Meeting-Join | Microsoft Teams
Michael Kolnik
1000amBIM Round Up | Meeting-Join | Microsoft Teams
Michael Kolnik
05/07/26 - THU (+11 Meetings)
1200amSouthland All Hands On Meeting
600amLEB | BIM Working Session | Meeting-Join | Microsoft Teams
Joe Dorinsville, Turner
Get Diogo and Luke an updated MES Anchor Embed package with RFA, Shop Drawing and Submittal
Adam took this one
630-710amLEB | BIM | Faith x Turner
Luke Jost - Joe Dorinsville
Lance Holding asked about Embeds, Luke state he would give the submittals to them
They talked with Patrick Brinnehal about HAC Frames and walls and cooridors
Luke Long asked about where to penetrate the Ancillary skid
5/14/265 - No John Rhee, Brent, Thomas Holler, NO PM TEAM
They went over underground, control joints, truck turning radius
Joe Brought up the access panels for Flush system, asked about rating, I would have to check submittals to verify. Me and Lance holmes informed joe the flush systems are temporary, once done, they get removed and the access panel stay
Anna said they were aware, but not the finalized locations, now they will be going through Valley for engineering, excel engineering to make sure everything is accounted for, engineered
I need to check on RO system
Scott asked about sign offs for lighting scope to base build duct connections, Joe said they havent covered it, sign off is around end of June. They will be circling back to loop area not that they have certain paperwork available
Joe said any issue
630-710amLEB | BIM | Faith x Turner
Luke Jost - Joe Dorinsville
5/14/265 - No John Rhee, Brent, Thomas Holler, NO PM TEAM
They went over underground, control joints, truck turning radius
Joe Brought up the access panels for Flush system, asked about rating, I would have to check submittals to verify. Me and Lance holmes informed joe the flush systems are temporary, once done, they get removed and the access panel stay
Anna said they were aware, but not the finalized locations, now they will be going through Valley for engineering, excel engineering to make sure everything is accounted for, engineered
Talked to Stefan, we are not providing the Access Panel, its GC2 wall, they are providing it
I need to check on RO system, ACCess panel and it looks like location may be borked
Scott asked about sign offs for lighting scope to base build duct connections, Joe said they havent covered it, sign off is around end of June. They will be circling back to loop area not that they have certain paperwork available
Joe said any issue can be brought up at anytime
900amTXE-FTI Weekly Sync Meeting
Luke Justice
Luke asked about submittals for Embed shop drawings
Michael said he submitted to IKE with HP, Ike said he don’t want them
Michael said he would send to Luke Justice
Zach brought up the FW stub ups being off, Luke made a note, Luis told him he was in the email chain, Luke said he would follow up
Luke asked about embed shop drawings, Michael said they are pouring txe3 on may 1st, embeds were requested by duane or dante on 4/15
Michael said he submitted them, I looked didn't see any submitted shop drawings
Adam said he would send them, I brought up it should be PMs sending this to our GC (FTI) and they should be sharing that info, but who the fuck knows
He just did another TXE3 embed anchor drawing and sent it out by email. I already had 1 done, SKMP.002 that was sent out by transmittal on 4/15, but no one ever looked at it, never got submitted, now we are doing double work
And we have multiple drawings for the same thing
Michael will walk site tomorrow with Luke Justice, Louis to look at FW Stubups, around 1 pm
All SI Drug test and Safety needs coordinated with FTI
Michael said he sent out Shop Drawings for anchors to multiple people
900amTXE-FTI Weekly Sync Meeting
Luke Justice
CANCELLED
1000 amLEB - BIM Coordination Meeting (Thu) | Meeting-Join | Microsoft Teams
Ryan Zoldan
LEB 6 due finalized next week
I requested a schedule from Ryan, he has the sign off, region schedule, I brought up a pull plan, be he says that will be through Turner
Mortensen is the Base build GC, why aren't they leading a pull plan schedule
John Rhee nor Brent were in this meeting
1000amSouthland CEO Meeting
1000 amLEB - BIM Coordination Meeting (Thu) | Meeting-Join | Microsoft Teams
Ryan Zoldan
LEB 6 due finalized next week
I requested a schedule from Ryan, he has the sign off, region schedule, I brought up a pull plan, be he says that will be through Turner
Mortensen is the Base build GC, why aren't they leading a pull plan schedule
900amLightning TXE Staff Meeting | Meeting-Join | Microsoft Teams
Jacob/ Michael
04/28/26 - TUE (+4 Meetings)
800amWeekly BIM Coordination Meeting - Region 2 (ZOOM)
Kyle Cummings/ Ethen Beery -- went over UG sign off interior building Region 2
830amLEB - BIM Coordination Meeting (Tue) | Meeting-Join | Microsoft Teams
900amJeremy/Paul Flush Meeting
Adam Brown
Change 3" MES Loop drains to 2"
Paul says we need both supports
Get adam 1A1-ML1 spool package
Jeremy wants an extra valve spool with rolling cart with the big flush fill cart
Need to revise hose hanger rack off mes, stud it all the way down, for 2" hose
Redo eol bypass for hac with pauls markups so it shortens the dead leg length
Cory is creating the MES Anchor Spool
Create a bypass for middle MES Loops from return to supply for flushing so we flush dead leg of end of lines
Copy West or East end MES Loop to middle for support
Verify couplings on MES Skid, Right side has valves, left side is empty.
Adam put bypass hac drawing in his chat
1000amLightning Eng Huddle
Tia/ Tom
Copy models into TXE 8,9,11,12
LEB Models 3,5,11,12
04/29/26 - WED (+2 Meetings)
800amTXE/LEB Weekly Internal BIM Coordination | Meeting-Join | Microsoft Teams
Luis Saldana
1000amBIM Round Up | Meeting-Join | Microsoft Teams
Michael Kolnik
04/30/26 - THU (+4 Meetings)
600amLEB Working Sesssion
Joe Dorinsville, Turner
Get Diogo and Luke an updated MES Anchor Embed package with RFA, Shop Drawing and Submittal
Adam took this one
900amTXE-FTI Weekly Sync Meeting
Luke asked about submittals for Embed shop drawings
Michael said he submitted to IKE with HP, Ike said he don’t want them
Michael said he would send to Luke Justice
Zach brought up the FW stub ups being off, Luke made a note, Luis told him he was in the email chain, Luke said he would follow up
Luke asked about embed shop drawings, Michael said they are pouring txe3 on may 1st, embeds were requested by duane or dante on 4/15
Michael said he submitted them, I looked didn't see any submitted shop drawings
Adam said he would send them, I brought up it should be PMs sending this to our GC (FTI) and they should be sharing that info, but who the fuck knows
He just did another TXE3 embed anchor drawing and sent it out by email. I already had 1 done, SKMP.002 that was sent out by transmittal on 4/15, but no one ever looked at it, never got submitted, now we are doing double work
And we have multiple drawings for the same thing
1000 amLEB - BIM COORDINATION
Ryan Zoldan
LEB 6 due finalized next week
I requested a schedule from Ryan, he has the sign off, region schedule, I brought up a pull plan, be he says that will be through Turner
Mortensen is the Base build GC, why aren't they leading a pull plan schedule
Sergio Guiterriez brought up the Gantry Crane box placement clashing with Electrical, the view showed it also clashing with 14" Flush skid, Luis Saldana said it shouldn' t interfere and Cranes stay until hacs are 100% placed
1100amFTI/Munters +Trane HAC Weekly Sync | Meeting-Join | ZOOM
04/17/26 - FRI (+2 Meetings)
730amMW Detailing Meeting
Marshal Hampton
Daniel De La Cruz did a tips on Spool sheets
730amTXE-FTI Weekly Sync Meeting
Luke Justice
John Cowley brough tup the FW Stub ups being off
Jeff Belthrop said he needs us to tell him what can we do to fix it
John Cowly was at TXE Meeting with Anchor clash confirming points of anchors and coordinate getting in early to set anchors
Meeting early next week to cofirm schedule
Asked to get included in meeting, I told them the issue was coordinating the setting of the anchor with interior walls and other elements
Jeff B says everyone is working 2 shifts, get ready, they will be doing interior fit out in 3 weeks
Luis Saldana says we still need a schedule
Chris Wilson is supposed to distribute
Luis Saldana says we need the concrete schedule
Jeff B says theyre finalizing IMP, will get to Russell Faulkner, told luke to get them schedule that was distributed last week
Jeff B says October 13th for first hand over, coming from Meta
Meetings getting setup for May 4th and FTI April 27th in Texas
Jeff B is in same trailer that Luke is in
Luis S says they are not getting updated concreate schedule
Showed the outdated SOG schedule
Jeff B says there are updated maps for it
Luke says they are being asked to make commisioning faster
Jeff B task is how to speed up commissioning
Blending of efforts
Everyone has warehouses in town
Iconix will be working 2 shifts, per Jeff B
Jeff B says everyone is working 2 shifts and weekends
Asked if anyone has done Optimus Commissioning with Meta, no one has doen it, including Jeff B
If they want it as fast as they say, we need to come up with plans to help the process
He will be glad to push any plans to Meta, needs smart guys to tell him the smart plan to push
John Cowhey expressed they are trying to do as much off site as possible
4/6/26 - 4/12/26
04/06/26 - MON (+1 Meetings)
900amLightning TXE Staff Meeting
Zach Washburn
04/07/26 - TUE (+3 Meetings)
800amBIM Coordination Region 2, TXE3
Alan Lopez, BIM Coordinatoro for Region 2, Hensel Phelps
Covered all underground clashes issues on TXE2
830amLEB | BIM Coordination
Ryan Zoldan
Missed due to 8am
1000amLightning-Eng-Coord-Huddle
Tia Giovanni
TWMU Skid Anchors,
Tom says they are looking at shifting walls on future buildings
Brent says it would be better to do a 1 off for LEB1 on top of diamond
Tom says they are already building frames or have frames built
Look at leave out 1 anchor for those that are within 2-1/2" of joint
Zach and Brent said ignore LEB1, let field deal with it
04/08/26 - WED (+3 Meetings)
7AMHDR - FTI Model Coordination
David Eldridge
Ken Raxon
Adam told them use Design model, if it doesn’t match up we will let our Eng team know
Verified that Tom changed SI-LTG to SI-M, caused a slew of shit, HDR is confused
8amTXE/LEB Weekly Internal BIM Coordination | Meeting-Join | Microsoft Teams
Luis Saldana FTI
Adam brought up UG Cerrris FW off, said he is waiting to see what Cerris is going to do, Luke and Luis agrees
New meeting 9am Thursday with Hensel Phelps to go over MOFE coorination
TWMU skid clash with FW Stub ups at TXE
Asked Patrick about resolution with MES and HAC Clash, he said they changed base plate for mes still waiting for anchor clash to be cleared
Adam has meeting with engineering today, should be able to notch base plate
Adam asked if Patrick was able to move the panels on hac that were clashing with couplings
Patrick said he did flip panels to clear clash
Patrick said he is repopulating with updated fan coils
TXE10 Duct is locked down according to Luis
Adam brought up making sure embeds are handed off to concrete guys for install on underground
He will submit new drawings for it
1000amBim Round Up
Michael Kolnick
04/09/26 - THU (+4 Meetings)
600amLEB|BIM Working Session
Joe Dorinsville
Emma Pezza
Dogic Dzenan Brought up Leb10 Span-ss structural grid lines don’t match datum file
Jared says the dataum is updated to correct datum file, but not showing, weird
Ronald Shaw brought up Interior Framing doesn't match Arch Desing model
Joe D says to keep using Arch design model
800amHAC MSA Submittal Coordination
Adam Brown
Do 2" Copper HAC Bypass
Brent wants to do EOL 16" MES Connection loop meeting
900amTXE-FTI Weekly Sync Meeting
Hensel Phelps
Luke Justice with Hensel Phelps (Office Engineer) ran the meeting
Luke will be having separate Cx meetings, Luis will be looped in
Kyle Cummins said meta asked them to accelerate the schedule by 15 weeks
3/30/26 - 4/5/26
03/30/26 - MON (+1 Meetings)
9amLIGHTNING TXE STAFF MEETING
Zach Washburn
Jacob Gelhousen
May-June boots on the ground
Actual onsite personall Field install, september
80 person manpower at TXE including support
Zach and Paul said no reason to flush MES on FOK2, don’t gain or learn anything
Need to add Pancakes for valves to itm database so they report on boms
03/31/26 - TUE (+3 Meetings)
800amBIM Coordination Region 2, TXE3
Alan Lopez, BIM Coordinatoro for Region 2, Hensel Phelps
Covered all underground clashes issues on TXE2
830amLEB | BIM Coordination
Ryan Zoldan
Covered design and clash issues with Region 1,2,3 and started talking about 4
Gave Region map, schedules
1000amLightning-Eng-Coord-Huddle
Thomas Chirdon
Drop link for contact list from one note
Get with patrick thur about panel clashing with couplings
Ask about floor sink RFI, Anchor RFI. Did notify them about these and let them know they need to RFI this info
Me and Michael had a phone convo afterwards. Told him, not sure if an anchor being that close to the joint would be a situation or not, that’s for an engineer to decide
Michael said originally they were going to dump into floor drains in middle of aisle, then pump out and truck out. John is the one who gave the floor sink markup, not sure why
04/01/26 - WED (+2 Meetings)
800amTXE/LEB Weekly Internal BIM Coordination
Jay Keiser, FTI
Luis Saldana, FTI
Frquency model updates?
1000amBIM Round Up
Jake G
Michael K
Missed BIM round up due to Tom pulling me into MES Coupling and pipe gapping for expansion and contraction
I informed everyone we all signed off on NWB and LEB1,2
930amTXE/LEB Southland Mech
Josh Pirkl, Stantec
4 mins late, no one was there
1000amLighting Engineering Coordination
Tom Chirdon
Adam said he will email patrick about moving hac panels off vic ouplings
Adam said box area is clear to move valves and PTs according to Paul and Jeremy at FOK
RFI anchoring to column diamonds for TWMU Skids and MES Skids
Need to verify no FS for drains
Only thing I see is round floor drains in middle of aisle, emergency drains
LEBNWB, no floor sinks anywhere near our scope on Helm and HDR files
03/25/26 - WED (+2 Meetings)
800amTXE/LEB Weekly Internal BIM Coordination
Jay Keiser, FTI
Luis Saldana, FTI
Jay went over BIM Coordination plan
Job setup and overviews for TXE and LEB with placeholders for MML and OKT (Diff contractors?)
Scott had a melt down about Rvt linked files and nwcs out of date or tooooo many files
NWCs need exported before Saturday so they get bridged auto
Stop clashing between same trade, our couplings clash with our pipes
Due to scott taking over the whole fucking meeting, I had to post my questions in chat
1000amBIM Round Up
Jake G
Michael K
Installed FOK MES to MSA Risers, got 1 in 10 minutes, they needed to hit 1 per hour, 4 a day
Michael asked about PTs
Brent issued a RFI for using a 250s, first 150 FDs will be copper
Adam is changing EOL Loops to stainless
Adam is doing a hac flythrough meeting Friday, 7am
Thomas
Not flushing 2-1/2" stainless
Need boot leg 16" loop and 8" stainless loop for FOK or near site flush, add drain ports on each
03/27/26 - FRI (+1 Meetings)
700amTW Header Meeting
Adam Brown
Flythrough model
3/16/26 - 3/22/26
03/16/26 - MON (+1 Meetings)
900amLightning TXE Staff Meeting
Jake Galhouseen
John Rhee
Ask John who the Super is Brian Oneill? Tommy Howler
Verify MEP/TWMU Piping spools at end of April?
Adam needs to Finalize JUMPERs CIA and submit to FTI
Adam will bring Occulus and work with VDC to get it fired up in Phoenix
Adam will have the Navis up for the next Bim meeting to look at manifold with Paul, Tom, Jeremy
03/17/26 - TUE (+3 Meetings)
830amLEB|BIM Coordnation
Ryan Zoldan
Area 3, 16th is sign off, more likely end of this week
Schedule is showing modeling for area 5, bldg 6 and 7
930amTXE/LEB Southland Mech
Josh Pirkl, Stantec
Missed meeting, didn't get a popup?
1000amLighting Engineering Coordination
Tom Chirdo
Ryan says he needs spools by end of week, have to have them completed by 6th
Add note not to use Vic Grease with Silica, only use undiluted proplyene glycol or dish soap
Tom says we cant use the standard vic grease on technical system
I told tom I moved what I could, there were still some that still landed on joints. We will pull dims off grids once we do shop drawings
John Rhee says he will work with schedule for getting anchors installed before walls
Tom says Meta released Fan Coil submittals for production
03/18/26 - WED (+2 Meetings)
800amTXE/LEB Weekly Internal BIM Coordination
Luis Saldana Faith
Cancelled
1000amBIM Round Up
Michael Kolnick
03/19/26 - THU (+3 Meetings)
605amLEB|BIM Working Session
Emma Peza, Joe Dorinsville
There will be a breakout meeting with MEP Turner manager to go over embed bolts conflicting with underground conduit, MES and HAC embeds.
No update on Span structural steel Span is waiting for updates from 3rd party
Dzenan Dogic is asking from helm about duct hitting seams in panel, need steel update
Scott brough up Span model using overlay for link, Jared Brant with Span Construction said he will fix, the new file will Be LEB-10_Span_EM.rvt file
1000amLEB _ BIM Coordination
Ryan Zoldan
Building 3 will sign off early next week
Talked to Ryan and Dustin with Crider, said HDR is lined up for LEB1 and2, Ryan says they think its HDR Underground that is misaligned, we all agreed to follow my PDF for dimensions for Stub Ups, will sign off on Fridays meeting
1100amMUNTERS
Jim Marsh
Patrick shows dim discrepency, saying we are dead in water until the model matches the PDF, PDF is 1/23/26 and the Model is from 3/9, review is to conclude on 3/17
Kato Kasuko says supposed to finish review on 3/24, patrick asked if they can verify that, that’s not the date they have
03/20/26 - FRI (+1 Meetings)
700amLEBNWB FW UG POC Meeting
Krunal HDR
I signed off on LEB1 and LEB2 FW UG POCs per the Proposed Dim drawing, HDRs models are within 1/16" of ours, helm hit our elevations except the 5'-9 7/9" and said they were close. I showed them off 1/4" in the model, comparing their old elevations and how much they need to move to low flange and high flange
Krunal and Ryan acknowledged sign off and agreed
Ryan says Crider will use dimension drawing for points. HDR UG model is still off a little
3/9/26 - 3/15/26
03/09/26 - MON (+1 Meetings)
900amTXE Lightning Staff Meeting
Micahel Kolnick
model 78 is updated in the model per Adam
Stainless TW Header design, Adam said he will start on web/thu
As built and or shop drawings for EOR approval
03/10/26 - TUE (+3 Meetings)
830amLEB - BIM Coordination
Ryan Zoldan
Sign off for Area 2 this week
Lots of Revizto issues that need clearing
Richard needs the FW Verification that HDR is on dimensions
Send it to Ryan, Hector, Krunal, Richard lopez, Dustin, Matt, Triston
930amTXE/LEB/Southland Mech
Josh Pirkl at Stantec
CIA - TXE base build was submitted, Adam will be getting above ground this week
CIA - LEB need to clean up submit this week
Duct insulation
FWM - Expansion Tank Header, and if it needs to be flushed
TXE10
1000amLightning ENG-Corod
Tom Chirdon
Verify that panel is getting moved to avoid clash
Zach says hole needed to be made larger for per Paul at FOK, FTI was notified, just need to verify
CIA - TXE10,1,2 Base build submitted in FTI Court, Adam doing above ground this week
CIA - LEB10,1,2 Hasn’t been submitted, Adam cleaning up this week
Models for TXE 6,7,8,9 and LEB 3,5,6,7 Adam says by next Wednesday
CIA for LEB 3,5,6,7 and TXE 6,7,8,9 will be a week from 3/18 perliminary since adam wasn’t here (in pheonix), I said so
I will look at TXE IFC for Floor sinks
John said turner didn’t show for meeting to go over this for LEB
Bring up vicinity of TWMU skid to Column and Diamon Joint cut at Column, along with vicinity to Wall they wont move at TXE
Adam says we will do a dim sheet for critical MES and MSA
Ron Heath made statement about duplicating spools, getting with adam as for the ask
Scoot the Make up water skid to within 1-2" off face of wall to get the feet out of the Column diamond joint cut
Check out embed proximity to fire rated wall on mid section
Zach said he will chase down coordination meeting with HP for TXE
03/11/26 - WED (+3 Meetings)
800amTXE/LEB Weekly Internal BIM Coordination
Luis Saldana
HP is now asking for 1-2" per Alec Herpel, they say 1/8" is not realistic
Me and adam both said no can do and will get the PM involved
Adam responded to an email going over the subject
Scott went through workflow of creating NWCs for Coordination and clash resolving
Stephen Primethal said he will create whatever view needed
LEB will continue using Design Structural, TXE will be using the Fab Company model
Scott and I told Stephen P that we need to use the trades actual model now that we are in IFC
I Did mention that I had to pull in Cerris Plumbing for Coordination and HELM Mech pipe seperately from GC folder
They asked about FW alignment at TXE, I told them I matched Cerris and looked at the current Dim sheet, everything looks good
Once HDR model is bridged, I will verify and update the Dim Sheet for LEBNWC
I did sent out LEB1 yesterday with a revision 1 on SK-001 and SK-001B, HDR had like 1 area that was 3/16"
Alex Harper said he will add CIA points for scotts POCs fan to louver, IDF cages
HAC Base plate clashing with MES Plate, they had to increase HAC Base plate, they originally were going to move it, but now they are saying we may need to move 1" into the gallery
NO, they are talking about MES and HAC Base plates, went from 8x8 to 10x10
Waiting for structural engineering to say if they can move hac plate or if we need to mvoe mes skid
Using EOR or trade partner model for IMP Leaveouts
I asked for Tom Chirdon to be invited to this meeting
Since they are going over IFC, IFP issued dates and issues
Once UG is signed off, we will cover Loop Side above ground
1000amBim Round Up
Paul Hernandez
Paul is asking for MES Connector loop spools for near sight, end of april
Told Paul , Tom Schultz, Scott about MES may need to move
1000amLighting TXE Baseplate Clash w/ Piping
John Cowhey, Patrick Brinnehl, Jeff Collins, Adam, Me
Patrick says they could probably move hac support,but he doesn’t want to, lol
Adam says we could probably move MES but he doesn’t want to
We will Move MES, per the meeting
Reengineer MES Anchors
Move MES Skid
Move MES Piping
Move 8" Flex Skid
Reengineer 8" Flush Skid
Move 6" Flush Skid to make room for 8" Flush Skid 90s connectimg to
Helm needs to adjust FW POCs
Cerris needs to adjust UG FW Stubups
Crider and Crider needs to adjust UG FW Stubups
Flush Connector spools need reworked
Duct needs reworked
Adjust access panel locations
GTP Points need updated
Makeup Water piping needs reworked
03/12/26 - THU (+4 Meetings)
605amLEB|BIM Working Session
Joe Dorinsville
Emma Pezza
Thursday Meetings will be for GCs in the future
Tuesday meetings will be for GCs and Trades
Thursdays meetings will be shortened to 1 hour
Jay Davis Asekd about Control points
Turner says they and SPO will be establishing any further Control points
Emma says they will need 2 sets of points for Total Stations and for GPS which are on columns
Temp Gas and Temp power will be removed from Thursday meeting, due to having a meeting Friday for those items
Emma and Luke Jost say to host a dedicated meeting for anchoring, slab penetrations
I told emma LEBNWB was updated by HDR, but we are waiting for bridged model to get updated so I can issue dimensional drawing
LEB1 and LEB2 are overall looking good, there was 1 that was a little off
Joe D confirmed they received our embedd model and submittal for our embeds
John Cowhey says they are checking for FW Stubups in place, Luis is checking with field Teams, if so, definitely not moving MES
He also states • Would like to reassess if moving the MSA post off the edge would be a feasible option – this may have less impact than the MES moving
Adam brought up FW drain on HAC side of msa, no low point drain if we remove eol loop
Tom brought up both rows of FW for fan coils, at end of line, 1 set of rows shouldn't be there. We have covered this, all fan coil models have both rows of piping, even blanks
Tom brought up access to MES riser couplings above the duct, zach says they will use moveable plateform based lifts (Boom lifts?)
900amTXE - Lightning Staff Meeting
Zach Washburn
1000amLEB - BIM Coordination
Ryan Zoldan
Ryan Henderson said he will get with David Eldridge about updating the HDR Mech model for LEBNWB
1100amMunters
Jim Marsh
Submitted to Meta for Review
Need by dates is Jan 2027, Meta tracker file?
Patrick plugged the model in and found 1 the eyeholes didn’t line up and had a cable tray protruding beyhond the frame, pipes werent centered properly, happened after rotating?
Estimated ETA for submittal return from Olsen, Kosuke Kato said he will check
03/13/26 - FRI (+1 Meetings)
700amLEBNWB FW UG POC Meeting
Krunal HDR
We verified everything was good, Helm has 1 Bypass in NW to update.
Now that NWB is finalized, HDR will submit this for IFC
I will go through LEB1 one final time and verify, create a new sheet like SK-003 LEBNWB for LEB1 with all views on it
We will meet again on Friday, 3.20 to finalize LEB1,2
3/2/26 - 3/8/26
03/02/26 - MON (+1 Meetings)
830amTXE Staff Meeting
Zach Washburn, hot topics only today
Adam got some hot items from Mid Atlantic for spool sheets
Look at design for full stainless steel system for Tech water system
moving to ss will be cost effective, but what does supply chain look like
End of month. The stainless valves will be hard to find, source
QA/QC review from Rob Nelson
Get TXE 3,5,6,7 Models going
Get LEB 3,5,6,7 Models going
03/03/26 - TUE (+1 Meetings)
830amLEB - BIM Coordination
Ryan Zoldan
I sent out new Email for LEBNWB showing HDR UG FW pipe is still off
Ryan responded by saying he doesn’t think theres much room to move underground any more due to completing Thermal Scanning with Crider and Crider
Ben Kozel with mortenson says they will need to check to see if they can move if dims are larger than 1/4"
Hector says he will have a break out meeting and bring Mark in
Dustin with Crider wasn’t on, Matt and Bill with Crider was on and didn’t say a fucking word as usual
Ryan admitted we didn't have Crider models for coordination that we used HDRs for LEBNWB
Covered Area 2 which is LEB1 and LEB2
03/04/26 - WED (+3 Meetings)
800amNaviate Office Hour
Cancelled
800amTXE/LEB Weekly Internal Bim
Luis Saldana, Luke Jost, Justin Jenkins
Alex Harpel said he is getting LEB CIA points by end of day and will put on ACC
Adam said he will send LEB Base Buidl Integration at end of week
Adam said he will send Points for Jumpers, FTI-Southland Integration by end of next week for TXE/LEB
Check IFCs for any issues on TXE10,1,2 and LEB10,1,2
It was asked by someone saying Hensel Phelps asked about CIA tolerances, they were told 5", me and adam both said it was 1/8"
Insure current models are distributed? Published on Sat, Design models will be packages and bridged on Mondays, heath says the NWCs are getting bridged as well, are those automatic? Stephen says yes
HDR/ Crider not lined up on LEBNWB UG, Luke said he will ping Ryan and make sure the HDR Breakouts happen, I told everyone this is pretty critical, if the Stub ups are off on underground, how do we line them up to connect to MES?
Helm Not lined up on LEB Above ground
Model Flythroughs?
Clash Issues? I told Luke, I sent them to him
900amBIM Round Up
Michael Kolnik
Cancelled
03/05/26 - THU (+4 Meetings)
605amLEB|BIM Working Session
Joe Dorinsville
I brought up the UG penetrations off at LEB10, Ryan said they are having a breakout meeting with HDR at 1pm Eastern
I brought up the Embeds and they need to be added to the Anchor bolt section of the Job Tracker
Diogo Christo with SPO asked for Embed content
Get Jod D and Diogo premlimary submittals for the embeds and send them our plate RFA
HOW THE FUCK ARE JOHN AND BRENT NOT IN THIS FUCKING MEETING?!!!!
800amLightning TXE Staff Meeting
Michael Kolnik
Deep dive on submittals, lots of things have changed
Get with Adam on uploading BOM/Spools to Stratus for TXE
The packages were created and have been approvded for purchasing but no sheets
Detailing needs to upload spool sheets, etc?
Send Thomas the RO Spec sheet for the skid I made based of of Culligan Spec sheet
Adam supposed to get with Paul/Jeremy/ Thomas to finalize the fill flush manifold
Adam work on TW Header Stainless design
1000amLEB BIM Coordination Meeting
Ryan Zoldan
Hector says they are still looking at it
Ryan shows that 10/23 isnt on the column line any more, it is 20' between 10/23 - 10/24 and FWS is 9 - 0 7/8" off 10/23
I have looked at archs and structurs for LEB10 CS Fitout IFCs and they show 19' between 10/23-10/24 and 10/23 is centered on the column in the aisle
Sent Ryan a message in LEB-BIM Coordination chat
He said it looks like I am correct, he is checking where they are getting their Grid Lines
1100amMunters
Jim Marsh and Patrick Brinnehl
submittal to meta end of this week with drip pan modifications
model will be made available to Patrick
Meta said they will be looking at the submittal to get it finalized
03/06/26 - FRI (+1 Meetings)
715amHDR LEBNWB FW UG Cooridnation meeting
HDR will update their model early next week
Once they do, SI will verify and move any thing to match, then reissue dimension drawing
HELM, Crider, Turner and Mortension will use dimension drawing to move and verify
2/23/26 - 3/1/26
02/23/26 - MON (+1 Meetings)
900AMLIGHTNING TXE STAFF MEETING
Zach Washburn
WE NEED TO RESUBMIT MSA AND HAC SPOOLS FOR IFC APPROVAL PER ZACH
Zach says what we have in the model is what we are going with for Critical dimension drawings for FTI-SI CCIA, pipe connections between MES Loops and MES, HAC, etc
02/24/26 - TUE (+4 Meetings)
830AMLEB-BIM COORDINATION
RYAN ZOLDAN
DIDN’T COVER ANYTHING THAT PERTAINED TO US
930AMTXE/LEB/SOUTHLAND MECH
JOSH PIRKL
CIA HAS BEEN GIVIN TO FTI, THEY ARE SUBMITTING TO STANTEC
PER ZACH TO JOSH PIRKL AT STANTEC
MAKEUP AIR DUCT INSULATION
WAITING ON META ANALYSIS
TOM SAID HE PROVIDED INFO TO KEVIN TO PUT IN THEIR CDD HASN’T HEARD ANYTHING BACK
JACEE SCHMIDT
FWM WORKING WITH PURGE RIGHT TO MAKE SURE IT GETS FLUSH PROPERLY AND WANT INPUT FROM SOUTHLAND
REFERRED TO THEIR PRELIM SUBMITTAL AND WANTED TO KNOW ABOUT SECTIONS OF PIPING OR SYSTEMS THAT PURGERIGHT EXCLUDED FROM THEIR PROPOSAL
JACEE SMITH WITH CERRIS SAYS THE FWM IS BEING PROVIDED BY SOUTHLAND
ROBAINA WITH HENSEL PHELPS IS LOOKING THROUGH MOFE LOG TO SEE WHERE ITS COMING FROM
THE TRACKER SAYS TBD
ZACH REACHED OUT TO THE PROGRAM TEAM FROM SOUTHLAND THEY SAY WE ARE PROVIDING THE FWM
SAYS HE WILL ADD HIM TO CALL NEXT WEEK
ROBAINA DID CONTACT THE MOFE TEAM AND THEY ARE ALREADY HAVING MEETINGS WITH SOUTHLAND ON THE FWM
SHE WILL GET ZACH INVITE
10amLightning-Eng-Coord Huddle
Tom Chirdon
Tom asked about the Detailing schedule, should Ryan with HRV be paying attention to the schedule
Adam did say yes, he needs dates for deliverables
sam with David pickett at EMT
Will also need the CIA for both projects
Adam said he does need to resubmit the packages for the MSA and FSHAC for IFC and given to Zach to submit to Faith, Tom wants a look before they submit
Told Tom I need to be spending more time looking at clashes and clearing or creating issues for them
Adam said Patrick Brinnehl stated they will be moving the panel that is clashing with our MSA to HAC coupling
Adam said he has LEB10 and 1 ready to submit this week for CIA, TXE he gave to Zach
Tom and Diana working on Revise and Resubmit for LEB Embeds
1130amMW Detailing Touch Base
Marshall Cancelled
02/25/26 - WED (+1 Meetings)
800AMLEB/TXE WEEKLY INTERNAL BIM COORDINATION
LUKE JOST
SCOTT BROUGHT UP SOME CLASH ISSUE AT LEB
I mentioned the Publish/ Bridge issues last week with HDR
Ron and Melanie asked for ACC items
Alec Harpel said he was supposed to get CIA from Zach
02/26/26 - THU (+3 Meetings)
600amLEB|BIM Working Session
Joe Dorinsville, Emma Pezza
I didn't get a reminder and missed the meeting
Didn't see any updates in the chat for started recording, end recording or any chat, did the meeting happen or change?
800amLightning TXE Staff Meeting
Zach Washburn
1100amMunters
Jim Marsh
Micahel said they had to bend the drain pan down to install coupling at FOK, asked if they could ship loose, no, due to water detector being attached and wired
The power panel on the other end is very close to pipe will be tough to install couplings and pup pieces, they cant center it due to sprinkler line in the middle
Munters wants ok from meeting to send submittals to Meta
The cross bar for siesmic and drain pan support will be removable
2/16/26 - 2/22/26
02/17/26 - TUE (+1 Meetings)
830amLEB-Bim Coordination
Ryan
AREA 1 FRIDAY SIGN OFF
RYAN VERIFIED HDR MATCHED THE 6-1 5/8" AND WILL HAVE CRIDER MATCH HDR
DUSTIN WITH CRIDER SAID THEY WILL MATCH HDR
EMBEDS?
CONCRETE IS DONE THROUGH TURNER
02/18/26 - WED (+2 Meetings)
800AMNAVIATE OFFICE HOUR
derrick has settings configured for adv number in 3.11.2, we hae
he says there is a bug with the check boxes in the beta
derrick did a walkthrough of the adv renumber using his settings with pipe lengths first
use sequence instead of chainging, huge improvement
900amTXE BIM ROUNDUP
Jacob G asked about a bom for valve count since hes looking at valve tagging
Zach asked why, he said just start at MSA then work down an isle and number them
Jacob and I both thought the failure domain would have a unique identifier, zach said no
Zach said get with stefan, he worked extensively on valve tagging so would know about identifying
02/19/26 - THU (+5 Meetings)
605AMLEB | BIM WORKING SESSION
Emma Pezza, Turner
Check on LEB Wall misalignment, Joe Dorinsville says the RFI was submitted and it has been closed, RFI 55, was told wall cannot move yesterday, they looked at log, it says embed will be under partition, but it’s a fire rated wall
Told Emma and Kashal about resubmit on embedd
Kushal asked Justin Jenkins about the CIA doc, he said Luke is out and hes the one handeling that
800amLIGHTNING TXE STAFF MEETING
Zach Washburn
Coupling in HAC Panel, FTI is moving panel inside the frame per
Embed Submittal in our court, revise and resubmit
Adam said he will have answer on eng review drawings tomorrow, zach wants ok to start fabrication
PVF was sent to Adam, he will look over tomorrow
Gaskets werent on Tech Water spools
Curtis said yesterday he was going to get with zach about using stratus to track spools/skids
move flush skids into container model
1000amLEB-BIM COORDINATION
RYAN ZOLDAN
No one was available when I asked about leb6 and 7, Ryan verified we are still coordinating LEB1. HDR may have wanted to get ahead due to the lowering of footers and zone of influences.
Ryan Henderson said forward him the email and he will verify info
1100AMFTI - MUNTERS/TRANE
PATRICK BRINNEHL
1200PMLEB Weekly VDC/BIM EOR, GC and Integrator Coordination Meeting
David Eldridge HDR
It was agreed HDR will use design models for their own coordination, not the field models
Justin agreed to push bridged models weekly on mondays
2/9/26 - 2/15/26
02/09/26 - MON (+2 Meetings)
700amCurtis/Stefan
Curtis said he ordered a 12' piece of flex for main line flush skid, not sure why when the spool sheet says 9-8
Since its 15 weeks out we have to adjust the spool to use that flex along with 2 pup pieces that are AGS x OGS grooved with OGS couplings
Need to spool the other flex and any other connecting pipes and fittings to flush skid
800amTXE - Staff meeting
Zach Washburn
Zach says he is going to make Adam 100% to Lightning
Need cush clamp submittal info for TW Headers
Air vent submittals
Chain valves submittals
Vic gasket submittals
Zach says no to verifying points, will rely on scans to verify
Zach says we need to pull critical pipe measurements from rack, need a shop drawing
I Brought up lead times and project boms
Adam says once we get things finalized, we can get them a new project bom
Zach says he doesn't know about a couple weeks
02/10/26 - TUE (+4 Meetings)
830amLEB-Bim Coordination
Ryan
Ryan asked if HDR matched our doc, I said I havent had a chance to verify yet, he asked Hector and he said they have an engineer dedicated to it, he believes they are but will verify
Ryan said once its verified, he will give crider and crider the thumbs up to match with their model
900amMountain West Operations
930amTXE/LEB/Southland Mech
Faith Josh Pirkl
Josh talked about disbanding this meeting feeling everything is covered
Zach kind of agreed
Adam went over CIA
Tom said he didn't think it was an actual contract doc, it was for Meta
Josh said Sebastian wanted this
They are trying to figure out where to put it
Tom C said he thinks it’s a good idea to keep the meeting going, Josh agreed
1000amLightning Eng Coord Huddle
Tom C
Ryan will be managing HRV
Tom gave an introduction of people for Ryan
02/11/26 - WED (+2 Meetings)
800amTXE/LEB Weekly Internal BIM Coordination
Faith Luke Jost
Faith Alec Herpel
Faith Justin Jenkins
900amBim Roundup
Paul Hernandez
Jeremy Miller
Look at hard piping RO to column/ wall
Create a cart for fill manifold, draw hoses, place throughout building
Adam brought up Coupling inside panel. FW We can extend pup piece, Tech water is spooled with full lengths on inside, cant cut
02/12/26 - THU (+4 Meetings)
600amLEB|BIM Working Session
Emma Pezza, Turner
I told Kaushal Bagdekar that the embed submittals were submitted to faith, they were looking for Structural EOR signoff
Luke/Justin with FTI said they will follow up
I Told him Ryan was verifying locaiton with HDR and then going to give Crider ok to match locations
Kaushal was asking about flange elevations
Ryan came on later saying they should have updated the model, the model was still inaccurate, he will get with them
Turner/ EMMA and Kaushal asked about CIA, Faith said they can give info on the CIA
they can share the template to show the format
Luke Jost said he will share what they have
Luke says Mechanical underground is the hot spot
EMMA says she will start assigning issues in clashing, check acc regularly
Get Underground Views published
Dan and Helm team get underground views published
Kasuhel was looking for model status on LEB10
The model they have in the bridged folder are good enough to be included in the container file? Luke/Justin says yes
800amLightning TXE Staff Meeting
Zach Washburn
Zach said he wants to get Adam out of the doing mode
Scott took over the meeting to talk about ACC structure
10amLEB-BIM Coordination
Ryan Zoldan
Richard with HDR said he has verified LEB1 is matching Southland will verify LEB2 today
I checked LEB1, not updated as of yet. May have to wait til HDR is published
11amMunters/ Trane
Patrick Brinnehl
Jim Marsh says early next week for new submittal and model will follow
2/2/26 - 2/8/26
02/03/26 - TUE (+2 Meetings)
830amLEB-BIM Coordination
Ryan Zoldan
Mortenson is back to NWB to finalize some RFIs
Currently coordinating Area 2, 3 weeks from yesterday for clash detection
LEB2 Feb3-March16
Survey Control Point map?
Thursday will disperse a control point map
Richard Lopez will send it out
Dustin with Crider says they will get modeled inside building this week. Ryan will work with FTI and get the right models so Crider can view them in their model
10amLightning-Eng-Coord Huddle
Tom C
Zach said they FTI sent over a quesiton on Critical layout for POC on the MSA to Adam
LEB 1,2,6,7 IFP going out Friday
TOM Emailed out his Tracker
02/04/26 - WED (+3 Meetings)
8amTXE/LEB Weekly Internal BIM
Luis Saldona, FTI
Need Control Points
Richard said he will give out version 1 in chat yesterday, version 2 will be released Thursday
The ones from Richard are site plan CPs, we need building CPs, perferably 10 around each building
Weekly meeting with Turner, Joe Dorinsville and Emma Pezza for LEB1,2,10
Not showing any reoccurance
HDR Underground Models need to be made available, Crider doesn’t have and they arent available from the Coordination Module
Clashes, couplings on pipes are showing as clashes
Flush skids inside MES Access shows as clash
Access to Architecturals
Alex Herpel says CIA has ug locations, starting this afternoon on Skids
Will there be a control point map
LUKE said Pat and david, says they are working it
Thomas says shouldn’t that be a formal request to the GC?
Justin Jenkins says they don't ask for that, lol
LUKE says he will see what the meeting shows on Thursday with Mortenson
Justin Jenkins says he will check with Turner for a weekly recurring meeting
Melanie asked Justin how they are doing the MES Skis
9amBim Roundup
Michael Kolnick
Full production in march, fok in february
Michael says we have time to see if the couplings in the panel work before changing the MSA
Use quick vics on copper, no other option
Quick connection is being made into items, construction was right, but model showed a 1x1-1/4" male adapter which was wrong
Justin jenkins says we should be the ones doing points on MES, adam says they set it, they own the points
Will need to create a new model with MES, TWMU skids and Flush skids with individual parts so we can put through Stratus
Duante says need points at any and all pocs for GTP and CIA
Scott went over using collections for prints
Adam says need to get Heath and team to make the NWF/NWDs
Adam says we need to get an LEB BIM Round up
11amHAC Follow Up
Ryan Boleen
I missed meeting, I was invited at 1118am
02/05/26 - THU (+5 Meetings)
6amLightning Skids Overview
Melanie
I cancelled due to new meeting with LEB|BIM at 6am
6amLEB|BIM Working Session
Joe Dorsinville Turner, Emma Pezza Turner
LEB10 - Need to make sure everyone has the Imbed shop drawings, submittals to Geo and maggie for concrete lift
Ryan Zoldan said once HDR finalized moving their UG stub ups, Crider will match
FTI dude was asking for a Navis model so they can get skid points for the CIA
10amLEB-Bim Coordination
Ryan Zoland
Sign off is Feb 20th for LEB1
Ryan said they will be getting updated Control Points today, I will touch base with Richard
10amTow Hall
CEO Ted Lynch
11amFTI/ Munters for TXE
Patrick Brinnehl
New submittal date?
02/06/26 - FRI (+1 Meetings)
830amBim Roundup
Paul Hernandex JR
Need shop drawings using MES as control
Draw sheet for plan north
Draw sheet for plan south
They will give manifold for DCW connections
We may need to add RO port connections on middle end loop for RO connection to TW Piping
They are looking to creating manifold from 3" DCW to RO Skids, may have to include a Backflow, Paul wants hard pipe
Adam helped Jeremy install Desktop connector and view NWDs from freedom works
Fan Coil Submittals
1/26/26 - 2/1/26
01/26/26 - MON (+1 Meetings)
8amLightning TXE Staff Meeting
Zach Washburn
Get flex couplings replaced with Rigid couplings, adam is taking care of
Everything FOK goes through chad vernell
Makeup Water Piping matches to PNID
TW Headers need spooled
Lois Soldanos did send Lightning coordination meeting sent out, but only adam got it
Need shop drawings made of POC to MES off rack, grids
Mid atlantic is getting busy on the MSA, need to verify info
Adam will send a sternly written email that no fab is to be started completed unless it goes through him
Zach says LEB is not doing a staff meeting
Talk to Brent if there are issues that are LEB specific
Need to submit our shop drawings to tom
Starting FOK on the 17th of Feb
Jacob wants a checklist finalized on Feb 9th
Adam says Zach still has not got with him for Detailing Deliverables
01/27/26 - TUE (+2 Meetings)
8amLEB-BIM Coord Meeting
Ryan Zoldan
10amLightning-Eng Coordination
Tom C
Shop drawing dates determined by zach and field
Need to create dim sheet for MOFE equipment
Track and log clashes
Interface agreement meeting on Thursday at 11, I asked adam for attendance
Go over LEB1 POCs
MES Model, still waiting for final owner approved version
FOK, need info as far as progress, viability, lessons learned
Need to clean up spool models
Something was wrong with MSA piping, adam is waiting on red lines so we can fix
Need rigid couplings added to database, Ronald will find out who can do this
Adam told vince we need to touch batch with Stratus workflow and start batching
Vince, Todd, Ron
Do they package their own spools? Ron says we will send spools, they build, package and distribute
Ron said he is going to try to get all other trades to match grids
Single source of truth is the Datum
01/29/26 - THU (+6 Meetings)
615amLEB|BIM Working Session
Joe Dorsinville TCCO
Tuesday Coordination Call? Went over FW connection points
Matt with Crider is looking to RFI coming up full size 18" and having full size 18" Bypass
Need plates drawn in for the Anchor Embeds
Adam said he will get the embeds drawn in
Diogo Christo asked to be included due to concrete
Need to remove Extra floating Fittings
Adam brought up wall difference between Data hall middle left to middle right, side of anchor is hitting plan north wall on left side not right side
Duct work is clashing with girders and steel up above
Joe Fiera with Helm is looking to coordinate duct with scott
Joe with Helm is doing Ductwork and air handlers
Crider is doing ug stub ups, Helm is doing the bypass
Helm is with Turner, Crider is with Mortensen
Emma is Turner leading LEBNWB and LEB1,2
Joe is Turner leading LEB10
Ruben has an updated org chart for LEB Turner
Contacts are availabel for Turner in ACC, I asked for invite for us
7amLEB|BIM Working Session
Emma Pezza, Turner
Asked Elec to get the model populated for LEB NWB, 1, 2
Separate coordination calls for LEBNWB and LEB1, we need invites
Get Brent invited
Joe asked for printed model for next Thursday
Holman Lance asked for FTI model for coordinating flange?
8amLightning TXE Staff Meeting
From Mon meeting
From Mon meeting
From Mon meeting
From Mon meeting
From Mon meeting
From Mon meeting
From Mon meeting
Ummm not until spooling complete? Proper order of things?
NEED TO BRING UP
NEED TO BRING UP
NEED TO BRING UP
Go over schedules, install dates, coordination issues
NEED TO BRING UP
NEED TO BRING UP
Zach verified that FTI will be doing pup pieces between Fan Coils, not us
he will get with patrcik brinnehl to get pup pieces installed on 1 side
Adked adam about stratus and todd, instead of having 16 models, do 1 and add in views
Wee need to develop assemblies and packages
We will batch and spool and package
Zach mentioned getting Adam out of detailing and more in lead
Need to get Redline dims into model and update MSA
They want to build ASAP and verify
Adam said end of day Monday
Adama brought up MSA ss valves using 107 quick vic, replace with 07 rigids due to leaks at cable between ss valves and 107 quck vic couplings
Adam gave zach BOM per failure domain
Zach and Michael mentioned drains on EOL bypass loops, we don’t show anything
Actually they are there on FW loops
8amTXE-Staff Meeting
From Mon meeting
From Mon meeting
From Mon meeting
From Mon meeting
From Mon meeting
From Mon meeting
From Mon meeting
Ummm not until spooling complete? Proper order of things?
NEED TO BRING UP
NEED TO BRING UP
NEED TO BRING UP
Go over schedules, install dates, coordination issues
NEED TO BRING UP
Zach verified that FTI will be doing pup pieces between Fan Coils, not us
he will get with patrcik brinnehl to get pup pieces installed on 1 side
Asked adam about stratus and todd, instead of having 16 models, do 1 and add in views
Wee need to develop assemblies and packages
We will batch and spool and package
Zach mentioned getting Adam out of detailing and more in lead
Need to get Redline dims into model and update MSA
They want to build ASAP and verify
Adam said end of day Monday
Adama brought up MSA ss valves using 107 quick vic, replace with 07 rigids due to leaks at cable between ss valves and 107 quck vic couplings
Adam gave zach BOM per failure domain
Zach and Michael mentioned drains on EOL bypass loops, we don’t show anything
Actually they are there on FW loops
FOK is on HOLD, don't fly there, don’t go, its on hold per Zach
NWFs and NWDs have been updated today
Adam says he need to follow up with Faith for POC connections to MES off rack/grids
Individual spool drawings - adam says tracking, waiting on submittals for quick connect adapts and if 606 couplings will be able to made
Will get with Zach later this week
Michael is trying to dig them up
Thomas Shulz said he will get submittals updated on ACC
2 weeks away from FOK
Redlines from MSA, Adam said he will get measurements updated
Someone on Zachs speaker said insualtion is not needed. Zach asked if there was an RFI
Zach put RFI was answered and insultaion not needed on project tracker
ASBUILT and Shop drawings for EOR approval
Adam says he needs to get with BIM, Zach says before submittal we need to get them finalized
Onsite scope shop drawings? Waiting for couplings to get updated
We are tagging the HAC
Mid Atlantic is tagging the MSA
Adam gave Zach a tour of One note and line items were going through
17,18,19th pit stop will not happen for FOK
10amLEB-BIM Coordination meeting
Ryan Zoldan
I brought up the proposed locations for LEB1 ug connections and they all agreed that I can model them in to help to make sure they are good
Hector agreed that would help them verify and approve
11AMMunters FC
Jim Marsh with Munters
Patrick Brinnehl
Couplings hitting fan coil case
Model shows open panels around pipes
Clashes with couplings look more like clashes with HAC Frame then fan coils
Check both end couplings and middle couplings
Jim marsh said they are looking at zero tolerances for horizontal and 1/8" veritcal
Will be on next submitall update
1/19/26 - 1/25/26
01/20/26 - TUE (+4 Meetings)
8amLEB-BIM Coordination
LEB1 Modeling Jan 12-Feb 20
10amLightning Eng Coord Huddle
Specs sent out
MES Prints updated from MERC on 1/15/26
Do they have a finallized model avail?
Have meetings tonight and tomorrow with FTI, cover Coordination, models
1130 amMW Detailer Touchbase
Jim Brown went over the recent files list in Revit before you actually open a project
100pmSouthland and FTI CEP part 2
They will put a view together with other trades and their models for us to use to fly
They will have the LEB Model Coordination available within an hour
They will be having 1 meetings on Wednesday for an hour to cover TXE and LEB
They will send out the doc that has all this info laid out including contacts and publishing workflows
01/21/26 - WED (+1 Meetings)
800amLightning SI/FTI Coordination
Tia Giovanni, Patrick Brinnehl, Justin Jenkins, Jeff, Adam
Lois is supposed to be sending out invite for Wed Coord meeting
Stephen Primethal will be enabling the LEB Model Coordination module this week
We will host the spool model, hopefully 1 model that we can link into each project building model
Me and Adam talked, each Project and building type will need its own spool model
Heath will make Blank spool models for each project/ building type and we will copy in txe1 then delete whats not needed
We will then link in those spool models to our coordinated model for each Project/ Building type
01/22/26 - THU (+3 Meetings)
8amLightning TXE Staff Meeting
Zach Washburn
Zach said we are only providing 1 failure domain of spools, the fab shops will track quantities on their own, per zach, then zach says we need to talk to them
Adam was added to Fabrication meeting
Noel, went over some safety things
10amLEB-Bim Coordination
Ryan Zoland
I brought up the relocation of FW UG to the proposed locations, Ryan and Amy said we will see what HDR and Crider can do
1130am- MUNTERS/ Trane
Patrick Brinnehl
Patrick has rev 0.f submittal from sep 21st
Munters say Rev 1 submittal by Monday, need Meta approval
Need to verify PIPE and Frame dims and tolerances
Munters is tracking 2.0.6 for the centerlines for connections
zach asked for tolerances, munters said 1/4", centerlines are 1/8" with adj brackets that can be made to fit
FTI is mounting the FC to the FSHAC, Patrick showed up to date drawing for Munters
Munters will send the model to patrick along with tube spec so FTI knows how they will secure unit to frame
Patrick said they are currently building a FOK (WHATTT?!!!!)
Adam says they may switch to munters due to availability
Jim Marsh says they have an updated drawing with revisions based off all the comments from previous drawings/meetings
Patrick needs operational and dry weight
They show est 2400 lbs on submitall, They said may be dry weight
1/12/26 - 1/18/26
01/12/26 - MON (+1 Meetings)
800amTXE Staff Meeting by Zach
Jeff - Need to ask about FC submittals, we need to verify POC's or use randoms which the spool sheets currently do not have
Talk to Eric Boherengir about submittals, Bargaehr, Eric [email protected]
Adam - Do we need to submit shop drawing to Southland EOR for approval
packaging on stratus yes once the model is complete, spooling is complete
we need to get with NW, Ryan/ Phil and go over spool sheet info, header info and relaying proper info to accelerate
TWMU Matching PNIDs, still have to verify
01/13/26 - TUE (+5 Meetings)
800amLEB - BIM Coordination Meeting
900amMW Operations Meeting
930amTXE/LEB/Southland Mech, Adam invited me to listen in, every 2 weeks
1000amLightning Eng Coord Huddle
MES Spec submittal, RVT Model? I found some in SI TXE Proposal Area dated 7/3/25, shows 2-1/2" TWR pipe in copper
TWMU Spec submittal, location, RVT Model?
Adam - Do we need to submit shop drawings to EOR (Submittals)?
TOM is going through specs, will send out, will be send for both sets, will check in specs for shop drawings, 1/4" scale
Scott Hyjacked the meeting, he needs to follow IFP
1130amMW Detailer Touchbase
Mayo Hospital bid going out next week
More data center work in the area
More amazon work
The lightning scope starting core and sheel at Eagle Mountain campus next week
Holiday on Monday
Tips and Tricks, Dave Alleman, Temporary View Properties
01/14/26 - WED (+4 Meetings)
700amDid a quick meeting with Jay, Paul, Michael, Thomas, Scott and Adam
Talked about FOK, couplings for TWMU, Design stage/ Construction Stage, who is spear heading this abomination
800amAdditional Naviate Office hour
Didn’t attend but they are covering export points and recording the meeting
800amFTI/ Novenco Meeting by Patrick Brinnehl
john Gowey and Ben Brokowski will be heading this off from now on
Hans, Torbin with Novenco asking about where to route their power cable
11/21/25 was Rev 2.0.5, waiting on 2.0.6, Hans with Novenco said he will find info
The RFA was 12/09, Hans verified this was the lastest model, on their ACC
Patrick needs dry and wet weights
I got links to prelim submittals on Meta Lightning ACC, but it says no access
stefan asked about pipe length tolerances, was told no tolerances in CDDs
Hans said he will add a tolerance to submittal
MPK told Novenco the pipes need to be exact to dims detailed in the CDD
will cover more in next meeting to go over CDDs
900amFTI TW Headers
FTI wants 16 different skews/spools for the TW Headers
Mario Sze with faith was
meeting with John, ryan said this is what came of it
Ryan has an idea of how to do this
John Cowly, Nate Bogs, Jewels Perez, Chad were in meeting last week where it was said they needed 16 skews
Mario said he wants to talk to them before proceeding with the splitting spools
Ryan said he still needs spools split apart for him, lol
1/5/26 - 1/11/26
01/05/26 - MON (+1 Meetings)
800amTXE Staff Meeting
I need to verify HAC EOLs PNIDs show HACs not even some valves are offset more to center of building but model shows all even with all EOLs on the outside
Based on Lightning IFP mech plans 11/26/15, M120-1-10-L, whats in revit is what is on plans
Talked with Adam, he mentioned since units are connected to each other, there are pipes on both sides of units, they have to continue out the end so both flush loops will be at the ends of the row, not staggered as shown in Mech Pipe IFPs
Sent email to Zach, Michael and Jay
Split out TW Header spools, 1 pipe spool on 1 sheet for accelerate, 2-3 weeks
Verify MUW Piping matches PNID
BOMs are good according to Michael
POCs are good, just sent updated out today
I brought the gaps between top loop and hac piping and the valves half in half out
Zach said they are not spooled yet
01/06/26 - TUE (+2 Meetings)
800amLEB-BIM Coordination
Ryan Zoldan, didn't cover anything that affected us
1000amLightning ENG-Coord Huddle
Tom C, keeps notes and emails summary, Very NICE!
01/08/26 - THU (+1 Meetings)
1000amLEB-BIM Coordination
Ryan Zoldan, today is supposed to be sign off date
pushed off til the 15th
12/22/25 - 12/28/25
12/22/25 - MON (+1 Meetings)
800amTXE Staff Meeting
Jay wants to remove the pup piece on the MES TW Supply that’s dead ended, Zach agreed
Said to get with Phil to see if there are any issues with deleting it
Detailing deliveries, Zach says him and Adam will touch base either today or tomorrow
Michael K needs a navis model to look at
steven konoff is the PM for MES Fab down there, MERC?
12/23/25 - TUE (+1 Meetings)
800amLEB - BIM Coordination Meeting
Abbey Mumford
Did everyone get to look at addendum set that was published Friday, 12/19/25
Ryan Zolan
Tues 10am, Lightning Eng Huddle
Need to have another meeting about Coordination with Patrick and Justin
12/1/25 - 12/7/25
12/02/25 - TUE (+1 Meetings)
800amLightning-Eng Coord Huddle
Duct work needs completed, to be completed by SI team
Scott said he was behind and will need to jump on the update
Zach provided a date of end of december
Zach is looking for Fabrication drawings
Zach says Adam is the Program Detailing Lead for all Lightning Projects
We need TW header spools
Phil FOK is in the in the hands of NW shop
Phil says he will complete spools today
Except the 4" pup for FCM and 40' jumpers
I just got access to Southland ACC Project files for Lightning
Need to publish to stratus, phil says he doesn’t know anything about stratus
Heath says we need to publish to GC hub
FTI owns the placement of the hac, we will need to spool the connections
Phil says we cant do spools until they set the equipment, we need something to measure off of
FOK headers for FC Water headers are going to be different than production headers
UMP, NOVEMCO headers? WTF?
We need to verify POC's
We havent received submittals from them for POC's
TXE and LEB are each using different brands
Phil says we are responsible for connections to FW for FOK
Need an approved submittal that shows the spool changes that phil did in the model based off ?
MERC was originally doing Duct attached to MES, but they pulled it out of their scope so now we are doing it out of vegas, per Zach
Tom Chirdon brought up breaking out coordination models from eng models
Schedule talk for later this week
Zach talked about filling out the Project Dashboard so we know what deliverables are needed and when
3/24/25 - 3/30/25
03/26/25 - WED (+3 Meetings)
600amLEB|BIM Working Session
Emma Pezza, Joe Dorinsville
Missed meeting due to not being able to logon to VDC, took IT 4.5 hours to respond and fix
1000amLEB|BIM Coordination Meeting
Ryan Zoland, Richard Lopez
1100amTXE Coordination
Kyle Cummings
Add Meeting
Copy Meeting Into This Day
Copies the meeting with its time, title, host, link, and all notes.
Copy Last Week's Meetings
Creates a Mon–Sun week from the template and pulls notes forward
from the previous week by matching meeting titles.
Delete Week
This permanently deletes all days, meetings, and notes for that week.
Copy Notes From
Copies that meeting's notes into this one (adds to any existing notes).